THERMAL MODERNISATION OF PUBLIC BUILDINGS LOCATED IN LUBOCHNIA COMMUNE, I.E. SCHOOL AND PRESCHOOL BUILDING IN LUBOCHNI AND PUBLIC GYMNASIUM IN LUBOCHNI (Q101936): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations)
(‎Changed label, description and/or aliases in it, and other parts: Adding Italian translations)
label / itlabel / it
 
TERMOMODERNIZZAZIONE DI EDIFICI PUBBLICI SITUATI NEL COMUNE DI LUBOCHNIA, I.E. IL TEAM BUILDING SCOLASTICO E PRESCOLASTICO A LUBOCHNI E L'EDIFICIO PUBBLICO DELLE SCUOLE SUPERIORI JUNIOR A LUBOCHNI
Property / summary
 
L'obiettivo principale del progetto è in linea con gli obiettivi del POR 2014-2020, con l'obiettivo dell'asse prioritario IV "Economia a basse emissioni di carbonio" attuato nell'ambito dell'obiettivo tematico 4, "Sostenere la transizione verso un'economia a basse emissioni di carbonio in tutti i settori" e con l'obiettivo specifico 4.2. "L'obiettivo specifico dell'azione è migliorare l'efficienza energetica nel settore pubblico e nel settore dell'edilizia abitativa". L'obiettivo principale del progetto è: "Migliorare l'efficienza energetica degli edifici pubblici nel comune di Lubochnia". Essa sarà realizzata mediante il conseguimento degli obiettivi specifici di: ridurre il consumo energetico per il riscaldamento degli edifici pubblici, ridurre i costi energetici per gli edifici pubblici, aumentare l'isolamento termico degli edifici pubblici, decarbonizzare e ridurre la CO2. L'attuazione del progetto avrà un impatto positivo sull'ambiente a causa dello scopo e della portata dei lavori previsti volti a ridurre la domanda di energia e a ridurre le emissioni di gas nocivi nell'atmosfera attraverso l'uso di una fonte di energia rinnovabile — il progetto prevede l'utilizzo di una fonte alternativa sotto forma di pannelli fotovoltaici e pompe elettriche circolanti. Il gruppo destinatario del progetto è la comunità locale del comune di Lubochnia, vale a dire gli utenti delle strutture, in particolare gli studenti degli istituti interessati dal progetto, vale a dire il team scolastico e prescolare di Lubochnia e il ginnasio pubblico di Lubochnia, i genitori degli studenti, i dipendenti delle strutture e gli ospiti dall'esterno. Il progetto presuppone l'esecuzione di compiti, ad esempio: 1. Termomodernizzazione della costruzione della Scuola e del Team prescolare a Lubochnia, il costo del compito: 1 301 871,08 PLN lordo; 2. Termomodernizzazione dell'edificio della Palestra Pubblica di Lubochnia, il costo del compito: PLN 1 714 448,66 lordi; 3. Vigilanza degli investitori, costo del compito: 24 600,00 PLN lordo; 4. Promozione del progetto, costo delle attività: 3 259,50 PLN lordo. (Italian)
Property / summary: L'obiettivo principale del progetto è in linea con gli obiettivi del POR 2014-2020, con l'obiettivo dell'asse prioritario IV "Economia a basse emissioni di carbonio" attuato nell'ambito dell'obiettivo tematico 4, "Sostenere la transizione verso un'economia a basse emissioni di carbonio in tutti i settori" e con l'obiettivo specifico 4.2. "L'obiettivo specifico dell'azione è migliorare l'efficienza energetica nel settore pubblico e nel settore dell'edilizia abitativa". L'obiettivo principale del progetto è: "Migliorare l'efficienza energetica degli edifici pubblici nel comune di Lubochnia". Essa sarà realizzata mediante il conseguimento degli obiettivi specifici di: ridurre il consumo energetico per il riscaldamento degli edifici pubblici, ridurre i costi energetici per gli edifici pubblici, aumentare l'isolamento termico degli edifici pubblici, decarbonizzare e ridurre la CO2. L'attuazione del progetto avrà un impatto positivo sull'ambiente a causa dello scopo e della portata dei lavori previsti volti a ridurre la domanda di energia e a ridurre le emissioni di gas nocivi nell'atmosfera attraverso l'uso di una fonte di energia rinnovabile — il progetto prevede l'utilizzo di una fonte alternativa sotto forma di pannelli fotovoltaici e pompe elettriche circolanti. Il gruppo destinatario del progetto è la comunità locale del comune di Lubochnia, vale a dire gli utenti delle strutture, in particolare gli studenti degli istituti interessati dal progetto, vale a dire il team scolastico e prescolare di Lubochnia e il ginnasio pubblico di Lubochnia, i genitori degli studenti, i dipendenti delle strutture e gli ospiti dall'esterno. Il progetto presuppone l'esecuzione di compiti, ad esempio: 1. Termomodernizzazione della costruzione della Scuola e del Team prescolare a Lubochnia, il costo del compito: 1 301 871,08 PLN lordo; 2. Termomodernizzazione dell'edificio della Palestra Pubblica di Lubochnia, il costo del compito: PLN 1 714 448,66 lordi; 3. Vigilanza degli investitori, costo del compito: 24 600,00 PLN lordo; 4. Promozione del progetto, costo delle attività: 3 259,50 PLN lordo. (Italian) / rank
 
