Reconstruction of the power grid with SN and NN voltages allowing connection of electricity generation units from RES in Tarnów and Nowy Sądecki districts (Q112106): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations)
(‎Changed label, description and/or aliases in it, and other parts: Adding Italian translations)
label / itlabel / it
 
Ricostruzione della rete elettrica con una tensione di SN e NN che consente la connessione di unità di produzione di energia elettrica da fonti rinnovabili nei distretti di Tarnów e Nowysądecki
Property / summary
 
L'attuazione del progetto garantirà il corretto funzionamento delle reti elettriche in determinate località del distretto di Tarnów e del distretto di Nowy Sądeckie, ampliando la possibilità di collegare nuove unità di produzione di energia elettrica da fonti rinnovabili in dispersione. Nei comuni in cui si trova il progetto è previsto un aumento significativo del numero di impianti FER che producono energia elettrica. Il progetto consiste in sei compiti per ricostruire la rete a bassa tensione con il necessario cut-off della rete media napięcia:Zadanie 1. Aggiornamento della rete nN alimentata da Bujne TRTS545;Task 2. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 5 S758 e della rete nN e SN;Task 3. Modernizzazione della rete nN alimentata dalla stazione di trasformazione TRTS531 Dzierżaniny 4; Compito 4. Ammodernamento della rete nN alimentata dalla stazione di trasformazione Jastrzębia 5 Trts 588; Task 5. Ammodernamento della stazione di trasformazione TRTS755 Rzepiennik Biskupi 2 e delle reti NN e SN;Task 6. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 6 TRTS759 e delle reti nN e SN. L'aumento delle sezioni trasversali della rete e l'ammodernamento delle stazioni di trasformazione permetteranno di aumentare la potenza di connessione del RES. I compiti mirano anche a migliorare le condizioni di approvvigionamento dei singoli clienti alimentati dalla rete nN e a migliorare la certezza dell'approvvigionamento dei clienti, effettuando ulteriori connessioni delle reti nN potenziate alle reti alimentate da altre stazioni di trasformazione. Gli investimenti consentiranno al richiedente di gestire in modo più efficace l'energia elettrica prodotta da FER.Soluzioni tecniche e architettoniche selezionate, ricostruzione e costruzione di linee aeree e, ove necessario, cavi sono soluzioni sviluppate durante le trattative con i proprietari terrieri. Sono state selezionate le soluzioni più convenienti e allo stesso tempo accettabili dai proprietari terrieri. Continuato al punto Q. (Italian)
Property / summary: L'attuazione del progetto garantirà il corretto funzionamento delle reti elettriche in determinate località del distretto di Tarnów e del distretto di Nowy Sądeckie, ampliando la possibilità di collegare nuove unità di produzione di energia elettrica da fonti rinnovabili in dispersione. Nei comuni in cui si trova il progetto è previsto un aumento significativo del numero di impianti FER che producono energia elettrica. Il progetto consiste in sei compiti per ricostruire la rete a bassa tensione con il necessario cut-off della rete media napięcia:Zadanie 1. Aggiornamento della rete nN alimentata da Bujne TRTS545;Task 2. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 5 S758 e della rete nN e SN;Task 3. Modernizzazione della rete nN alimentata dalla stazione di trasformazione TRTS531 Dzierżaniny 4; Compito 4. Ammodernamento della rete nN alimentata dalla stazione di trasformazione Jastrzębia 5 Trts 588; Task 5. Ammodernamento della stazione di trasformazione TRTS755 Rzepiennik Biskupi 2 e delle reti NN e SN;Task 6. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 6 TRTS759 e delle reti nN e SN. L'aumento delle sezioni trasversali della rete e l'ammodernamento delle stazioni di trasformazione permetteranno di aumentare la potenza di connessione del RES. I compiti mirano anche a migliorare le condizioni di approvvigionamento dei singoli clienti alimentati dalla rete nN e a migliorare la certezza dell'approvvigionamento dei clienti, effettuando ulteriori connessioni delle reti nN potenziate alle reti alimentate da altre stazioni di trasformazione. Gli investimenti consentiranno al richiedente di gestire in modo più efficace l'energia elettrica prodotta da FER.Soluzioni tecniche e architettoniche selezionate, ricostruzione e costruzione di linee aeree e, ove necessario, cavi sono soluzioni sviluppate durante le trattative con i proprietari terrieri. Sono state selezionate le soluzioni più convenienti e allo stesso tempo accettabili dai proprietari terrieri. Continuato al punto Q. (Italian) / rank
 
