Our electricity supply is achieved from 2 separate transformers through 2 separate measuring points. As part of the second phase, we would like to install a 150 kW system for storage rooms on 026/280 hrs (8441 Márkó Iparos u. 6). (English)
Property / summary: Our electricity supply is achieved from 2 separate transformers through 2 separate measuring points. As part of the second phase, we would like to install a 150 kW system for storage rooms on 026/280 hrs (8441 Márkó Iparos u. 6). (English) / rank
 
Normal rank
Property / summary: Our electricity supply is achieved from 2 separate transformers through 2 separate measuring points. As part of the second phase, we would like to install a 150 kW system for storage rooms on 026/280 hrs (8441 Márkó Iparos u. 6). (English) / qualifier
 
point in time: 8 February 2022
Timestamp+2022-02-08T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 21:33, 8 February 2022

Project Q3933646 in Hungary
Language Label Description Also known as
English
Installation of a solar system on the warehouse buildings of Reál-M Kft. Phase II
Project Q3933646 in Hungary

    Statements

    0 references
    44,955,975 forint
    0 references
    124,312.71 Euro
    0.00276521 Euro
    3 December 2021
    0 references
    223,441.462 Euro
    0.0027336256 Euro
    15 December 2021
    0 references
    81,738,136.364 forint
    0 references
    54.999999 percent
    0 references
    15 October 2020
    0 references
    31 October 2021
    0 references
    REÁL-M Kereskedelmi és Szolgáltató Korlátolt Felelősségű Társaság
    0 references
    0 references

    47°8'33.40"N, 17°48'51.30"E
    0 references
    Villamos energia ellátásunkat 2 külön trafóról 2 külön mérési ponton keresztül valósítjuk meg. A második ütem keretében a 026/280 hrsz -en (8441 Márkó Iparos u. 6. szám alatt lévő) levő raktárhelyiségek esetében egy 150 kW-os rendszert kívánunk telepíteni. (Hungarian)
    0 references
    Our electricity supply is achieved from 2 separate transformers through 2 separate measuring points. As part of the second phase, we would like to install a 150 kW system for storage rooms on 026/280 hrs (8441 Márkó Iparos u. 6). (English)
    8 February 2022
    0 references
    Márkó, Veszprém
    0 references

    Identifiers

    GINOP-4.1.4-19-2019-00051
    0 references