Q146430 (Q146430): Difference between revisions
Jump to navigation
Jump to search
(Created claim: summary (P836): The project for the protection and sustainable development of the Lido de Sète in Marseillan is entering its last operational phase, Phase 5, which consists of deploying the swell attenuator to an additional 1400 m to complete a 2400 m submerged structure., translated_summary) |
(Changed label, description and/or aliases in 1 language: remove_english_label) |
||
label / en | label / en | ||
Revision as of 14:41, 12 October 2020
Project in France financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project in France financed by DG Regio |
Statements
1,081,080.0 Euro
0 references
3,861,000.0 Euro
0 references
28.0 percent
0 references
11 May 2016
0 references
30 April 2019
0 references
Sète Agglopôle Méditerranée (SAM)
0 references
34110
0 references
Le projet de protection et aménagement durable du Lido de Sète à Marseillan entre dans sa dernière phase opérationnelle, la phase 5, qui consiste à déployer l'atténuateur de houle sur 1400 m supplémentaire pour arriver à terme à un ouvrage immergé sur 2 400 m. (French)
0 references
The project for the protection and sustainable development of the Lido de Sète in Marseillan is entering its last operational phase, Phase 5, which consists of deploying the swell attenuator to an additional 1400 m to complete a 2400 m submerged structure. (English)
12 October 2020
0 references
0 references
Identifiers
4248
0 references
5208
0 references