“Renewable energy installations in the municipality of Domaniewice” (Q4424716): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in en, and other parts: Adding translation)
(‎Changed an Item: Import item from Poland)
Property / intervention field
 
Property / intervention field: Renewable energy: solar / rank
 
Normal rank

Revision as of 15:08, 24 October 2022

Project Q4424716 in Poland
Language Label Description Also known as
English
“Renewable energy installations in the municipality of Domaniewice”
Project Q4424716 in Poland

    Statements

    0 references
    2,624,998.9 zloty
    0 references
    583,537.26 Euro
    0 references
    3,088,234.0 zloty
    0 references
    686,514.42 Euro
    0 references
    85.0 percent
    0 references
    1 June 2021
    0 references
    30 June 2023
    0 references
    GMINA DOMANIEWICE
    0 references
    Celem głównym proj.pn. Instalacje odnawialnych źródeł energii na terenie gminy Domaniewice” jest: zwiększenie produkcji energii ze źródeł odnawialnych i zmniejszenie wykorzystania konwencjonalnych źródeł energii w gminie Domaniewice, skutkujące poprawą stanu środowiska naturalnego. Grupą docelową są właściciele posesji, na terenie których zainstalowano infrastrukturę OZE/osoby korzystające z usług budynku użyteczności publ.- łącznie 507 osób oraz pośrednio wszyscy mieszkańcy gminy i woj. łódzkiego. Realizacja projektu obejmuje zadania: 1. Przygotowanie projektu: 1.1 Opracowanie dokumentacji aplikacyjnej - studium wykonalności, PFU. 1.2 Opracowanie dokumentacji technicznej – dok. techniczna w formule zaprojektuj wybuduj. 2. Roboty montażowo-instalacyjne- zakup i montaż instalacji OZE: -paneli fotowoltaicznych na terenie prywatnych posesji mieszkańców gminy–159 szt., -paneli fotowoltaicznych na terenie budynków użyteczności publicznej gminy–3 szt., -kotłów na biomasę–10 szt., 3. Koszty pośrednie: 3.1 nadzór inwestorski i przygotowanie postępowania – nadzór inwestorski i przygotowanie postępowania na wybór dostawcy. 3.2 zarządzanie projektem - dodatki do wynagrodzeń pracowników gminy odpowiedzialnych za proces zarządzania projektem. 3.3 promocja projektu –tablica informacyjno-pamiątkowa, plakaty, naklejki. Łączna moc zastosowanych urządzeń fotowoltaicznych: 0,83 MWe. Zastosowane w projekcie kotły na biomasę będą miały łączna moc: 0,22 MW. Zmniejszenie emisji gazów cieplarnianych (efekt ekologiczny) w projekcie: 627,42 tony/równoważnika ekwiwalentu CO2. Wartość finansowa projektu wynosi 3 390 962,82 zł. W ramach środków została zabezpieczona kwota 463 235,10 zł, stanowiąca 15% kosztów kwal., oraz kwota 302 728,82 zł pokrywająca wszystkie koszty niekwal. projektu (w tym vat). Pozostała kwota wydatków, wynosząca 2 624 998,90 zł 85% kosztów kwal.- zostanie sfinansowana z funduszy UE. Okres realizacji projektu II 2021-II 2023. (Polish)
    0 references
    The main objective of the project. Installations of renewable energy sources in the commune of Domaniewice” are: increasing the production of energy from renewable sources and reducing the use of conventional energy sources in the municipality of Domaniewice, resulting in an improvement of the natural environment. The target group is the owners of the property, on the territory of which the RES infrastructure/persons using the services of the utility building publ. — a total of 507 people and indirectly all residents of the municipality and the Łódzkie voivodeship were installed. The implementation of the project includes the following tasks: 1. Preparation of the project: 1.1 Development of application documentation — feasibility study, PFU. 1.2 Development of technical documentation — doc. technical in the formula design build. 2. Installation and assembly works — purchase and installation of RES installations: photovoltaic panels in the private property of the inhabitants of the commune-159 pcs., -photovoltaic panels in the public buildings of the commune-3 pcs., -boilers for biomass-10 pcs., 3. Indirect costs: 3.1 Investor supervision and procedure preparation — investor supervision and preparation of the procedure for the selection of the supplier. 3.2 Project management — allowances to the salaries of municipal employees responsible for the project management process. 3.3 promotion of the project — information and memorial board, posters, stickers. Total power of photovoltaic devices used: 0.83 MWe. The biomass boilers used in the project will have a total power: 0.22 MW. Reduction of greenhouse gas emissions (environmental effect) in the project: 627.42 tonnes/equivalent of CO2 equivalent. The financial value of the project is PLN 3,390,962.82. As part of the funds, the amount of PLN 463 235.10 was secured, representing 15 % of the costs of the quarters, and the amount of PLN 302 728.82 covering all costs of the unqualified project (including vat). The remaining amount of expenditure, amounting to PLN 2 624 998.90 85 % of the costs, will be financed by EU funds. Project implementation period II 2021-II 2023. (English)
    0 references
    WOJ.: ŁÓDZKIE, POW.: łowicki
    0 references

    Identifiers

    RPLD.13.02.00-10-0012/21
    0 references