Property / co-financing rate
55.0 percent
Amount55.0 percent
Unitpercent
 
Property / co-financing rate: 55.0 percent / rank
Normal rank
 
Property / budget
13,308,938.0 forint
Amount13,308,938.0 forint
Unitforint
 
Property / budget: 13,308,938.0 forint / rank
Normal rank
 
Property / budget
37,624.37 Euro
Amount37,624.37 Euro
UnitEuro
 
Property / budget: 37,624.37 Euro / rank
Preferred rank
 
Property / budget: 37,624.37 Euro / qualifier
exchange rate to Euro: 0.002827 Euro
Amount0.002827 Euro
UnitEuro
 
Property / budget: 37,624.37 Euro / qualifier
point in time: 13 February 2022
Timestamp+2022-02-13T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0
 
Property / EU contribution
7,319,915.0 forint
Amount7,319,915.0 forint
Unitforint
 
Property / EU contribution: 7,319,915.0 forint / rank
Normal rank
 
Property / EU contribution
20,693.4 Euro
Amount20,693.4 Euro
UnitEuro
 
Property / EU contribution: 20,693.4 Euro / rank
Preferred rank
 
Property / EU contribution: 20,693.4 Euro / qualifier
exchange rate to Euro: 0.002827 Euro
Amount0.002827 Euro
UnitEuro
 
Property / EU contribution: 20,693.4 Euro / qualifier
point in time: 13 February 2022
Timestamp+2022-02-13T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0
 

Revision as of 22:23, 14 February 2022

Project Q3933723 in Hungary
Language Label Description Also known as
English
INSTALLATION OF SOLAR SYSTEM AT NATURALPLAST KFT.
Project Q3933723 in Hungary

    Statements

    0 references
    1 March 2021
    0 references
    30 September 2021
    0 references
    NATURALPLAST Ipari és Kereskedelmi Korlátolt Felelősségü Társaság
    0 references
    0 references

