Construction of a photovoltaic installation for laundry (Q137722): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: Fixing rounding issue)
(‎Removed claim: summary (P836): The object of the project is the construction of a roof photovoltaic installation on the roof of the former beneficiary, the town of Busko Morskie, the municipality of Darłowo district, West Pomerania Province. The installation will consist of 352 mono-crystalline modules having a nominal capacity of 98,56 kWp located on the eastern side of the wind. Electricity generation of 87 817 kWh/year is planned. This will help to reduce the cost of ele...)
Property / summary
The object of the project is the construction of a roof photovoltaic installation on the roof of the former beneficiary, the town of Busko Morskie, the municipality of Darłowo district, West Pomerania Province. The installation will consist of 352 mono-crystalline modules having a nominal capacity of 98,56 kWp located on the eastern side of the wind. Electricity generation of 87 817 kWh/year is planned. This will help to reduce the cost of electricity in the Applicant’s laundry by 100 % in the year. Phases of the project: The following activities and activities are foreseen under this project: (1) a diagnosis of the current situation and an identification of the investment needs in the area concerned (2) of the formulation of the project, including in particular the definition of the objectives, results, activities, resources, timing, budget and all other elements of the complete project 3) of the preparation of the technical documentation (building design) necessary for the implementation of the project — the commissioning of an external contractor 4) a feasibility study — an external company 5), of project acceptance: assessment of the application completed by the signature of co-financing agreements for project 6) selection of the contractor, (7) execution of assembly and construction work, (8) collection of works on the basis of a hand-over protocol 9) final financial settlement of the project. The project is stationary. (English)
 
Property / summary: The object of the project is the construction of a roof photovoltaic installation on the roof of the former beneficiary, the town of Busko Morskie, the municipality of Darłowo district, West Pomerania Province. The installation will consist of 352 mono-crystalline modules having a nominal capacity of 98,56 kWp located on the eastern side of the wind. Electricity generation of 87 817 kWh/year is planned. This will help to reduce the cost of electricity in the Applicant’s laundry by 100 % in the year. Phases of the project: The following activities and activities are foreseen under this project: (1) a diagnosis of the current situation and an identification of the investment needs in the area concerned (2) of the formulation of the project, including in particular the definition of the objectives, results, activities, resources, timing, budget and all other elements of the complete project 3) of the preparation of the technical documentation (building design) necessary for the implementation of the project — the commissioning of an external contractor 4) a feasibility study — an external company 5), of project acceptance: assessment of the application completed by the signature of co-financing agreements for project 6) selection of the contractor, (7) execution of assembly and construction work, (8) collection of works on the basis of a hand-over protocol 9) final financial settlement of the project. The project is stationary. (English) / rank
Normal rank
 

Revision as of 19:20, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a photovoltaic installation for laundry
Project in Poland financed by DG Regio

    Statements

    0 references
    367,523.36 zloty
    0 references
    88,205.61 Euro
    13 January 2020
    0 references
    475,034.75 zloty
    0 references
    114,008.34 Euro
    13 January 2020
    0 references
    77.37 percent
    0 references
    29 April 2016
    0 references
    20 September 2017
    0 references
    TRANS-EKO SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references
    Przedmiotem projektu jest budowa instalacji fotowoltaicznej na dachu wiaty przynależnej do Pralni Beneficjenta, miejscowość Bukowo Morskie, gmina Darłowo powiat sławieński, województwo zachodniopomorskie. Przedmiotowa instalacja będzie składała się z 352 modułów monokrystalicznych o mocy nominalnej 98,56 kWp, zlokalizowanych od strony wschodniej wiaty. Planuje się wytwarzanie energii elektrycznej przez instalację w ilości 87 817 kWh/rok. Pomoże to zmniejszyć koszty energii elektrycznej w Pralni Wnioskodawcy o 100 % w ciągu roku. Etapy projektu: W ramach przedmiotowego projektu przewidziano następujące działania i czynności: 1)diagnoza sytuacji obecnej i określenie potrzeb inwestycyjnych na rozpatrywanym obszarze 2)formułowanie projektu, obejmujące przede wszystkim określenie celów, rezultatów, działań, zasobów, harmonogramu, budżetu oraz wszystkich innych elementów tworzących kompletne przedsięwzięcie 3)przygotowanie dokumentacji technicznej (projekt budowlany) niezbędnej do realizacji projektu – zlecenie firmie zewnętrznej 4)przygotowanie studium wykonalności – firma zewnętrzna 5)akceptacja projektu: ocena wniosku zakończona podpisaniem umów o współfinansowaniu projektu 6) przeprowadzenie wyboru wykonawcy, 7)wykonanie robót montażowych i budowlanych, 8)odbiór prac na podstawie protokołu zdawczo-odbiorczego 9)końcowe rozliczenie finansowe projektu. Przedmiotowy projekt ma charakter stacjonarny. (Polish)
    0 references

    Identifiers

    RPZP.02.10.00-32-A171/16
    0 references