Improving the energy efficiency of public utility buildings in the Po Świętone Commune through deep thermal modernisation and implementation of RES (Q4416739): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in en, and other parts)
(‎Changed an Item: Import item from Poland)
Property / intervention field
 
Property / intervention field: Energy efficiency renovation of public infrastructure, demonstration projects and supporting measures / rank
 
Normal rank

Revision as of 14:58, 24 October 2022

Project Q4416739 in Poland
Language Label Description Also known as
English
Improving the energy efficiency of public utility buildings in the Po Świętone Commune through deep thermal modernisation and implementation of RES
Project Q4416739 in Poland

    Statements

    0 references
    3,082,842.27 zloty
    0 references
    685,315.84 Euro
    0 references
    3,853,552.83 zloty
    0 references
    856,644.79 Euro
    0 references
    80.0 percent
    0 references
    1 July 2020
    0 references
    30 June 2022
    0 references
    GMINA POŚWIĘTNE
    0 references
    0 references
    Wniosek składa podmiot uprawniony do udzielenia wsparcia – Gmina Poświętne z pow. wołomińskiego, woj. mazowieckiego. Projekt przewiduje zaprojektowanie i wykonanie głębokiej termomodernizacji pięciu budynków użyteczności publicznej prowadzących działalność pozaleczniczą, ulokowanych na terenie Gminy Poświętne. Planuje się działania gruntowne, efektywne i wykorzystujące OZE (elektrownia fotowoltaiczna, pompy ciepła). Uzyskana zostanie ponad 60% poprawa efektywności energetycznej. Projekt jest zgodny z Planem Gospodarki Niskoemisyjnej Gminy Poświętne (PGN) oraz stanowi projekt rewitalizacyjny zgodnie z Lokalnym Programem Rewitalizacji Gminy Poświętne (program wpisany do wykazu programów rewitalizacji województwa mazowieckiego na dzień składania wniosku). Projekt wymianę urządzeń grzewczych na OZE (pompa ciepła EHP), a także zamianę starego kotła węglowego na kondensacyjny kocioł gazowy. Koszty przygotowawcze nie przekraczają 5% kosztów kwalifikowanych. Koszt promocji nie przekracza 1% kosztów kwalifikowanych i wynosi nie więcej niż 10 000 zł. Przewidziano tryb zaprojektuj/wykonaj, ale Wnioskodawca wykazuje pełną gotowość do realizacji, bo pozyskał wszystkie wymagane do rozpoczęcia inwestycji zgłoszenia/pozwolenia budowlane. Zakres prac jest zgodny z katalogiem kosztów kwalifikowanych RPO WM 2014-2020. VAT jest wydatkiem niekwalifikowanym. Projekt cechuje bardzo korzystny wskaźnik nakład/rezultat. Realizacja zostanie przeprowadzona w poszanowaniu zasad horyzontalnych UE oraz z uwzględnieniem zasad tzw. uniwersalnego projektowania. Projekt jest zgodny z celem konkursu, wpisuje się w cele RPO WM 2014-2020 dla IV Osi priorytetowej, charakteryzuje go pozytywny wpływ na redukcje tzw. niskiej emisji tj. ponad 80% spadek emisji CO2, PM10, PM2,5. Projekt cechuje się wysoka wartością dodaną. Szczegóły w audytach, SW, AF i PFU. Dla projektu wykonano audyt energetyczny ex-ante celem precyzyjnego oszacowania kosztów i korzyści. (Polish)
    0 references
    The application is submitted by the entity authorised to provide support — the Po Świętone Commune from the area of Wołomiński, Mazowieckie Voivodeship. The project provides for the design and execution of a deep thermo-modernisation of five public buildings carrying out non-medical activities located in the Po Świętone Commune. Deep, efficient and RES activities are planned (photovoltaic power plant, heat pumps). More than 60 % improvement in energy efficiency will be achieved. The project is in line with the Low-Emission Economy Plan of the Holy Commune (PGN) and is a revitalisation project in accordance with the Local Program for Revitalisation of the Holy Commune (program included in the list of revitalisation programmes of the Mazowieckie Voivodeship at the date of submission of the application). The project to replace heating devices with RES (eHP heat pump), as well as replacing the old coal boiler with a condensing gas boiler. Preparatory costs shall not exceed 5 % of the eligible costs. The cost of the promotion does not exceed 1 % of the eligible costs and is not more than PLN 10,000. The design/execution mode is provided, but the Applicant shows full readiness to implement, because he has obtained all the building applications/permissions required to start the investment. The scope of work is in line with the catalogue of eligible costs of ROP WM 2014-2020. VAT is an ineligible expenditure. The project is characterised by a very favorable input/result ratio. Implementation will be carried out in accordance with the horizontal principles of the EU and taking into account the principles of so-called ‘universal design’. The project is in line with the aim of the competition, it is part of the objectives of the 2014-2020 ROP for Priority Axis IV, it is characterised by a positive impact on the reductions of the so-called low emissions, i.e. more than 80 % decrease in CO2, PM10, PM2,5 emissions. The project has a high added value. Details in audits, SW, AF and PFU. An ex-ante energy audit was carried out for the project in order to accurately estimate the costs and benefits. (English)
    21 October 2022
    0 references
    WOJ.: MAZOWIECKIE, POW.: wołomiński
    0 references

    Identifiers

    RPMA.04.02.00-14-I166/20
    0 references