    47°26'35.27"N, 21°23'25.08"E
    0 references
    A fejlesztés célterülete: Napelemes rendszer telepítése hálózati villamosenergia-termelés céljából. Előkészítő tevékenységek: - A fejlesztés céljának meghatározását követően – függetlenül a támogatási lehetőségtől- megtörtént a tájékozódás a megvalósíthatóság körülményeiről, lehetőségeiről. – Több potenciális kivitelezővel történtek tárgyalások. – Kiválasztásra került a legalkalmasabb - és egyben a legköltséghatékonyabb megoldást kínáló- kivitelező: az E.ON Energiakereskedelmi Kft., mely cég esetében a szakmaiság biztosított, az E.ON csoport tagjaként vélelmezhetően a teljes megvalósítás kockázata minimalizálható. – A kiválasztott kivitelező „kulcsrakész” kivitelezést vállal, melyhez kapcsolódóan indikatív árajánlatot és műszaki anyagokat biztosított a pályázat műszaki részének összeállításához. – Statikai szakvélemény készült. - Energetikai szakértő a jelen és a tervezett állapotra vonatkozóan energetikai tanúsítványt készített. – Építész elkészítette a építész műszaki leírást. – A projekt megkezdését megelőzően elvégzendő építési munkák – palacsere- tekintetében kivitelezővel előzetes egyeztetések történtek. –Kiválasztásra került a műszaki ellenőr személye. A Projekt megvalósításának lépései: 1. A kiválasztott kivitelezővel kapcsolatfelvétel, szerződéses feltételek letárgyalása, szerződéskötés-kivitelezésre. 2. Műszaki ellenőrrel szerződéskötés. 3. Építési kivitelezés – a rendszerre való csatlakozásig. Távfelügyeleti hozzáférés biztosítása. 4. Műszaki ellenőr –által a teljesítés elfogadása, megfelelőség igazolása. A Projekt menedzselésében belső és külső szakemberek vesznek részt. A NATURALPLAST Kft. vezetőinek támogatott projektek és építési beruházásban van tapasztalatuk, napelem telepítésében nincs, de ez felhasználói oldalon nem is várható el. A közreműködő szakembereknek - köztük a kivitelezéssel megbízandó E.ON Energiaiker. Kft-nek- viszont ez a profilja, ezért nagy tapasztalattal rendelkeznek a megvalósítandó technológia terén. Projektelemek: Egyszerűsített energetikai fejlesztés: Napelemes rendszer telepítése a NATURALPLAST Kft. székhelyén és tulajdonában lévő üzemi épületcsoport épületeire: 1. műhely; 2. raktár. A beépítésre kerülő eszközök és az alkalmazott technológiát helyszíni felmérést követően az E.ON Energiakereskedelmi Kft. határozta meg, az alábbiak szerint: 158 db JA Solar 315W MONO panel; SolarEdge SE 25K+wifi + SolarEdge SE 17K+wifi inverter; 79 db SolarEdge P650 optimalizáló + wifi; ferde tetőre szerelt tartószerkezet - egy speciális rozsdamentes anyagból készült szabványos német gyártmányú fém váz. Az eszközök újak, beszerzésük a Felhívásban meghatározott szállítóktól történik. A kiépítendő rendszer teljesítménye: 49,77 kWp, hálózati energiatermelésre alkalmas rendszer. A rendszer bekötésre kerül az E.ON hálózatába. A távfelügyelet és monitoring biztosított. A kiépítendő rendszer magas szintű technológiát és technikai színvonat képvisel; és megvalósítja a Projekt célját. /Az Építési tervdokumentáció részben csatolva műszaki-technológiai leírás, termékismertető, kapcsolási rajz és a megvalósulást bemutató 3 D látványtervek./ (Hungarian)
    0 references
    Target area of development: Installation of a solar system for electricity generation in the grid. Preparatory activities: — After defining the purpose of the development, irrespective of the possibility of aid, information was made on the conditions and possibilities of feasibility. — Negotiations have taken place with a number of potential contractors. — The most suitable contractor and the most cost-effective solution have been selected: as a member of the E.ON Group, E.ON Energiakereskedelmi Kft., for which professionalism is ensured, can be presumed to minimise the risk of full implementation. — The selected contractor undertakes “turnkey” execution, in connection with which he provided an indicative quote and technical material for the compilation of the technical part of the tender. — A static report has been prepared. — Energy expert has prepared an energy certificate for the present and planned state. — Architect has drawn up a technical description of the architect. — Preliminary consultations with the contractor concerning the works to be carried out before the start of the project — shale replacement. —The identity of the technical inspector has been selected. Steps to implement the project: 1. Contact the selected contractor, negotiate contractual conditions, conclude contracts. 2. Contracting with a technical inspector. 3. Construction work — until connection to the system. Provision of remote surveillance access. 