Construction of a two-track line Krajk-Basczynna-Plewiska line with the construction/expansion/upgrading of stations in this line line (Q86122): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Fixing rounding issue) |
(Removed claim: summary (P836): The project will cover 4 separate investment tasks, called:Construction of the 400 kV Basica-Babczyn line, Construction of 400 kV Basczyn-Plewiska line, Construction of 400/110 kV Basczyn line with the introduction of the 400 kV Krajnik Plewiska line, Construction of 400/110 kV Basczyn station, and the installation of 400 kV Bavia-Plewiska line and the installation of reactive power compensation equipment.In addition, the purchase and supply o...) |
||
Property / summary | |||
Property / summary: The project will cover 4 separate investment tasks, called:Construction of the 400 kV Basica-Babczyn line, Construction of 400 kV Basczyn-Plewiska line, Construction of 400/110 kV Basczyn line with the introduction of the 400 kV Krajnik Plewiska line, Construction of 400/110 kV Basczyn station, and the installation of 400 kV Bavia-Plewiska line and the installation of reactive power compensation equipment.In addition, the purchase and supply of ATR and the choke at 400/110 kV Basina is planned under separate contracts with contractors.The estimated length of the line will be about 434 km of line tracks (Krajnik — Basczyn line.70 km x 2 and Basczyn — Plewiska line (approx. 147 km x2.) Power Station 400/110 kV Bazina will be located in the area of Basczyn in the municipality of Lubiczyn, in the county of Lubim, in Lubuskie Province.The site is supposed to cover about 10 ha.400/220 kV Krajnik station is located in the village of Krajnik and Nowe Czarnovo in the municipality of Gryfino, the county of West Pomerania Province. (English) / rank | |||
Revision as of 15:33, 14 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a two-track line Krajk-Basczynna-Plewiska line with the construction/expansion/upgrading of stations in this line line |
Project in Poland financed by DG Regio |
Statements
444,269,244.16 zloty
0 references
444,269,244.16 zloty
0 references
100.0 percent
0 references
1 January 2014
0 references
31 October 2023
0 references
POLSKIE SIECI ELEKTROENERGETYCZNE S.A
0 references
Projekt swym zakresem obejmował będzie 4 odrębne zadania inwestycyjne o nazwie: Budowa linii 400 kV Krajnik-Baczyna, Budowa linii 400 kV Baczyna-Plewiska, Budowa stacji 400/110 kV Baczyna wraz z wprowadzeniem linii 400 kV Krajnik-Plewiska, Rozbudowa stacji 400/110 kV Baczyna związku z wprowadzeniem linii 400 kV Baczyna-Plewiska oraz instalacją urządzeń do kompensacji mocy biernej. Ponadto, planowany jest zakup i dostawa ATR oraz dławika na stację 400/110 kV Baczyna w ramach odrębnych umów z wykonawcami. Szacowana długość linii wyniesie około 434 km torów prądowych (linia Krajnik – Baczyna ok. 70 km x 2 oraz linia Baczyna – Plewiska około 147 km x2.) Stacja elektroenergetyczna 400 / 110 kV Baczyna będzie zlokalizowana na terenie miejscowości Baczyna w gminie Lubiszyn, w powiecie gorzowskim, w województwie lubuskim. Teren pod budowę stacji ma obejmować około 10 ha. Stacja elektroenergetyczna 400/220 kV Krajnik zlokalizowana jest na terenie miejscowości Krajnik oraz Nowe Czarnowo w gminie Gryfino, powiat gryfiński, województwo zachodniopomorskie (Polish)
0 references
Identifiers
POIS.07.01.00-00-0009/17
0 references