Construction of a tram line to Vilnius with the purchase of rolling stock and associated infrastructure. (Q86080): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project involves the construction of three sections of the tram line to Vilnius.Two sections within the line of Rakowiecka — Pulawy — Govorna — Spacerowa — Belwederska — Sobieski — al.The Republic of Poland (with the construction of the relevant terminals) and the third section on ul.A battle of Warsaw on the section from ul.Grójec to West Denmark, with a total length of ca.11.70 km.The final length of the route will be determined on the b...)
(‎Created claim: summary (P836): The project includes the construction of three sections of the tram route to Wilanów. Two sections within Rakowiecka Street – Puławska – Goworka – Walk – Belwederska – Sobieskiego – al. Rzeczpospolita (including the construction of relevant frontal terminals) and the third section within ul. The Battle of Warsaw 1920 on the section from ul. Grójecka to the Western Railway Station with a total length of approx. It’s 11,70 miles. The final length...)
Property / summary
 
The project includes the construction of three sections of the tram route to Wilanów. Two sections within Rakowiecka Street – Puławska – Goworka – Walk – Belwederska – Sobieskiego – al. Rzeczpospolita (including the construction of relevant frontal terminals) and the third section within ul. The Battle of Warsaw 1920 on the section from ul. Grójecka to the Western Railway Station with a total length of approx. It’s 11,70 miles. The final length of the route will be determined on the basis of the design documentation. (English)
Property / summary: The project includes the construction of three sections of the tram route to Wilanów. Two sections within Rakowiecka Street – Puławska – Goworka – Walk – Belwederska – Sobieskiego – al. Rzeczpospolita (including the construction of relevant frontal terminals) and the third section within ul. The Battle of Warsaw 1920 on the section from ul. Grójecka to the Western Railway Station with a total length of approx. It’s 11,70 miles. The final length of the route will be determined on the basis of the design documentation. (English) / rank
 
Normal rank
Property / summary: The project includes the construction of three sections of the tram route to Wilanów. Two sections within Rakowiecka Street – Puławska – Goworka – Walk – Belwederska – Sobieskiego – al. Rzeczpospolita (including the construction of relevant frontal terminals) and the third section within ul. The Battle of Warsaw 1920 on the section from ul. Grójecka to the Western Railway Station with a total length of approx. It’s 11,70 miles. The final length of the route will be determined on the basis of the design documentation. (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:32, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a tram line to Vilnius with the purchase of rolling stock and associated infrastructure.
Project in Poland financed by DG Regio

    Statements

    0 references
    554,638,744.87 zloty
    0 references
    133,113,298.77 Euro
    13 January 2020
    0 references
    973,069,700.0 zloty
    0 references
    233,536,728.0 Euro
    13 January 2020
    0 references
    57.0 percent
    0 references
    29 January 2014
    0 references
    31 July 2021
    0 references
    TRAMWAJE WARSZAWSKIE SP. Z O.O.
    0 references
    0 references

    52°14'1.3"N, 21°4'17.0"E
    0 references
    Projekt obejmuje budowę trzech odcinków trasy tramwajowej do Wilanowa. Dwóch odcinków w ciągu ulic Rakowieckiej – Puławskiej – Goworka – Spacerowej – Belwederskiej – Sobieskiego – al. Rzeczpospolitej (wraz z budową odpowiednich terminali czołowych) oraz trzeciego odcinka w ciągu ul. Bitwy Warszawskiej 1920 r. na odcinku od ul. Grójeckiej do Dworca Zachodniego o łącznej długości ok. 11,70 km. Ostateczna długość trasy zostanie ustalona na podstawie opracowanej dokumentacji projektowej. (Polish)
    0 references
    The project includes the construction of three sections of the tram route to Wilanów. Two sections within Rakowiecka Street – Puławska – Goworka – Walk – Belwederska – Sobieskiego – al. Rzeczpospolita (including the construction of relevant frontal terminals) and the third section within ul. The Battle of Warsaw 1920 on the section from ul. Grójecka to the Western Railway Station with a total length of approx. It’s 11,70 miles. The final length of the route will be determined on the basis of the design documentation. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.06.01.00-00-0033/16
    0 references