Normal rank
Property / summary: L'attuazione del progetto garantirà il corretto funzionamento delle reti elettriche in determinate località del distretto di Tarnów e del distretto di Nowy Sądeckie, ampliando la possibilità di collegare nuove unità di produzione di energia elettrica da fonti rinnovabili in dispersione. Nei comuni in cui si trova il progetto è previsto un aumento significativo del numero di impianti FER che producono energia elettrica. Il progetto consiste in sei compiti per ricostruire la rete a bassa tensione con il necessario cut-off della rete media napięcia:Zadanie 1. Aggiornamento della rete nN alimentata da Bujne TRTS545;Task 2. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 5 S758 e della rete nN e SN;Task 3. Modernizzazione della rete nN alimentata dalla stazione di trasformazione TRTS531 Dzierżaniny 4; Compito 4. Ammodernamento della rete nN alimentata dalla stazione di trasformazione Jastrzębia 5 Trts 588; Task 5. Ammodernamento della stazione di trasformazione TRTS755 Rzepiennik Biskupi 2 e delle reti NN e SN;Task 6. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 6 TRTS759 e delle reti nN e SN. L'aumento delle sezioni trasversali della rete e l'ammodernamento delle stazioni di trasformazione permetteranno di aumentare la potenza di connessione del RES. I compiti mirano anche a migliorare le condizioni di approvvigionamento dei singoli clienti alimentati dalla rete nN e a migliorare la certezza dell'approvvigionamento dei clienti, effettuando ulteriori connessioni delle reti nN potenziate alle reti alimentate da altre stazioni di trasformazione. Gli investimenti consentiranno al richiedente di gestire in modo più efficace l'energia elettrica prodotta da FER.Soluzioni tecniche e architettoniche selezionate, ricostruzione e costruzione di linee aeree e, ove necessario, cavi sono soluzioni sviluppate durante le trattative con i proprietari terrieri. Sono state selezionate le soluzioni più convenienti e allo stesso tempo accettabili dai proprietari terrieri. Continuato al punto Q. (Italian) / qualifier
 
point in time: 15 January 2022
Timestamp+2022-01-15T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 10:40, 15 January 2022

Project Q112106 in Poland
Language Label Description Also known as
English
Reconstruction of the power grid with SN and NN voltages allowing connection of electricity generation units from RES in Tarnów and Nowy Sądecki districts
Project Q112106 in Poland

