URGENT WORK TO SECURE, RESTORE AND CONSOLIDATE AS A RESULT OF AN EMERGENCY RESPONSE TO THE SAFETY, REHABILITATION AND REHABILITATION OF THE S. P. 143 MOUNTAIN AREA AND ABATEMARCO, EMERGENCY CIVIL PROTECTION OPERATIONS. (Q2023237): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations)
(‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
label / delabel / de
 
DRINGENDE ANSTRENGUNGEN ZUR SICHERUNG, WIEDERHERSTELLUNG UND KONSOLIDIERUNG VON ERDRUTSCHEN AUF DEM SP 143 ZWISCHEN DEM BERG ANTILIA UND ABATEMARCO – DRINGENDE KATASTROPHENSCHUTZEINSÄTZE.
Property / summary
 
DIE INTERVENTION WIRD MIT DER SICHERUNG EINES TEILS DES STRASSENWEGS VON SP 143 IDENTIFIZIERT, DAS AN DEN STÜTZSTRUKTUREN DER EINFAHRTSEBENE AN DER ERDRUTSCHBEWEGUNG TEILNIMMT, DIE DIE STRASSE IN MINDESTENS ZWEI PUNKTEN TRANCIANDOLA VOLLSTÄNDIG BEEINFLUSST. ES IST GEPLANT, EIN SCHOTT VON STÖCKEN ZU BAUEN, UM DEN VORDEREN ERDRUTSCH FLUSSABWÄRTS UND GABBIONATE MEHR EIN MONTE DURCH ARBEITEN ERGÄNZT, DIE FÜR EINE KORREKTE REGELUNG DES OBERFLÄCHENWASSERS. (German)
Property / summary: DIE INTERVENTION WIRD MIT DER SICHERUNG EINES TEILS DES STRASSENWEGS VON SP 143 IDENTIFIZIERT, DAS AN DEN STÜTZSTRUKTUREN DER EINFAHRTSEBENE AN DER ERDRUTSCHBEWEGUNG TEILNIMMT, DIE DIE STRASSE IN MINDESTENS ZWEI PUNKTEN TRANCIANDOLA VOLLSTÄNDIG BEEINFLUSST. ES IST GEPLANT, EIN SCHOTT VON STÖCKEN ZU BAUEN, UM DEN VORDEREN ERDRUTSCH FLUSSABWÄRTS UND GABBIONATE MEHR EIN MONTE DURCH ARBEITEN ERGÄNZT, DIE FÜR EINE KORREKTE REGELUNG DES OBERFLÄCHENWASSERS. (German) / rank
 
Normal rank
Property / summary: DIE INTERVENTION WIRD MIT DER SICHERUNG EINES TEILS DES STRASSENWEGS VON SP 143 IDENTIFIZIERT, DAS AN DEN STÜTZSTRUKTUREN DER EINFAHRTSEBENE AN DER ERDRUTSCHBEWEGUNG TEILNIMMT, DIE DIE STRASSE IN MINDESTENS ZWEI PUNKTEN TRANCIANDOLA VOLLSTÄNDIG BEEINFLUSST. ES IST GEPLANT, EIN SCHOTT VON STÖCKEN ZU BAUEN, UM DEN VORDEREN ERDRUTSCH FLUSSABWÄRTS UND GABBIONATE MEHR EIN MONTE DURCH ARBEITEN ERGÄNZT, DIE FÜR EINE KORREKTE REGELUNG DES OBERFLÄCHENWASSERS. (German) / qualifier
 
point in time: 24 December 2021
Timestamp+2021-12-24T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 00:20, 24 December 2021

Project Q2023237 in Italy
Language Label Description Also known as
English
URGENT WORK TO SECURE, RESTORE AND CONSOLIDATE AS A RESULT OF AN EMERGENCY RESPONSE TO THE SAFETY, REHABILITATION AND REHABILITATION OF THE S. P. 143 MOUNTAIN AREA AND ABATEMARCO, EMERGENCY CIVIL PROTECTION OPERATIONS.
Project Q2023237 in Italy

    Statements

    0 references
    337,500.0 Euro
    0 references
    450,000.0 Euro
    0 references
    75.0 percent
    0 references
    3 October 2016
    0 references
    29 October 2018
    0 references
    PROVINCIA DI SALERNO
    0 references
    0 references

