Insulation of the 6 kV network. Rzeszów for a voltage of 15 kV — upgrade of three stations 110/SN: Rzeszów, Stoniwa and Rzeszów Central. (Q86097): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The project will be implemented in Podkarpackie Province, on the premises of Rzeszów in three locations.The project involves the upgrading of three WN/SN stations:Rzeszów Central, Rzeszów, and Stenoniwa, which aims to adapt the existing 6 kV network located in the city of Rzeszów to 15 kV.As part of the project, 110/SN transformers will be included in the stations in the case of two winding transformers with a 110/15 kV transmission.Taking int...) |
(Created claim: summary (P836): The project will be implemented in the Podkarpackie Voivodeship, on the territory of Rzeszów in three locations. The subject of the Project is the modernisation of three WN/SN stations: Rzeszów Centralna, Rzeszów Staromieście and Staroniwa, whose aim is to adapt the existing 6 kV network located in the town of Rzeszów to work at a voltage of 15 kV. As part of the project, the 110/SN transformers will be replaced with 110/15 kV double winding tra...) |
||||||||||||||
Property / summary | |||||||||||||||
The project will be implemented in the Podkarpackie Voivodeship, on the territory of Rzeszów in three locations. The subject of the Project is the modernisation of three WN/SN stations: Rzeszów Centralna, Rzeszów Staromieście and Staroniwa, whose aim is to adapt the existing 6 kV network located in the town of Rzeszów to work at a voltage of 15 kV. As part of the project, the 110/SN transformers will be replaced with 110/15 kV double winding transformers. Due to, among other things, the high level of operation of 110 kV devices and the need to increase power security, the Rzeszów Central and Staroniwa stations will reconstruct the 110 kV switchgear for the H 5 system in GIS technology and reconstructed SN switching system. At WN/SN Rzeszów Station, Centrala and Staroniwa will build a new station building with internal 110 kV switching room in the GIS system, 15 kV switching room, power transformers, PW and DG transformers, BKR stations, other rooms necessary for the operation of the GPZ. At the Rzeszów Staromieście station a new 15 kV distribution room will be built. All stations will also be replaced with power transformers (two in each station). (English) | |||||||||||||||
Property / summary: The project will be implemented in the Podkarpackie Voivodeship, on the territory of Rzeszów in three locations. The subject of the Project is the modernisation of three WN/SN stations: Rzeszów Centralna, Rzeszów Staromieście and Staroniwa, whose aim is to adapt the existing 6 kV network located in the town of Rzeszów to work at a voltage of 15 kV. As part of the project, the 110/SN transformers will be replaced with 110/15 kV double winding transformers. Due to, among other things, the high level of operation of 110 kV devices and the need to increase power security, the Rzeszów Central and Staroniwa stations will reconstruct the 110 kV switchgear for the H 5 system in GIS technology and reconstructed SN switching system. At WN/SN Rzeszów Station, Centrala and Staroniwa will build a new station building with internal 110 kV switching room in the GIS system, 15 kV switching room, power transformers, PW and DG transformers, BKR stations, other rooms necessary for the operation of the GPZ. At the Rzeszów Staromieście station a new 15 kV distribution room will be built. All stations will also be replaced with power transformers (two in each station). (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project will be implemented in the Podkarpackie Voivodeship, on the territory of Rzeszów in three locations. The subject of the Project is the modernisation of three WN/SN stations: Rzeszów Centralna, Rzeszów Staromieście and Staroniwa, whose aim is to adapt the existing 6 kV network located in the town of Rzeszów to work at a voltage of 15 kV. As part of the project, the 110/SN transformers will be replaced with 110/15 kV double winding transformers. Due to, among other things, the high level of operation of 110 kV devices and the need to increase power security, the Rzeszów Central and Staroniwa stations will reconstruct the 110 kV switchgear for the H 5 system in GIS technology and reconstructed SN switching system. At WN/SN Rzeszów Station, Centrala and Staroniwa will build a new station building with internal 110 kV switching room in the GIS system, 15 kV switching room, power transformers, PW and DG transformers, BKR stations, other rooms necessary for the operation of the GPZ. At the Rzeszów Staromieście station a new 15 kV distribution room will be built. All stations will also be replaced with power transformers (two in each station). (English) / qualifier | |||||||||||||||
point in time: 14 October 2020
|
Revision as of 15:32, 14 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Insulation of the 6 kV network. Rzeszów for a voltage of 15 kV — upgrade of three stations 110/SN: Rzeszów, Stoniwa and Rzeszów Central. |
Project in Poland financed by DG Regio |
Statements
17,852,316.83 zloty
0 references
27,000,666.09 zloty
0 references
66.12 percent
0 references
15 June 2016
0 references
30 June 2019
0 references
PGE DYSTRYBUCJA S.A.
0 references
Projekt będzie realizowany w woj. podkarpackim, na terenie m. Rzeszowa w trzech lokalizacjach. Przedmiotem Projektu jest modernizacja trzech stacji WN/SN: Rzeszów Centralna, Rzeszów Staromieście oraz Staroniwa, której celem jest przystosowanie istniejącej sieci 6 kV znajdującej się na terenie miasta Rzeszowa do pracy na napięciu 15 kV. W ramach projektu na stacjach zostaną wymienione transformatory 110/SN na transformatory dwuuzwojeniowe o przekładni 110/15 kV. Z uwagi m.in. na znaczny stopień wyeksploatowania urządzeń 110 kV oraz potrzebę zwiększenia pewności zasilania, w stacjach Rzeszów Centralna i Staroniwa zostanie przebudowana rozdzielnia 110 kV do układu H 5 w technologii GIS oraz przebudowana rozdzielnia SN. W stacji WN/SN Rzeszów Centrala i Staroniwa wybudowany zostanie nowy budynek stacji z wnętrzową rozdzielnią 110 kV w systemie GIS, rozdzielnią 15 kV, stanowiskami transformatorów mocy, transformatorów PW i DG, stanowiskami BKR, innymi pomieszczeniami niezbędnymi do funkcjonowania GPZ. W stacji Rzeszów Staromieście zabudowana zostanie nowa rozdzielnia 15 kV. We wszystkich stacjach zostaną wymienione także transformatory mocy (po dwa w każdej stacji). (Polish)
0 references
The project will be implemented in the Podkarpackie Voivodeship, on the territory of Rzeszów in three locations. The subject of the Project is the modernisation of three WN/SN stations: Rzeszów Centralna, Rzeszów Staromieście and Staroniwa, whose aim is to adapt the existing 6 kV network located in the town of Rzeszów to work at a voltage of 15 kV. As part of the project, the 110/SN transformers will be replaced with 110/15 kV double winding transformers. Due to, among other things, the high level of operation of 110 kV devices and the need to increase power security, the Rzeszów Central and Staroniwa stations will reconstruct the 110 kV switchgear for the H 5 system in GIS technology and reconstructed SN switching system. At WN/SN Rzeszów Station, Centrala and Staroniwa will build a new station building with internal 110 kV switching room in the GIS system, 15 kV switching room, power transformers, PW and DG transformers, BKR stations, other rooms necessary for the operation of the GPZ. At the Rzeszów Staromieście station a new 15 kV distribution room will be built. All stations will also be replaced with power transformers (two in each station). (English)
14 October 2020
0 references
Identifiers
POIS.07.01.00-00-0001/16
0 references