    Statements

    0 references
    1,763,286.35 zloty
    0 references
    423,188.72 Euro
    13 January 2020
    0 references
    2,989,634.44 zloty
    0 references
    717,512.27 Euro
    13 January 2020
    0 references
    58.98 percent
    0 references
    25 February 2019
    0 references
    31 March 2020
    0 references
    TAURON DYSTRYBUCJA SPÓŁKA AKCYJNA
    0 references
    0 references
    Realizacja projektu zapewni prawidłowe funkcjonowanie sieci elektroenergetycznych na terenie wybranych miejscowości powiatu tarnowskiego i nowosądeckiego poszerzając możliwość przyłączania nowych jednostek wytwarzania energii elektrycznej ze źródeł odnawialnych w rozproszeniu. W gminach gdzie zlokalizowany jest projekt planowany jest znaczący wzrost ilości instalacji OZE wytwarzających energię elektryczną. Projekt składa się z sześciu zadań przebudowy sieci niskiego napięcia wraz z niezbędnym odcinakiem sieci średniego napięcia:Zadanie 1. Modernizacja sieci nN zasilanej ze stacji Bujne TRTS545;Zadanie 2. Modernizacja stacji transformatorowej Rzepiennik Biskupi 5 S758 oraz sieci nN i SN;Zadanie 3. Modernizacja sieci nN zasilanej ze stacji transformatorowej TRTS531 Dzierżaniny 4;Zadanie 4. Modernizacja sieci nN zasilanej ze stacji transformatorowej Jastrzębia 5 TRTS 588;Zadanie 5. Modernizacja stacji transformatorowej TRTS755 Rzepiennik Biskupi 2 oraz sieci nN i SN;Zadanie 6. Modernizacja stacji transformatorowej Rzepiennik Biskupi 6 TRTS759 oraz sieci nN i SN.Zwiększenie przekrojów sieci oraz modernizacja stacji transformatorowych pozwoli na zwiększenie mocy przyłączeniowej OZE. Zadania mają również na celu poprawę warunków zasilania odbiorców indywidualnych zasilanych z sieci nN oraz poprawę pewności zasilania odbiorców, poprzez wykonanie dodatkowych połączeń modernizowanych sieci nN z sieciami zasilanymi z innych stacji transformatorowych. Inwestycje pozwolą Wnioskodawcy skuteczniej zarządzać energią elektryczną wytworzoną z OZE.Wybrane rozwiązania techniczne oraz architektoniczne, przebudowa i budowa linii napowietrznych i tam gdzie było to konieczne kablowych, są rozwiązaniami wypracowanymi w toku negocjacji z właścicielami gruntów. Wybrano rozwiązania najbardziej korzystne kosztowo i jednocześnie akceptowalne przez właścicieli gruntów.Ciąg dalszy w punkcie Q. (Polish)
    0 references
    The implementation of the project will ensure the proper functioning of electricity networks in the selected towns of Tarnów and Nowy Sądecki districts, extending the possibility of connecting new units of electricity generation from renewable sources in dispersion. In municipalities where the project is located, a significant increase in the number of RES installations producing electricity is planned. The project consists of six tasks to rebuild the low-voltage network with the necessary cut-off of the medium voltage network:Task 1. Modernisation of the nN powered network from Bujne TRTS545;Task 2. Modernisation of the transformer station Rzepiennik Biskupi 5 S758 and NN and SN networks;Task 3. Modernisation of nN network powered from transformer station TRTS531 Lease 4;Task 4. Modernisation of the nN network powered from the hawk transformer station 5 TRTS 588;Task 5. Modernisation of the TRTS755 Transformer Station Biskupi 2 and NN and SN networks;Task 6. Modernisation of the transformer station Biskupi Rzepiennik 6 TRTS759 as well as nN and SN networks.Increasing network cross-sections and modernisation of transformer stations will increase the connection power of RES. The tasks are also aimed at improving the conditions for supplying individual customers powered from the nN network and improving the reliability of the power supply of the recipients by making additional connections of modernised nN networks with networks powered from other transformer stations. The investments will allow the Applicant to manage the electricity produced from RES more effectively.The selected technical and architectural solutions, reconstruction and construction of overhead lines and, where necessary, cable lines, are solutions developed in the course of negotiations with landowners. The most cost-effective and at the same time acceptable solutions were chosen by landowners. (English)
    20 October 2020
    0 references