Normal rank
Property / summary: L'obiettivo principale del progetto è in linea con gli obiettivi del POR 2014-2020, con l'obiettivo dell'asse prioritario IV "Economia a basse emissioni di carbonio" attuato nell'ambito dell'obiettivo tematico 4, "Sostenere la transizione verso un'economia a basse emissioni di carbonio in tutti i settori" e con l'obiettivo specifico 4.2. "L'obiettivo specifico dell'azione è migliorare l'efficienza energetica nel settore pubblico e nel settore dell'edilizia abitativa". L'obiettivo principale del progetto è: "Migliorare l'efficienza energetica degli edifici pubblici nel comune di Lubochnia". Essa sarà realizzata mediante il conseguimento degli obiettivi specifici di: ridurre il consumo energetico per il riscaldamento degli edifici pubblici, ridurre i costi energetici per gli edifici pubblici, aumentare l'isolamento termico degli edifici pubblici, decarbonizzare e ridurre la CO2. L'attuazione del progetto avrà un impatto positivo sull'ambiente a causa dello scopo e della portata dei lavori previsti volti a ridurre la domanda di energia e a ridurre le emissioni di gas nocivi nell'atmosfera attraverso l'uso di una fonte di energia rinnovabile — il progetto prevede l'utilizzo di una fonte alternativa sotto forma di pannelli fotovoltaici e pompe elettriche circolanti. Il gruppo destinatario del progetto è la comunità locale del comune di Lubochnia, vale a dire gli utenti delle strutture, in particolare gli studenti degli istituti interessati dal progetto, vale a dire il team scolastico e prescolare di Lubochnia e il ginnasio pubblico di Lubochnia, i genitori degli studenti, i dipendenti delle strutture e gli ospiti dall'esterno. Il progetto presuppone l'esecuzione di compiti, ad esempio: 1. Termomodernizzazione della costruzione della Scuola e del Team prescolare a Lubochnia, il costo del compito: 1 301 871,08 PLN lordo; 2. Termomodernizzazione dell'edificio della Palestra Pubblica di Lubochnia, il costo del compito: PLN 1 714 448,66 lordi; 3. Vigilanza degli investitori, costo del compito: 24 600,00 PLN lordo; 4. Promozione del progetto, costo delle attività: 3 259,50 PLN lordo. (Italian) / qualifier
 
point in time: 15 January 2022
Timestamp+2022-01-15T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 08:47, 15 January 2022

Project Q101936 in Poland
Language Label Description Also known as
English
THERMAL MODERNISATION OF PUBLIC BUILDINGS LOCATED IN LUBOCHNIA COMMUNE, I.E. SCHOOL AND PRESCHOOL BUILDING IN LUBOCHNI AND PUBLIC GYMNASIUM IN LUBOCHNI
Project Q101936 in Poland

    Statements

    0 references
    1,988,506.02 zloty
    0 references
    477,241.44 Euro
    13 January 2020
    0 references
    2,339,418.85 zloty
    0 references
    561,460.52 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    31 August 2016
    0 references
    30 October 2017
    0 references
    GMINA LUBOCHNIA
    0 references

