(‎Removed claim: summary (P836): The project includes:— construction of a sewage treatment plant Q = 3687 p.e. — construction of sanitary sewage system (gravity network — 16.1 km, compressor station — 1.25 km, connections — 1.5 km) — use of solar lamps using sunlight to illuminate the sewage treatment plant, — HMI/SCADA monitoring system., remove_old_english_translation)
Property / summary
The project includes:— construction of a sewage treatment plant Q = 3687 p.e. — construction of sanitary sewage system (gravity network — 16.1 km, compressor station — 1.25 km, connections — 1.5 km) — use of solar lamps using sunlight to illuminate the sewage treatment plant, — HMI/SCADA monitoring system. (English)
 
Property / summary: The project includes:— construction of a sewage treatment plant Q = 3687 p.e. — construction of sanitary sewage system (gravity network — 16.1 km, compressor station — 1.25 km, connections — 1.5 km) — use of solar lamps using sunlight to illuminate the sewage treatment plant, — HMI/SCADA monitoring system. (English) / rank
Normal rank
 

Revision as of 15:59, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of the wastewater treatment plant and the sanitary sewage system in Nowy Month.
Project in Poland financed by DG Regio

    Statements

    0 references
    11,319,512.19 zloty
    0 references
    2,716,682.93 Euro
    13 January 2020
    0 references
    13,317,073.17 zloty
    0 references
    3,196,097.56 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 August 2015
    0 references
    30 September 2020
    0 references
    GMINA NOWE MIASTO
    0 references
    0 references

    52°39'22.7"N, 20°37'50.5"E
    0 references
    Projekt obejmuje: - budowę oczyszczalni ścieków Q= 3687 RLM, - budowę kanalizacji sanitarnej (sieć grawitacyjna - 16,1 km, sieć tłoczna - 1,25 km, przyłącza - 1,5 km), - zastosowanie lamp solarnych z wykorzystaniem światła słonecznego do oświetlenia terenu oczyszczalni, - system monitoringu typu HMI/SCADA. (Polish)