    La mise en œuvre du projet garantira le bon fonctionnement des réseaux électriques dans certaines localités du district de Tarnów et du district de Nowy Sądeckie, en étendant la possibilité de raccorder de nouvelles unités de production d’électricité à partir de sources renouvelables en dispersion. Dans les municipalités où le projet est situé, une augmentation significative du nombre d’installations SER produisant de l’électricité est prévue. Le projet comprend six tâches visant à reconstruire le réseau basse tension avec la coupure nécessaire du réseau moyen napięcia:Zadanie 1. Mise à niveau du réseau nN alimenté par Bujne TRTS545;Tâche 2. Modernisation de la station de transformation Rzepiennik Biskupi 5 S758 et du réseau nN et SN;Tâche 3. Modernisation du réseau nN alimenté par la station de transformation TRTS531 Dzierżaniny 4;Tâche 4. Modernisation du réseau nN alimenté par la station de transformation Jastrzębia 5 Trts 588; tâche 5. Modernisation de la station de transformation TRTS755 Rzepiennik Biskupi 2 et des réseaux NN et SN;Tâche 6. Modernisation de la station de transformation Rzepiennik Biskupi 6 TRTS759 et des réseaux nN et SN. L’augmentation des sections transversales du réseau et la modernisation des stations de transformateurs permettront d’augmenter la puissance de raccordement des RES. Les tâches visent également à améliorer les conditions d’approvisionnement des clients individuels alimentés par le réseau nN et à améliorer la sécurité d’approvisionnement des clients, en effectuant des connexions supplémentaires des réseaux nN améliorés aux réseaux alimentés par d’autres stations de transformation. Les investissements permettront à la requérante de gérer plus efficacement l’électricité produite à partir des sources d’énergie renouvelables. Des solutions techniques et architecturales sélectionnées, la reconstruction et la construction de lignes aériennes et, le cas échéant, des câbles sont des solutions développées au cours des négociations avec les propriétaires fonciers. Les solutions les plus rentables et les plus acceptables ont été choisies par les propriétaires fonciers.Suite au point Q. (French)
    1 December 2021
    0 references
    Mit der Durchführung des Projekts wird das ordnungsgemäße Funktionieren der Stromnetze in ausgewählten Ortschaften des Bezirks Tarnów und des Bezirks Nowy Sądeckie sichergestellt, wodurch die Möglichkeit erweitert wird, neue Stromerzeugungsanlagen aus erneuerbaren Quellen in Streuung anzuschließen. In Gemeinden, in denen das Projekt angesiedelt ist, ist eine deutliche Erhöhung der Zahl der Strom erzeugenden EE-Anlagen geplant. Das Projekt besteht aus sechs Aufgaben zum Wiederaufbau des Niederspannungsnetzes mit dem notwendigen Cut-off des Medium Grid napięcia:Zadanie 1. Upgrade des nN-Netzes angetrieben von Bujne TRTS545;Task 2. Modernisierung der Transformatorstation Rzepiennik Biskupi 5 S758 und des Netzes nN und SN;Task 3. Modernisierung des nN-Netzes, das von der Transformatorstation TRTS531 Dzierżaniny 4 betrieben wird;Task 4. Modernisierung des nN-Netzes, das von der Transformatorstation Jastrzębia 5 Trts 588 betrieben wird; Aufgabe 5. Modernisierung der Transformatorstation TRTS755 Rzepiennik Biskupi 2 und der NN- und SN-Netze;Task 6. Modernisierung der Transformatorstation Rzepiennik Biskupi 6 TRTS759 sowie der Netze nN und SN. Durch die Erhöhung der Netzquerschnitte und Modernisierung der Transformatoren können die Anschlussleistung von RES erhöht werden. Die Aufgaben zielen auch darauf ab, die Versorgungsbedingungen einzelner Kunden, die aus dem nN-Netz angetrieben werden, zu verbessern und die Versorgungssicherheit der Kunden zu verbessern, indem zusätzliche Verbindungen von nN-Netzen zu den von anderen Transformatorenstationen betriebenen Netzen hergestellt werden. Die Investitionen werden es dem Antragsteller ermöglichen, den aus erneuerbaren Energiequellen erzeugten Strom effektiver zu verwalten.Ausgewählte technische und architektonische Lösungen, Wiederaufbau und Bau von Freileitungen und erforderlichenfalls Kabel sind Lösungen, die während der Verhandlungen mit den Grundbesitzern entwickelt wurden. Die kostengünstigsten und gleichzeitig akzeptablen Lösungen von Grundbesitzern wurden ausgewählt.Fortsetzung in Punkt Q. (German)
    7 December 2021
    0 references
