Photovoltaic power plant in ELEKTRO-LECH enterprise
Property / summary
 
The implementation of the project will consist of the construction of a PV installation with a capacity of 29.70 KWP with the planned use of the energy produced for its own needs. The installation will be located on the roof and on the ground. The project will be implemented in the period from 01.06.2022 to 31.08.2022. The effect of the project will be the installation of additional capacity for generating electricity from renewable sources, 1 company will receive support for the construction of an electricity generating unit from RES. Thanks to the implementation of the project, the annual electricity costs incurred by the Applicant will be reduced by min. PLN 30 thousand. (English)
Property / summary: The implementation of the project will consist of the construction of a PV installation with a capacity of 29.70 KWP with the planned use of the energy produced for its own needs. The installation will be located on the roof and on the ground. The project will be implemented in the period from 01.06.2022 to 31.08.2022. The effect of the project will be the installation of additional capacity for generating electricity from renewable sources, 1 company will receive support for the construction of an electricity generating unit from RES. Thanks to the implementation of the project, the annual electricity costs incurred by the Applicant will be reduced by min. PLN 30 thousand. (English) / rank
 
Normal rank
Property / summary: The implementation of the project will consist of the construction of a PV installation with a capacity of 29.70 KWP with the planned use of the energy produced for its own needs. The installation will be located on the roof and on the ground. The project will be implemented in the period from 01.06.2022 to 31.08.2022. The effect of the project will be the installation of additional capacity for generating electricity from renewable sources, 1 company will receive support for the construction of an electricity generating unit from RES. Thanks to the implementation of the project, the annual electricity costs incurred by the Applicant will be reduced by min. PLN 30 thousand. (English) / qualifier
 
point in time: 21 October 2022
Timestamp+2022-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:26, 21 October 2022

Project Q4419595 in Poland
Language Label Description Also known as
English
Photovoltaic power plant in ELEKTRO-LECH enterprise
Project Q4419595 in Poland

    Statements

    0 references
    54,411.43 zloty
    0 references
    12,095.66 Euro
    0 references
    98,929.89 zloty
    0 references
    21,992.11 Euro
    0 references
    55.0 percent
    0 references
    1 June 2022
    0 references
    30 November 2022
    0 references
    PRZEDSIĘBIORSTWO USŁUGOWO HANDLOWE "ELEKTRO-LECH" ŁUKASZ GRZEGORZ MISIEJUK
    0 references
    0 references
    Realizacja projektu będzie polegała na budowie instalacji PV o mocy 29,70 kWP z planowanym wykorzystaniem wyprodukowanej energii na własne potrzeby. Instalacja będzie umiejscowiona na dachu oraz na gruncie. Projekt będzie realizowany w okresie od 01.06.2022 do 31.08.2022 r. Efektem realizacji projektu będzie instalacja dodatkowych zdolności wytwarzania energii elektrycznej ze źródeł odnawialnych, 1 przedsiębiorstwo otrzyma wsparcie na budowę jednostki wytwarzania energii elektrycznej z OZE.Dzięki realizacji projektu roczne koszty energii elektrycznej ponoszone przez Wnioskodawcę ulegną zmniejszeniu o min. 30 tys. zł. (Polish)
    0 references
    The implementation of the project will consist of the construction of a PV installation with a capacity of 29.70 KWP with the planned use of the energy produced for its own needs. The installation will be located on the roof and on the ground. The project will be implemented in the period from 01.06.2022 to 31.08.2022. The effect of the project will be the installation of additional capacity for generating electricity from renewable sources, 1 company will receive support for the construction of an electricity generating unit from RES. Thanks to the implementation of the project, the annual electricity costs incurred by the Applicant will be reduced by min. PLN 30 thousand. (English)
    21 October 2022
    0 references
    WOJ.: LUBELSKIE, POW.: parczewski
    0 references
    0 references

    Identifiers

    RPLU.15.01.00-06-0083/22
    0 references