    40°9'44.28"N, 15°21'55.66"E
    0 references
    L'INTERVENTO SI IDENTIFICA CON LA MESSA IN SICUREZZA DI PORZIONE DEL TRACCIATO STRADALE DELLA SP 143, INTERVENENDO SULLE STRUTTURE DI SOSTEGNO DEL PIANO CARRABILE IN CORRISPONDENZA DEL MOVIMENTO FRANOSO CHE INTERESSA LA STRADA IN ALMENO DUE PUNTI TRANCIANDOLA COMPLETAMENTE. SI PREVEDE LA REALIZZAZIONE DI UNA PARATIA DI PALI A CONTENIMENTO DEL FRONTE FRANA A VALLE E GABBIONATE PIù A MONTE COMPLETATE DA OPERE ATTE AD UNA CORRETTA REGIMENTAZIONE DELLE ACQUE SUPERFICIALI. (Italian)
    0 references
    THE AIM OF THE INTERVENTION IS TO SECURE PART OF THE ROAD SECTION OF THE SP 143 BY ACTING ON THE SUPPORT STRUCTURES OF THE PLANE RACK IN CONNECTION WITH THE BREAKOUT MOVEMENT, WHICH AFFECTS THE ROAD IN AT LEAST TWO POINTS OF THE ROAD, WHICH COVERS THE ROAD IN AT LEAST TWO PARTS OF THE ROAD. A PARTITION OF STAKES IS TO BE CARRIED OUT IN ORDER TO CURB THE VALLEY AND WILL COMBINE UP TO AN EARLIER STAGE BY WORKS WHICH ARE SUITABLE FOR THE PROPER MANAGEMENT OF SURFACE WATERS. (English)
    0 references
    L’INTERVENTION EST IDENTIFIÉE AVEC LA FIXATION D’UNE PARTIE DE LA ROUTE DE LA SP 143, INTERVENANT SUR LES STRUCTURES DE SUPPORT DE L’AVION DE L’ALLÉE AU MOUVEMENT DE GLISSEMENT DE TERRAIN AFFECTANT LA ROUTE EN AU MOINS DEUX POINTS TRANCIANDOLA COMPLÈTEMENT. IL EST PRÉVU DE CONSTRUIRE UNE CLOISON DE POTEAUX POUR CONTENIR LE GLISSEMENT DE TERRAIN AVANT EN AVAL ET GABBIONATE PLUS UN MONTE COMPLÉTÉ PAR DES TRAVAUX ADAPTÉS À UN RÉGIME CORRECT D’EAU DE SURFACE. (French)
    14 December 2021
    0 references
    DE INTERVENTIE WORDT GEÏDENTIFICEERD MET HET VASTZETTEN VAN EEN DEEL VAN HET WEGPAD VAN SP 143, DAT OP DE ONDERSTEUNENDE STRUCTUREN VAN HET OPRITVLAK BIJ DE AARDVERSCHUIVING VOLLEDIG VAN INVLOED IS OP DE WEG OP TEN MINSTE TWEE PUNTEN TRANCIANDOLA. HET IS DE BEDOELING OM EEN SCHOT VAN PALEN TE BOUWEN OM DE VOORSTE AARDVERSCHUIVING STROOMAFWAARTS TE BEVATTEN EN GABBIONATE MEER EEN MONTE, AANGEVULD MET WERKEN DIE GESCHIKT ZIJN VOOR EEN CORRECT BEHEER VAN OPPERVLAKTEWATER. (Dutch)
    23 December 2021
    0 references
    DIE INTERVENTION WIRD MIT DER SICHERUNG EINES TEILS DES STRASSENWEGS VON SP 143 IDENTIFIZIERT, DAS AN DEN STÜTZSTRUKTUREN DER EINFAHRTSEBENE AN DER ERDRUTSCHBEWEGUNG TEILNIMMT, DIE DIE STRASSE IN MINDESTENS ZWEI PUNKTEN TRANCIANDOLA VOLLSTÄNDIG BEEINFLUSST. ES IST GEPLANT, EIN SCHOTT VON STÖCKEN ZU BAUEN, UM DEN VORDEREN ERDRUTSCH FLUSSABWÄRTS UND GABBIONATE MEHR EIN MONTE DURCH ARBEITEN ERGÄNZT, DIE FÜR EINE KORREKTE REGELUNG DES OBERFLÄCHENWASSERS. (German)
    24 December 2021
    0 references

    Identifiers

    H47H14002270006
    0 references