    De uitvoering van het project zal zorgen voor een goede werking van de elektriciteitsnetten in bepaalde plaatsen van het district Tarnów en van het district Nowy Sądeckie, waarbij de mogelijkheid wordt uitgebreid om nieuwe eenheden voor elektriciteitsopwekking uit hernieuwbare bronnen in dispersie aan te sluiten. In gemeenten waar het project is gelegen, is een aanzienlijke toename van het aantal installaties voor de productie van elektriciteit uit hernieuwbare bronnen gepland. Het project bestaat uit zes taken om het laagspanningsnet te herbouwen met de noodzakelijke afsluiting van het medium grid napięcia:Zadanie 1. Upgraden van het nN-netwerk aangedreven door Bujne TRTS545;Task 2. Modernisering van het transformatorstation Rzepiennik Biskupi 5 S758 en het netwerk nN en SN;Task 3. Modernisering van het nN-netwerk aangedreven door het transformatorstation TRTS531 Dzierżaniny 4;Taak 4. Modernisering van het nN-netwerk aangedreven door het transformatorstation Jastrzębia 5 Trts 588; taak 5. Modernisering van het transformatorstation TRTS755 Rzepiennik Biskupi 2 en de NN- en SN-netwerken;Taak 6. Modernisering van het transformatorstation Rzepiennik Biskupi 6 TRTS759 en de nN- en SN-netwerken. Verhoging van de dwarsdoorsneden van het netwerk en modernisering van transformatorstations zal het mogelijk maken om het aansluitvermogen van RES te verhogen. De taken zijn ook gericht op het verbeteren van de leveringsvoorwaarden van individuele klanten die vanuit het nN-netwerk worden aangedreven en het verbeteren van de zekerheid van de levering van klanten, door het maken van extra verbindingen van opgewaardeerde nN-netwerken met de netwerken die door andere transformatorstations worden aangedreven. De investeringen zullen de aanvrager in staat stellen de elektriciteit die wordt geproduceerd uit hernieuwbare energiebronnen doeltreffender te beheren.Gekozen technische en architectonische oplossingen, wederopbouw en aanleg van bovengrondse lijnen en, waar nodig, kabels zijn oplossingen die tijdens onderhandelingen met grondeigenaren zijn ontwikkeld. De meest kosteneffectieve en tegelijkertijd aanvaardbare oplossingen van grondeigenaren zijn geselecteerd.Volgens punt Q. (Dutch)
    17 December 2021
    0 references
    L'attuazione del progetto garantirà il corretto funzionamento delle reti elettriche in determinate località del distretto di Tarnów e del distretto di Nowy Sądeckie, ampliando la possibilità di collegare nuove unità di produzione di energia elettrica da fonti rinnovabili in dispersione. Nei comuni in cui si trova il progetto è previsto un aumento significativo del numero di impianti FER che producono energia elettrica. Il progetto consiste in sei compiti per ricostruire la rete a bassa tensione con il necessario cut-off della rete media napięcia:Zadanie 1. Aggiornamento della rete nN alimentata da Bujne TRTS545;Task 2. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 5 S758 e della rete nN e SN;Task 3. Modernizzazione della rete nN alimentata dalla stazione di trasformazione TRTS531 Dzierżaniny 4; Compito 4. Ammodernamento della rete nN alimentata dalla stazione di trasformazione Jastrzębia 5 Trts 588; Task 5. Ammodernamento della stazione di trasformazione TRTS755 Rzepiennik Biskupi 2 e delle reti NN e SN;Task 6. Ammodernamento della stazione di trasformazione Rzepiennik Biskupi 6 TRTS759 e delle reti nN e SN. L'aumento delle sezioni trasversali della rete e l'ammodernamento delle stazioni di trasformazione permetteranno di aumentare la potenza di connessione del RES. I compiti mirano anche a migliorare le condizioni di approvvigionamento dei singoli clienti alimentati dalla rete nN e a migliorare la certezza dell'approvvigionamento dei clienti, effettuando ulteriori connessioni delle reti nN potenziate alle reti alimentate da altre stazioni di trasformazione. Gli investimenti consentiranno al richiedente di gestire in modo più efficace l'energia elettrica prodotta da FER.Soluzioni tecniche e architettoniche selezionate, ricostruzione e costruzione di linee aeree e, ove necessario, cavi sono soluzioni sviluppate durante le trattative con i proprietari terrieri. Sono state selezionate le soluzioni più convenienti e allo stesso tempo accettabili dai proprietari terrieri. Continuato al punto Q. (Italian)
    15 January 2022
    0 references

    Identifiers

    RPMP.04.01.02-12-0208/18
    0 references