Construction of the public notification and alarm system and integrated communication in the district of the crossing district in the hazard environment, in particular of the flood (Q122516): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: budget (P474): 719,871.9744 euro) |
(Changed an Item: Fixing rounding issue) |
||||||||||||||
Property / budget | |||||||||||||||
719,871.97 Euro
| |||||||||||||||
Property / budget: 719,871.97 Euro / rank | |||||||||||||||
Preferred rank | |||||||||||||||
Property / budget: 719,871.97 Euro / qualifier | |||||||||||||||
exchange rate to Euro: 0.24 Euro
| |||||||||||||||
Property / budget: 719,871.97 Euro / qualifier | |||||||||||||||
point in time: 13 January 2020
|
Revision as of 03:25, 25 September 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of the public notification and alarm system and integrated communication in the district of the crossing district in the hazard environment, in particular of the flood |
Project in Poland financed by DG Regio |
Statements
2,549,546.57 zloty
0 references
2,999,466.56 zloty
0 references
85.0 percent
0 references
22 December 2016
0 references
31 May 2019
0 references
POWIAT BYTOWSKI
0 references
Celem projektu jest poprawa bezpieczeństwa powodziowego w skali lokalnej, a także lepsze zabezpieczenia terenów zurbanizowanych przed skutkami podtopień i powodzi spowodowanych nawalnymi opadami i innych zagrożeń naturalnych. W ramach projektu zaplanowane zostały do realizacji prace związane montażem urządzeń Systemu powiadamiania i alarmowania ludności oraz zintegrowanej łączności w powiecie bytowskim w uwarunkowaniach zagrożenia, w szczególności powodziowego na terenie Gmin: Borzytuchom, Bytów, Czarna Dąbrówka, Kołczygłowy, Lipnica, Miastko, Parchowo, Studzienice, Trzebielino oraz Tuchomie. Liderem projektu będzie powiat bytowski, a Gminy z terenu powiatu partnerami. W ramach projektu planowane są prace remontowo-budowlane, prace przygotowawcze, także działania związane z promocją i informacją oraz sprawowanie nadzoru nad realizacją inwestycji. (Polish)
0 references
The aim of the project is to improve flood safety at local scale, as well as to provide better protection for urban areas against the effects of flooding and flooding caused by recurring precipitation and other natural hazards. Within the framework of the project, the installation of equipment for the notification and alarm equipment of the public and of the integrated communication in the powiat byway in the emergency, in particular of the floods in the Municipalities, is planned for: Borzytuchom, Bytów, Czarna Dąbrówka, Kolczykhead, Lipnica, Miastko, Parchowo, Studzinice, Trzebiolino and Tuchoma. The project leader will be the powiat bytown and the municipality in the district of the partners. The project consists of renovation and construction work, preparatory work, including promotion and information activities and supervision of the implementation of the investment. (English)
0 references
Identifiers
RPPM.11.01.00-22-0016/16
0 references