4. Technical inspector by accepting performance and attesting conformity. Internal and external experts are involved in the management of the project. The managers of NATURALPLAST Ltd. have experience of supported projects and works, they do not have any solar panel installation, but this cannot be expected on the user side. E.ON Energiaiker to be entrusted to the involved professionals, including the implementation. However, this is the profile of Kft., so they have extensive experience in the field of the technology to be implemented. Project elements: Simplified energy development: Installation of a solar system on the buildings of the plant building group located and owned by NATURALPLAST Kft.: Workshop 1; 2nd Warehouse. The devices to be installed and the technology used were determined by E.ON Energiakereskedelmi Kft., following an on-site survey, as follows: 158 pcs JA Solar 315 W MONO panel; SolarEdge SE 25K+wifi + SolarEdge SE 17K+wifi inverter; 79 Pcs SolarEdge P650 Optimiser + Wi-Fi; frame mounted on an oblique roof — a standard German-made metal frame made of special stainless material. The equipment is new and purchased from the suppliers specified in the call. Performance of the system to be installed: 49.77 kWp, network power generation system. The system is connected to the E.ON network. Remote monitoring and monitoring is ensured. The system to be built represents a high level of technology and a technical colour train; and achieve the goal of the Project. /The construction design documentation is partly accompanied by technical and technological description, product description, wiring diagram and 3 D visual designs showing the realisation./ (English)
    8 February 2022
    0 references
    Domaine cible de développement: Installation d’un système solaire pour la production d’électricité dans le réseau. Activités préparatoires: — Après avoir défini l’objectif du développement, indépendamment de la possibilité d’une aide, des informations ont été fournies sur les conditions et les possibilités de faisabilité. — Des négociations ont eu lieu avec un certain nombre de contractants potentiels. — Le contractant le plus approprié et la solution la plus rentable ont été sélectionnés: en tant que membre du groupe E.ON, E.ON Energiakereskedelmi Kft., pour lequel le professionnalisme est assuré, peut être présumé minimiser le risque de mise en œuvre intégrale. — Le contractant retenu procède à l’exécution «clé en main», dans le cadre de laquelle il a fourni un devis indicatif et du matériel technique pour l’élaboration de la partie technique de l’offre. — Un rapport statique a été préparé. — Un expert en énergie a préparé un certificat énergétique pour l’état actuel et prévu. — Architecte a établi une description technique de l’architecte. — Consultations préliminaires avec le contractant concernant les travaux à réaliser avant le début du projet — remplacement du schiste. —L’identité de l’inspecteur technique a été sélectionnée. Étapes de la mise en œuvre du projet: 1. Contacter le contractant sélectionné, négocier les conditions contractuelles, conclure des contrats. 2. Contrat avec un inspecteur technique. 3. Travaux de construction — jusqu’à la connexion au système. Fourniture d’un accès à la surveillance à distance. 4. Inspecteur technique en acceptant les performances et en attestant la conformité. Des experts internes et externes participent à la gestion du projet. Les gestionnaires de NATURALPLAST Ltd. ont de l’expérience des projets et des travaux soutenus, ils n’ont pas d’installation de panneaux solaires, mais cela ne peut être attendu du côté de l’utilisateur. E.ON Energiaiker sera confié aux professionnels concernés, y compris la mise en œuvre. Cependant, c’est le profil de Kft., ils ont donc une vaste expérience dans le domaine de la technologie à mettre en œuvre. Éléments du projet: Développement énergétique simplifié: Installation d’un système solaire sur les bâtiments du groupe de bâtiments de l’usine situé et détenu par NATURALPLAST Kft.: Atelier 1; 2e Entrepôt. Les appareils à installer et la technologie utilisée ont été déterminés par E.ON Energiakereskedelmi Kft., à la suite d’un relevé sur place, comme suit: 158 PCs JA Solar 315 W MONO panneau; SolarEdge SE 25K+wifi + onduleur SolarEdge SE 17K+wifi; 79 PC SolarEdge P650 Optimizer + Wi-Fi; cadre monté sur un toit oblique — un cadre standard en métal allemand en matériau inoxydable spécial. L’équipement est neuf et acheté auprès des fournisseurs spécifiés dans l’appel. Performances du système à installer: 49,77 kWp, système de production d’électricité du réseau. Le système est connecté au réseau E.ON. La surveillance et la surveillance à distance sont assurées. Le système à construire représente un haut niveau de technologie et un train de couleurs techniques; et atteindre l’objectif du projet. /La documentation de conception de construction est en partie accompagnée d’une description technique et technologique, d’une description du produit, d’un schéma de câblage et de conceptions visuelles 3D montrant la réalisation./ (French)
    10 February 2022
    0 references
    Hajdúszoboszló, Hajdú-Bihar
    0 references

    Identifiers

    GINOP-4.1.4-19-2019-00143
    0 references