    51°36'32.0"N, 20°3'8.6"E
    0 references
    Cel główny projektu jest zgodny z założeniami RPO WŁ 2014-2020, z celem Osi priorytetowej IV „Gospodarka niskoemisyjna” realizowanej w ramach celu tematycznego 4 pn. „Wspieranie przejścia na gospodarkę niskoemisyjną we wszystkich sektorach” i z celem szczegółowym działania 4.2.: „Celem szczegółowym działania jest poprawiona efektywność energetyczna w sektorze publicznym i w sektorze budownictwa mieszkaniowego”. Cel główny projektu to: „Zwiększenie efektywności energetycznej budynków użyteczności publicznej w Gminie Lubochnia”. Zostanie on osiągnięty poprzez realizację celów szczegółowych, tj.: zmniejszenie zużycia energii do ogrzewania budynków publicznych, obniżenie kosztów związanych z obsługą energetyczną budynków publicznych, zwiększenie termoizolacyjności budynków publicznych, zmniejszenie emisyjności i redukcja CO2. Realizacja projektu będzie miała pozytywny wpływ na środowisko ze względu na cel i zakres planowanych prac, których celem jest zmniejszenie zapotrzebowania na energię i redukcję emisji szkodliwych gazów do atmosfery poprzez zastosowanie źródła energii odnawialnej – projekt zakłada wykorzystanie źródła alternatywnego w postaci paneli fotowoltaicznych oraz pomp obiegowych elektrycznych. Grupą docelową projektu jest społeczność lokalna gminy Lubochnia, tj. użytkownicy obiektów, tu w szczególności uczniowie placówek objętych projektem, czyli Zespołu Szkolno-Przedszkolnego w Lubochni oraz Publicznego Gimnazjum w Lubochni, rodzice uczniów, pracownicy obiektów, goście z zewnątrz. Projekt zakłada realizacje np. zadań: 1. Termomodernizacja budynku Zespołu Szkolno-Przedszkolnego w Lubochni, koszt zadania: 1 301 871,08 zł brutto; 2. Termomodernizacja budynku Publicznego Gimnazjum w Lubochni, koszt zadania: 1 714 448,66 zł brutto; 3. Nadzór inwestorski, koszt zadania: 24 600,00 zł brutto; 4. Promocja projektu, koszt zadania: 3 259,50 zł brutto. (Polish)
    0 references
    The main objective of the project is in line with the objectives of ROP WŁ 2014-2020, with the objective of Priority Axis IV “low carbon economy” implemented under the thematic objective 4 BC. “Supporting the transition to a low carbon economy in all sectors” and with the specific objective of Action 4.2: The specific objective is to improve energy efficiency in the public sector and in the housing sector. The main objective of the project is to: Increasing the energy efficiency of public utility buildings in Lubochnia Municipality. It will be achieved through the achievement of the specific objectives, i.e.: reduce energy consumption for heating public buildings, reduce costs related to the operation of public buildings, increase thermal insulation of public buildings, reduce emissions and reduce CO2. The implementation of the project will have a positive impact on the environment due to the objective and scope of the planned works aimed at reducing energy demand and reducing emissions of harmful gases into the atmosphere through the use of renewable energy sources – the project assumes the use of an alternative source in the form of photovoltaic panels and electric circulating pumps. The target group of the project is the local community of Lubochnia commune, i.e. users of facilities, in particular students of institutions covered by the project, i.e. the School and Preschool Complex in Lubochnia and the Public High School in Lubochnia, parents of pupils, employees of facilities, guests from outside. The project envisages implementation of e.g. tasks: 1. Thermal modernisation of the school and preschool complex building in Lubochnia, cost of the task: 1 301 871.08 PLN gross; 2. Thermal modernisation of the public gymnasium in Lubochnia, cost of the task: 1 714 448.66 PLN gross; 3. Investor supervision, cost of the task: 24 600.00 PLN gross; 4. Promotion of the project, cost of the task: 3 259.50 PLN gross. (English)
    17 October 2020
    0 references
