Construction of a 600kWp photovoltaic power plant in the village of Połski Stare, gm. Piszczac (Q104829): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The project involves the construction of a 600kWp photovoltaic power plant in the village of Połski Stare, on plot No 737/14, gm. Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in the village of Połski Stare. In the investment in question, solar photovoltaic is converted into electricity generation from a renewable source. The electricity gener...) |
(Created claim: summary (P836): The project includes the construction of a 600 kWp photovoltaic power plant in Połoski Stare, on plot No. 737/14, Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in Połoski Stare. In this investment – photovoltaic cells, solar radiation is converted into electricity – the generation of electricity from a renewable source. The electricity produced...) |
||||||||||||||
Property / summary | |||||||||||||||
The project includes the construction of a 600 kWp photovoltaic power plant in Połoski Stare, on plot No. 737/14, Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in Połoski Stare. In this investment – photovoltaic cells, solar radiation is converted into electricity – the generation of electricity from a renewable source. The electricity produced will be sold to the professional energy network. The following indicators will be achieved through the implementation of the project: Product – Additional renewable electricity generation capacity (MWe) – 0,6; Additional generation capacity from renewable sources (MW) – 0,6; Number of enterprises receiving support – 1; Number of RES energy conversion units built – 1 and REZULTATU – Manufacture of electricity from newly built/new RES installations (MWhe/year) – 577; Estimated annual decrease in greenhouse gas emissions (tonnes of CO2/year equivalent) – 191.7256; Electricity production from newly built RES installations (MWhe/year) – 577. (English) | |||||||||||||||
Property / summary: The project includes the construction of a 600 kWp photovoltaic power plant in Połoski Stare, on plot No. 737/14, Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in Połoski Stare. In this investment – photovoltaic cells, solar radiation is converted into electricity – the generation of electricity from a renewable source. The electricity produced will be sold to the professional energy network. The following indicators will be achieved through the implementation of the project: Product – Additional renewable electricity generation capacity (MWe) – 0,6; Additional generation capacity from renewable sources (MW) – 0,6; Number of enterprises receiving support – 1; Number of RES energy conversion units built – 1 and REZULTATU – Manufacture of electricity from newly built/new RES installations (MWhe/year) – 577; Estimated annual decrease in greenhouse gas emissions (tonnes of CO2/year equivalent) – 191.7256; Electricity production from newly built RES installations (MWhe/year) – 577. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project includes the construction of a 600 kWp photovoltaic power plant in Połoski Stare, on plot No. 737/14, Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in Połoski Stare. In this investment – photovoltaic cells, solar radiation is converted into electricity – the generation of electricity from a renewable source. The electricity produced will be sold to the professional energy network. The following indicators will be achieved through the implementation of the project: Product – Additional renewable electricity generation capacity (MWe) – 0,6; Additional generation capacity from renewable sources (MW) – 0,6; Number of enterprises receiving support – 1; Number of RES energy conversion units built – 1 and REZULTATU – Manufacture of electricity from newly built/new RES installations (MWhe/year) – 577; Estimated annual decrease in greenhouse gas emissions (tonnes of CO2/year equivalent) – 191.7256; Electricity production from newly built RES installations (MWhe/year) – 577. (English) / qualifier | |||||||||||||||
point in time: 17 October 2020
|
Revision as of 16:58, 17 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a 600kWp photovoltaic power plant in the village of Połski Stare, gm. Piszczac |
Project in Poland financed by DG Regio |
Statements
946,811.79 zloty
0 references
1,505,265.17 zloty
0 references
62.9 percent
0 references
30 April 2018
0 references
30 July 2019
0 references
"EKO-INWEST" SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Realizacja projektu obejmuje budowę elektrowni fotowoltaicznej o mocy 600 kWp w miejscowości Połoski Stare, na działce nr 737/14, gm. Piszczac. Celem głównym projektu jest poprawa konkurencyjności rynku energii odnawialnej poprzez budowę elektrowni fotowoltaicznej w miejscowości Połoski Stare. W przedmiotowej inwestycji - ogniwa fotowoltaiczne, następuje konwersja promieniowania słonecznego w energię elektryczną - wytwarzanie energii elektrycznej ze źródła odnawialnego. Wytwarzana energia elektryczna sprzedawana będzie do sieci energetyki zawodowej. Dzięki realizacji projektu zostaną osiągnięte następujące wskaźniki: PRODUKTU - Dodatkowa zdolność wytwarzania energii elektrycznej ze źródeł odnawialnych (MWe) - 0,6; Dodatkowa zdolność wytwarzania energii ze źródeł odnawialnych (MW) - 0,6; Liczba przedsiębiorstw otrzymujących wsparcie - 1; Liczba wybudowanych jednostek przetwarzania energii eletrycznej z OZE - 1 oraz REZULTATU - Produkcja energii elektrycznej z nowo wybudowanych/nowych mocy wytwórczych instalacji wykorzystującej OZE (MWhe/rok) - 577; Szacowany roczny spadek emisji gazów cieplarnianych (tony równoważnika CO2/rok) - 191,7256; Produkcja energii elektrycznej z nowo wybudowanych instalacji wykorzystującej OZE (MWhe/rok) - 577. (Polish)
0 references
The project includes the construction of a 600 kWp photovoltaic power plant in Połoski Stare, on plot No. 737/14, Piszczac. The main objective of the project is to improve the competitiveness of the renewable energy market by building a photovoltaic power plant in Połoski Stare. In this investment – photovoltaic cells, solar radiation is converted into electricity – the generation of electricity from a renewable source. The electricity produced will be sold to the professional energy network. The following indicators will be achieved through the implementation of the project: Product – Additional renewable electricity generation capacity (MWe) – 0,6; Additional generation capacity from renewable sources (MW) – 0,6; Number of enterprises receiving support – 1; Number of RES energy conversion units built – 1 and REZULTATU – Manufacture of electricity from newly built/new RES installations (MWhe/year) – 577; Estimated annual decrease in greenhouse gas emissions (tonnes of CO2/year equivalent) – 191.7256; Electricity production from newly built RES installations (MWhe/year) – 577. (English)
17 October 2020
0 references
Identifiers
RPLU.04.02.00-06-0001/17
0 references