Property / budget
4,489,500.0 zloty
Amount4,489,500.0 zloty
Unitzloty
 
Property / budget: 4,489,500.0 zloty / rank
Normal rank
 
Property / budget
1,077,480.0 Euro
Amount1,077,480.0 Euro
UnitEuro
 
Property / budget: 1,077,480.0 Euro / rank
Preferred rank
 
Property / budget: 1,077,480.0 Euro / qualifier
exchange rate to Euro: 0.24 Euro
Amount0.24 Euro
UnitEuro
 
Property / budget: 1,077,480.0 Euro / qualifier
point in time: 13 January 2020
Timestamp+2020-01-13T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0
 

Revision as of 14:10, 22 June 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Reconstruction of the 110/15 kV substation in order to enable the development of renewable energy
Project in Poland financed by DG Regio

    Statements

    0 references
    2,648,488.37 zloty
    0 references
    635,637.2088 Euro
    13 January 2020
    0 references
    72.66 percent
    0 references
    28 December 2018
    0 references
    30 September 2020
    0 references
    ENERGA-OPERATOR SPÓŁKA AKCYJNA
    0 references
    0 references
    0 references
    Zakres Projektu obejmuje przebudowę stacji elektroenergetycznej GPZ 110/15 kV Kleczew celem umożliwienia rozwoju energetyki odnawialnej. Stacja stanowi element sieci dystrybucyjnej na napięciu 110 kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV. (Polish)
    0 references
    The scope of the project involves the reconstruction of the GPZ 110/15 kV Kleczew electricity station in order to enable the development of renewable energy.The station is part of the 110 kV distribution network where the 15 kV electricity transition is performed. (English)
    0 references

    Identifiers

    POIS.01.01.02-00-0004/18
    0 references