Recovery of infrastructure related to fire damage of June 17, 2017 – Rehabilitation of Municipal Roads (Q2877858): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in de, and other parts: Adding German translations)
(‎Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations)
label / nllabel / nl
 
Herstel van infrastructuur in verband met brandschade van 17 juni 2017 — Revalidatie van gemeentelijke wegen
Property / summary
 
Herprogrammering in de tijd die wordt gerechtvaardigd door vertragingen in de loop van het contract als gevolg van ongunstige weersomstandigheden voor de uitvoering/terugwinning van openbare infrastructuur (wegwegen) die rechtstreeks door de branden wordt getroffen, die op 17 juni 2017 van start gaan. (Dutch)
Property / summary: Herprogrammering in de tijd die wordt gerechtvaardigd door vertragingen in de loop van het contract als gevolg van ongunstige weersomstandigheden voor de uitvoering/terugwinning van openbare infrastructuur (wegwegen) die rechtstreeks door de branden wordt getroffen, die op 17 juni 2017 van start gaan. (Dutch) / rank
 
Normal rank
Property / summary: Herprogrammering in de tijd die wordt gerechtvaardigd door vertragingen in de loop van het contract als gevolg van ongunstige weersomstandigheden voor de uitvoering/terugwinning van openbare infrastructuur (wegwegen) die rechtstreeks door de branden wordt getroffen, die op 17 juni 2017 van start gaan. (Dutch) / qualifier
 
point in time: 18 December 2021
Timestamp+2021-12-18T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 22:25, 18 December 2021

Project Q2877858 in Portugal
Language Label Description Also known as
English
Recovery of infrastructure related to fire damage of June 17, 2017 – Rehabilitation of Municipal Roads
Project Q2877858 in Portugal

    Statements

    0 references
    1,841,143.0 Euro
    0 references
    2,166,051.0 Euro
    0 references
    85.0 percent
    0 references
    14 May 2018
    0 references
    28 February 2020
    0 references
    MUNICÍPIO DE FIGUEIRÓ DOS VINHOS
    0 references
    Q2990814 (Deleted Item)
    0 references

    39°54'8.82"N, 8°16'31.08"W
    0 references
    Reprogramação temporal justificada pelos atrasos ocorridos no decurso da empreitada devido às condições climáticas adversas à execução/recuperação das infraestruturas públicas (Estradas rodoviárias) diretamente afetados pelos incêndios com início no dia 17 de junho de 2017. (Portuguese)
    0 references
    Time reprogramming justified by delays in the course of the undertaking due to adverse climatic conditions to the implementation/recovery of public infrastructure (road roads) directly affected by fires beginning on 17 June 2017. (English)
    7 July 2021
    0 references
    Reprogrammation temporelle justifiée par des retards dans l’exécution du contrat en raison de conditions météorologiques défavorables à la mise en œuvre/récupération des infrastructures publiques (routes routières) directement touchées par les incendies à compter du 17 juin 2017. (French)
    4 December 2021
    0 references
    Zeitliche Neuprogrammierung aufgrund von Verzögerungen im Vertragsverlauf aufgrund ungünstiger Witterungsbedingungen bei der Umsetzung/Wiederherstellung öffentlicher Infrastruktur (Straßenstraßen), die unmittelbar von den Bränden ab dem 17. Juni 2017 betroffen sind. (German)
    13 December 2021
    0 references
    Herprogrammering in de tijd die wordt gerechtvaardigd door vertragingen in de loop van het contract als gevolg van ongunstige weersomstandigheden voor de uitvoering/terugwinning van openbare infrastructuur (wegwegen) die rechtstreeks door de branden wordt getroffen, die op 17 juni 2017 van start gaan. (Dutch)
    18 December 2021
    0 references
    Figueiró dos Vinhos
    0 references

    Identifiers

    CENTRO-07-2316-FEDER-000111
    0 references