    Le principal objectif du projet est conforme aux objectifs du plan d’action régional 2014-2020, avec l’objectif de l’axe prioritaire IV «Économie à faible intensité de carbone» mis en œuvre au titre de l’objectif thématique no 4, «Soutenir la transition vers une économie à faible intensité de carbone dans tous les secteurs» et avec l’objectif spécifique 4.2: «L’objectif spécifique de l’action est d’améliorer l’efficacité énergétique dans le secteur public et dans le secteur du logement». L’objectif principal du projet est de: «Amélioration de l’efficacité énergétique des bâtiments publics de la municipalité de Lubochnia». Elle sera réalisée par la réalisation des objectifs spécifiques suivants: réduire la consommation d’énergie pour le chauffage des bâtiments publics, réduire les coûts énergétiques des bâtiments publics, augmenter l’isolation thermique des bâtiments publics, décarboner et réduire le CO2. La mise en œuvre du projet aura un impact positif sur l’environnement en raison de l’objectif et de la portée des travaux prévus visant à réduire la demande d’énergie et à réduire les émissions de gaz nocifs dans l’atmosphère grâce à l’utilisation d’une source d’énergie renouvelable — le projet suppose l’utilisation d’une source alternative sous la forme de panneaux photovoltaïques et de pompes électriques à circulation. Le groupe cible du projet est la communauté locale de la municipalité de Lubochnia, c’est-à-dire les utilisateurs des installations, en particulier les étudiants des établissements couverts par le projet, c’est-à-dire l’équipe scolaire et préscolaire de Lubochnia et le gymnase public de Lubochnia, les parents d’étudiants, les employés des installations et les invités de l’extérieur. Le projet suppose la mise en œuvre de tâches telles que: 1. Thermomodernisation de la construction de l’école et de l’équipe préscolaire à Lubochnia, le coût de la tâche: 1 301 871,08 PLN brut; 2. Thermomodernisation de la construction du gymnase public à Lubochnia, le coût de la tâche: 1 714 448,66 PLN brut; 3. Surveillance des investisseurs, coût de la tâche: 24 600,00 PLN brut; 4. Promotion du projet, coût de la tâche: 3 259,50 PLN brut. (French)
    1 December 2021
    0 references
    Das Hauptziel des Projekts steht im Einklang mit den Zielen des ROP 2014-2020 mit dem Ziel der Prioritätsachse IV „Niedrige CO2-Emissionen“ im Rahmen des thematischen Ziels 4; „Unterstützung des Übergangs zu einer CO2-armen Wirtschaft in allen Sektoren“ und mit spezifischem Ziel 4.2: „Das spezifische Ziel der Maßnahme ist die Verbesserung der Energieeffizienz im öffentlichen Sektor und im Wohnungssektor“. Hauptziel des Projekts ist: Verbesserung der Energieeffizienz öffentlicher Gebäude in der Gemeinde Lubochnia. Sie wird erreicht, indem die spezifischen Ziele erreicht werden: Senkung des Energieverbrauchs für die Beheizung öffentlicher Gebäude, Senkung der Energiekosten für öffentliche Gebäude, Erhöhung der Wärmedämmung öffentlicher Gebäude, Dekarbonisierung und Verringerung der CO2-Emissionen. Die Durchführung des Projekts wird sich aufgrund des Zwecks und des Umfangs der geplanten Arbeiten positiv auf die Umwelt auswirken, um den Energiebedarf zu senken und die Emissionen schädlicher Gase in die Atmosphäre durch den Einsatz einer erneuerbaren Energiequelle zu reduzieren – das Projekt geht von der Nutzung einer alternativen Quelle in Form von Photovoltaik-Panels und elektrischen Umwälzpumpen aus. Zielgruppe des Projekts ist die lokale Gemeinde der Gemeinde Lubochnia, d. h. Nutzer der Einrichtungen, insbesondere Studenten der vom Projekt abgedeckten Einrichtungen, d. h. das Schul- und Vorschulteam in Lubochnia und das öffentliche Gymnasium in Lubochnia, Eltern von Studenten, Mitarbeiter der Einrichtungen und Gäste von außen. Das Projekt übernimmt z. B. Aufgaben: 1. Thermomodernisierung des Gebäudes des Schul- und Vorschulteams in Lubochnia, die Kosten für die Aufgabe: 1 301 871,08 PLN brutto; 2. Thermomodernisierung des Gebäudes des öffentlichen Gymnasiums in Lubochnia, die Kosten für die Aufgabe: 1 714 448,66 PLN brutto; 3. Anlegeraufsicht, Kosten der Aufgabe: 24 600,00 PLN brutto; 4. Projektförderung, Aufgabenkosten: 3 259,50 PLN brutto. (German)
    7 December 2021
    0 references
