Modernisation and extension of the wastewater treatment plant in the municipality of Tylmanowa and the extension of the sewerage network in the municipality of Voluntary Lower Hall (Q112688): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): In the context of the project, the following activities are planned: activity 1 Modernisation and construction of waste water treatment plants in Tirmanowa, installation and replacement of equipment for plant with improved efficiency and fitness, including mechanical waste water treatment facilities, sewage sludge drainage and installation and implementation of a modern control system for the plant, by the extension of existing tanks and insta...)
(‎Created claim: summary (P836): As part of the project, the following activities are planned:Task 1 Modernisation and Expansion of the sewage treatment plant in Tylmanowa assembling and replacing equipment with higher efficiency and efficiency, including mechanical sewage treatment equipment, sewage drainage and installation and installation and implementation of modern treatment control system, through expansion of existing tanks and installation of additional technological e...)
Property / summary
 
As part of the project, the following activities are planned:Task 1 Modernisation and Expansion of the sewage treatment plant in Tylmanowa assembling and replacing equipment with higher efficiency and efficiency, including mechanical sewage treatment equipment, sewage drainage and installation and installation and implementation of modern treatment control system, through expansion of existing tanks and installation of additional technological equipment. (English)
Property / summary: As part of the project, the following activities are planned:Task 1 Modernisation and Expansion of the sewage treatment plant in Tylmanowa assembling and replacing equipment with higher efficiency and efficiency, including mechanical sewage treatment equipment, sewage drainage and installation and installation and implementation of modern treatment control system, through expansion of existing tanks and installation of additional technological equipment. (English) / rank
 
Normal rank
Property / summary: As part of the project, the following activities are planned:Task 1 Modernisation and Expansion of the sewage treatment plant in Tylmanowa assembling and replacing equipment with higher efficiency and efficiency, including mechanical sewage treatment equipment, sewage drainage and installation and installation and implementation of modern treatment control system, through expansion of existing tanks and installation of additional technological equipment. (English) / qualifier
 
point in time: 20 October 2020
Timestamp+2020-10-20T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 12:40, 20 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Modernisation and extension of the wastewater treatment plant in the municipality of Tylmanowa and the extension of the sewerage network in the municipality of Voluntary Lower Hall
Project in Poland financed by DG Regio

    Statements

    0 references
    5,168,494.53 zloty
    0 references
    1,240,438.69 Euro
    13 January 2020
    0 references
    7,015,738.51 zloty
    0 references
    1,683,777.24 Euro
    13 January 2020
    0 references
    73.67 percent
    0 references
    3 October 2017
    0 references
    30 September 2020
    0 references
    GMINA OCHOTNICA DOLNA
    0 references
    W ramach realizacji projektu planuje się następujące działania:Zadanie 1 Modernizacja i Rozbudowa oczyszczalni ścieków w Tylmanowej montaż i wymiana urządzeń na urządzenia o większej wydajności i sprawności, min. urządzenia do mechanicznego oczyszczania ścieków, odwadniania osadów ściekowych oraz montaż i wdrożenie nowoczesnego układu sterowania pracą oczyszczalni, poprzez rozbudowę istniejących zbiorników i montaż dodatkowych urządzeń technologicznychZadanie 2 Budowa kanalizacji sanitarnej w Ochotnicy Dolnej Etap V Zadanie 3 Wydatki związane z obsługą projektu Zadania 4 Budowa kanalizacji sanitarnej w Ochotnicy Górnej Etap III, część 2 (Polish)
    0 references
    As part of the project, the following activities are planned:Task 1 Modernisation and Expansion of the sewage treatment plant in Tylmanowa assembling and replacing equipment with higher efficiency and efficiency, including mechanical sewage treatment equipment, sewage drainage and installation and installation and implementation of modern treatment control system, through expansion of existing tanks and installation of additional technological equipment. (English)
    20 October 2020
    0 references

    Identifiers

    RPMP.05.03.02-12-0054/17
    0 references