Diversification of energy sources in the municipality of Cekcyn through installation of photovoltaic installations (Q4425316): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in en: Setting new description) |
(Changed label, description and/or aliases in en, and other parts: Adding translation) |
||
label / en | label / en | ||
Diversification of energy sources in the municipality of Cekcyn through installation of photovoltaic installations | |||
Property / summary | |||
The project consists of the creation of 53 photovoltaic microinstallations on private buildings and 6 micro-installations on public buildings. Photovoltaic installations installed on public buildings: — Elementary school in Cekcin (microinstallation with a power of 19.84 kW) — Władysław Broniewski Primary School in Iwc (microinstallation with a power of 16.64 kW)- Sports and visual hall in Cekcin (microinstallation with a power of 49.92 kW)- Primary school in Zielonka (microinstallation of power 12.16 kW) — Village Light in High (microinstallation with a power of 8 kW) — Municipal Office in Cekcin (microinstallation with a power of 26.88 kW) All installations will be located in the Commune of Cekcyn. The scope of the project also includes the preparation of tender documentation (including technical documentation), application documentation, investor supervision and project promotion. The work included in particular: carrying out local visions, developing audits of energy demand and technical capabilities. In addition, the work also included the preparation of tender documentation (including technical documentation) and documentation necessary to apply for funding. After signing the grant agreement, the project will be implemented in-kindly, and after its implementation — promotion of the project. Deadlines for implementation: The planned date of implementation — 31 October 2021The planned date for the physical implementation of the investment: — I stage — real estate of natural persons — March — May 2021 — stage II — public buildings — June — August 2021 (English) | |||
Property / summary: The project consists of the creation of 53 photovoltaic microinstallations on private buildings and 6 micro-installations on public buildings. Photovoltaic installations installed on public buildings: — Elementary school in Cekcin (microinstallation with a power of 19.84 kW) — Władysław Broniewski Primary School in Iwc (microinstallation with a power of 16.64 kW)- Sports and visual hall in Cekcin (microinstallation with a power of 49.92 kW)- Primary school in Zielonka (microinstallation of power 12.16 kW) — Village Light in High (microinstallation with a power of 8 kW) — Municipal Office in Cekcin (microinstallation with a power of 26.88 kW) All installations will be located in the Commune of Cekcyn. The scope of the project also includes the preparation of tender documentation (including technical documentation), application documentation, investor supervision and project promotion. The work included in particular: carrying out local visions, developing audits of energy demand and technical capabilities. In addition, the work also included the preparation of tender documentation (including technical documentation) and documentation necessary to apply for funding. After signing the grant agreement, the project will be implemented in-kindly, and after its implementation — promotion of the project. Deadlines for implementation: The planned date of implementation — 31 October 2021The planned date for the physical implementation of the investment: — I stage — real estate of natural persons — March — May 2021 — stage II — public buildings — June — August 2021 (English) / rank | |||
Normal rank |
Revision as of 15:26, 21 October 2022
Project Q4425316 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Diversification of energy sources in the municipality of Cekcyn through installation of photovoltaic installations |
Project Q4425316 in Poland |
Statements
672,742.92 zloty
0 references
149,550.75 Euro
0 references
1,345,485.85 zloty
0 references
299,101.5 Euro
0 references
50.0 percent
0 references
1 June 2020
0 references
31 October 2021
0 references
GMINA CEKCYN
0 references
Projekt polega na utworzeniu 53 mikroinstalacji fotowoltaicznych na budynkach prywatnych oraz 6 mikroinstalacji na budynkach użyteczności publicznej. Instalacje fotowoltaiczne montowane na obiektach użyteczności publicznej: - Szkoła Podstawowa w Cekcynie (mikroinstalacja o mocy 19,84 kW)- Szkoła Podstawowa im. Władysława Broniewskiego w Iwcu (mikroinstalacja o mocy 16,64 kW)- Hala sportowo-widowiskowa w Cekcynie (mikroinstalacja o mocy 49,92 kW)- Szkoła Podstawowa w Zielonce (mikroinstalacja o mocy 12,16 kW) - Świetlica Wiejska w Wysokim (mikroinstalacja o mocy 8 kW) - Urząd Gminy w Cekcynie (mikroinstalacja o mocy 26,88 kW) Wszystkie instalacje będą zlokalizowane na terenie Gminy Cekcyn. W zakres projektu wchodzi również przygotowanie dokumentacji przetargowej (w tym technicznej), aplikacyjnej, nadzór inwestorski oraz promocja projektu. Prace obejmowały w szczególności: przeprowadzenie wizji lokalnych, opracowanie audytów zapotrzebowania na energię oraz możliwości technicznych. Ponadto, w skład prac wchodziło również opracowanie dokumentacji przetargowej (w tym technicznej) oraz dokumentacji niezbędnej do ubiegania się o przyznanie dofinansowania. Po podpisaniu umowy o dofinansowanie nastąpi rzeczowa realizacja projektu, zaś po jej realizacji - promocja projektu. Terminy realizacji:Planowany termin realizacji – 31 października 2021 rokuPlanowany termin rzeczowej realizacji inwestycji: - I etap - nieruchomości osób fizycznych – marzec - maj 2021 roku- II etap - budynki użyteczności publicznej – czerwiec - sierpień 2021 roku (Polish)
0 references
The project consists of the creation of 53 photovoltaic microinstallations on private buildings and 6 micro-installations on public buildings. Photovoltaic installations installed on public buildings: — Elementary school in Cekcin (microinstallation with a power of 19.84 kW) — Władysław Broniewski Primary School in Iwc (microinstallation with a power of 16.64 kW)- Sports and visual hall in Cekcin (microinstallation with a power of 49.92 kW)- Primary school in Zielonka (microinstallation of power 12.16 kW) — Village Light in High (microinstallation with a power of 8 kW) — Municipal Office in Cekcin (microinstallation with a power of 26.88 kW) All installations will be located in the Commune of Cekcyn. The scope of the project also includes the preparation of tender documentation (including technical documentation), application documentation, investor supervision and project promotion. The work included in particular: carrying out local visions, developing audits of energy demand and technical capabilities. In addition, the work also included the preparation of tender documentation (including technical documentation) and documentation necessary to apply for funding. After signing the grant agreement, the project will be implemented in-kindly, and after its implementation — promotion of the project. Deadlines for implementation: The planned date of implementation — 31 October 2021The planned date for the physical implementation of the investment: — I stage — real estate of natural persons — March — May 2021 — stage II — public buildings — June — August 2021 (English)
0 references
WOJ.: KUJAWSKO-POMORSKIE, POW.: tucholski
0 references
Identifiers
RPKP.03.01.00-04-0042/20
0 references