    De hoofddoelstelling van het project is in overeenstemming met de doelstellingen van het ROP 2014-2020, met de doelstelling van prioritaire as IV „Een koolstofarme economie” die in het kader van thematische doelstelling 4 wordt uitgevoerd; „Ondersteuning van de overgang naar een koolstofarme economie in alle sectoren” en met specifieke doelstelling 4.2: „De specifieke doelstelling van de actie is verbetering van de energie-efficiëntie in de overheidssector en in de woningsector”. De hoofddoelstelling van het project is: „Verbetering van de energie-efficiëntie van openbare gebouwen in de gemeente Lubochnia”. Het zal worden bereikt door de specifieke doelstellingen van: het energieverbruik voor het verwarmen van openbare gebouwen verminderen, de energiekosten voor openbare gebouwen verlagen, de thermische isolatie van openbare gebouwen verhogen, koolstofvrij maken en CO2 verminderen. De uitvoering van het project zal een positief effect hebben op het milieu als gevolg van het doel en de reikwijdte van de geplande werkzaamheden die gericht zijn op het verminderen van de energievraag en het verminderen van de uitstoot van schadelijke gassen in de atmosfeer door het gebruik van een hernieuwbare energiebron — het project gaat uit van het gebruik van een alternatieve bron in de vorm van fotovoltaïsche panelen en elektrische circulatiepompen. De doelgroep van het project is de lokale gemeenschap van de gemeente Lubochnia, d.w.z. gebruikers van de faciliteiten, met name studenten van de instellingen waarop het project betrekking heeft, d.w.z. het school- en kleuterteam in Lubochnia en het openbare gymnasium in Lubochnia, ouders van studenten, medewerkers van de faciliteiten en gasten van buitenaf. Het project gaat uit van de uitvoering van bijvoorbeeld taken: 1. Thermomodernisering van de bouw van het school- en kleuterteam in Lubochnia, de kosten van de taak: 1 301 871,08 PLN bruto; 2. Thermomodernisering van het gebouw van het openbare gymnasium in Lubochnia, de kosten van de taak: 1 714 448,66 PLN bruto; 3. Toezicht op beleggers, kosten van de taak: 24 600,00 PLN bruto; 4. Projectpromotie, taakkosten: 3 259,50 PLN bruto. (Dutch)
    17 December 2021
    0 references
    L'obiettivo principale del progetto è in linea con gli obiettivi del POR 2014-2020, con l'obiettivo dell'asse prioritario IV "Economia a basse emissioni di carbonio" attuato nell'ambito dell'obiettivo tematico 4, "Sostenere la transizione verso un'economia a basse emissioni di carbonio in tutti i settori" e con l'obiettivo specifico 4.2. "L'obiettivo specifico dell'azione è migliorare l'efficienza energetica nel settore pubblico e nel settore dell'edilizia abitativa". L'obiettivo principale del progetto è: "Migliorare l'efficienza energetica degli edifici pubblici nel comune di Lubochnia". Essa sarà realizzata mediante il conseguimento degli obiettivi specifici di: ridurre il consumo energetico per il riscaldamento degli edifici pubblici, ridurre i costi energetici per gli edifici pubblici, aumentare l'isolamento termico degli edifici pubblici, decarbonizzare e ridurre la CO2. L'attuazione del progetto avrà un impatto positivo sull'ambiente a causa dello scopo e della portata dei lavori previsti volti a ridurre la domanda di energia e a ridurre le emissioni di gas nocivi nell'atmosfera attraverso l'uso di una fonte di energia rinnovabile — il progetto prevede l'utilizzo di una fonte alternativa sotto forma di pannelli fotovoltaici e pompe elettriche circolanti. Il gruppo destinatario del progetto è la comunità locale del comune di Lubochnia, vale a dire gli utenti delle strutture, in particolare gli studenti degli istituti interessati dal progetto, vale a dire il team scolastico e prescolare di Lubochnia e il ginnasio pubblico di Lubochnia, i genitori degli studenti, i dipendenti delle strutture e gli ospiti dall'esterno. Il progetto presuppone l'esecuzione di compiti, ad esempio: 1. Termomodernizzazione della costruzione della Scuola e del Team prescolare a Lubochnia, il costo del compito: 1 301 871,08 PLN lordo; 2. Termomodernizzazione dell'edificio della Palestra Pubblica di Lubochnia, il costo del compito: PLN 1 714 448,66 lordi; 3. Vigilanza degli investitori, costo del compito: 24 600,00 PLN lordo; 4. Promozione del progetto, costo delle attività: 3 259,50 PLN lordo. (Italian)
    15 January 2022
    0 references

    Identifiers

    RPLD.04.02.02-10-0036/16
    0 references