Implementation of the Operationality of the Liquid Grannel Terminal (Q2913355): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: modifying budgets in portugal one item from slovenia) |
(Changed label, description and/or aliases in fr, and other parts: Adding French translations) |
||||||||||||||
label / fr | label / fr | ||||||||||||||
Mise en œuvre de l’opérationnalité du terminal en vrac liquide | |||||||||||||||
Property / summary | |||||||||||||||
Cette opération consiste en l’exécution du contrat de mise en œuvre de l’exploitation des ponts nos 24, 25 et 26 du TGL du port d’Aveiro. Les principaux travaux à effectuer sont l’extension de la voie existante aux ponts de quai susmentionnés, la construction de réseaux de drainage des eaux de pluie et d’eau contaminée et la lutte contre les incendies. (French) | |||||||||||||||
Property / summary: Cette opération consiste en l’exécution du contrat de mise en œuvre de l’exploitation des ponts nos 24, 25 et 26 du TGL du port d’Aveiro. Les principaux travaux à effectuer sont l’extension de la voie existante aux ponts de quai susmentionnés, la construction de réseaux de drainage des eaux de pluie et d’eau contaminée et la lutte contre les incendies. (French) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: Cette opération consiste en l’exécution du contrat de mise en œuvre de l’exploitation des ponts nos 24, 25 et 26 du TGL du port d’Aveiro. Les principaux travaux à effectuer sont l’extension de la voie existante aux ponts de quai susmentionnés, la construction de réseaux de drainage des eaux de pluie et d’eau contaminée et la lutte contre les incendies. (French) / qualifier | |||||||||||||||
point in time: 6 December 2021
|
Revision as of 06:53, 6 December 2021
Project Q2913355 in Portugal
Language | Label | Description | Also known as |
---|---|---|---|
English | Implementation of the Operationality of the Liquid Grannel Terminal |
Project Q2913355 in Portugal |
Statements
1,419,886.0 Euro
0 references
1,670,454.0 Euro
0 references
85.0 percent
0 references
1 September 2017
0 references
31 December 2021
0 references
APA - ADMINISTRAÇÃO DO PORTO DE AVEIRO, S.A.
0 references
Esta operação consiste na execução da empreitada de implementação da operacionalidade das pontes cais n.º 24, n.º, 25 e n.º 26 do TGL do Porto de Aveiro. Os principais trabalhos a executar são o prolongamento da esteira existente até às referidas pontes cais e construção das redes de drenagem de águas pluviais e contaminadas e de combate a incêndios. (Portuguese)
0 references
This operation consists of the implementation of the construction of the operationality of the bridges Pier No. 24, No. 25, and No. 26 of the TGL of the Port of Aveiro. The main work to be carried out is the extension of the existing treadmill to the aforementioned pier bridges and the construction of rainwater drainage and contaminated and firefighting networks. (English)
8 July 2021
0 references
Cette opération consiste en l’exécution du contrat de mise en œuvre de l’exploitation des ponts nos 24, 25 et 26 du TGL du port d’Aveiro. Les principaux travaux à effectuer sont l’extension de la voie existante aux ponts de quai susmentionnés, la construction de réseaux de drainage des eaux de pluie et d’eau contaminée et la lutte contre les incendies. (French)
6 December 2021
0 references
Ílhavo, Gafanha da Nazaré