Installation of solar panels by the company ZHU and Gastracya Bogdan zopak to use solar energy for electricity generation. (Q131808): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Created claim: summary (P836): The investment consists of the purchase and installation of a photovoltaic power plant with a total power output of 36.14 kW at 2 locations: Piecki ul. 36H victory on plot No 1120 and at ul. Victory for 36K on plot No 1123. The project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to...)
Property / summary
 
The investment consists of the purchase and installation of a photovoltaic power plant with a total power output of 36.14 kW at 2 locations: Piecki ul. 36H victory on plot No 1120 and at ul. Victory for 36K on plot No 1123. The project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid, but due to the power of the installation (up to 40 kW) in accordance with Article 5 of the Renewable Energy Act (Journal of Laws 2015, item (478) and Article 7 (1) 8d with 4-9 Act — Energy Law (Journal of Laws 1997/54, item) (348) it will be made on the basis of the notification without the beneficiary having to have a valid technical connection for all the energy sources included in the project for electricity generation. The project fulfils all the conditions laid down in the SzocOP ROP WiM 2014-2020. This project involves the supply and installation of solar photovoltaic installations using polycrystalline technology for the production of electricity. The investment consists of the installation of a total of 139 photovoltaic panels with a combined output of 36.14 kW in separate systems with inverters and the necessary cabling and fittings. Solar panels are using solar radiation to convert solar radiation into electricity. By cable, they transmit energy to inverters where there is a change in direct current into alternating current. The plant will be connected to the grid and there will be no need to install batteries and recharging regulators as the network is capable of absorbing all the energy produced by the photovoltaic system. The electricity produced will be used directly for own account and any surplus will be entered into the grid. (English)
Property / summary: The investment consists of the purchase and installation of a photovoltaic power plant with a total power output of 36.14 kW at 2 locations: Piecki ul. 36H victory on plot No 1120 and at ul. Victory for 36K on plot No 1123. The project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid, but due to the power of the installation (up to 40 kW) in accordance with Article 5 of the Renewable Energy Act (Journal of Laws 2015, item (478) and Article 7 (1) 8d with 4-9 Act — Energy Law (Journal of Laws 1997/54, item) (348) it will be made on the basis of the notification without the beneficiary having to have a valid technical connection for all the energy sources included in the project for electricity generation. The project fulfils all the conditions laid down in the SzocOP ROP WiM 2014-2020. This project involves the supply and installation of solar photovoltaic installations using polycrystalline technology for the production of electricity. The investment consists of the installation of a total of 139 photovoltaic panels with a combined output of 36.14 kW in separate systems with inverters and the necessary cabling and fittings. Solar panels are using solar radiation to convert solar radiation into electricity. By cable, they transmit energy to inverters where there is a change in direct current into alternating current. The plant will be connected to the grid and there will be no need to install batteries and recharging regulators as the network is capable of absorbing all the energy produced by the photovoltaic system. The electricity produced will be used directly for own account and any surplus will be entered into the grid. (English) / rank
 
Normal rank

Revision as of 20:44, 10 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Installation of solar panels by the company ZHU and Gastracya Bogdan zopak to use solar energy for electricity generation.
Project in Poland financed by DG Regio

    Statements

    0 references
    184,314.0 zloty
    0 references
    44,235.36 Euro
    13 January 2020
    0 references
    267,057.6 zloty
    0 references
    64,093.82399999999 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    7 November 2016
    0 references
    30 June 2017
    0 references
    ZAKŁAD PRODUKCYJNO-HANDLOWO-USLUGOWY I GASTRONOMIA - BOGDAN KOŁPAK
    0 references

    53°44'57.1"N, 21°20'28.3"E
    0 references
    Inwestycja polega na zakupie i montażu elektrowni fotowoltaicznej o łącznej mocy 36,14 kW w 2 lokalizacjach: Piecki ul. Zwycięstwa 36H na działce nr 1120 oraz przy ul. Zwycięstwa 36K na działce nr 1123 . Projekt wpisuje się w typ projektu wymieniony w SzOOP RPO WiM 2014-2020 dla działania 4.1- instalacji wykorzystujących energię słońca - do 2 MWe/MWth. Instalacja zgodnie z możliwością opisaną w SzOOP będzie służyła potrzebom własnym przedsiębiorstwa i będzie podłączona do sieci, jednakże ze względu na moc instalacji (do 40 kW) zgodnie z art. 5 ustawy o odnawialnych źródłach energii (Dz.U. 2015 poz. 478) oraz Art. 7 ust. 8d ze znaczkiem 4-9 ustawy – Prawo energetyczne (Dz.U. Dz.U. 1997 nr 54 poz. 348) będzie ona dokonywana na podstawie zgłoszenia bez konieczności posiadania przez beneficjenta ważnych technicznych warunków przyłączenia wszystkich ujętych w projekcie źródeł wytwarzania energii do sieci elektroenergetycznej. Projekt spełnia wszystkie warunki brzegowe określone w SzOOP RPO WiM 2014-2020. Niniejszy projekt zakłada dostawę i montaż dachowych instalacji fotowoltaicznych z wykorzystaniem technologii polikrystalicznej do produkcji energii elektrycznej. Inwestycja polega na montażu łącznie 139 szt. paneli fotowoltaicznych o łącznej mocy 36,14 kW połączonych w samodzielne układy wraz z falownikami, z niezbędnym okablowaniem i osprzętem. Panele fotowoltaiczne wykorzystują zjawisko fotowoltaiczne do przetwarzania promieniowania słonecznego na energię elektryczną. Za pomocą połączeń kablowych przekazują one energię do falowników, gdzie następuje zmiana prądu stałego w prąd zmienny. Elektrownia będzie podłączona do sieci, natomiast nie będzie potrzeby instalowania akumulatorów oraz regulatorów ładowania, ponieważ sieć jest w stanie przyjąć całą energię wyprodukowaną przez system fotowoltaiczny. Wyprodukowana energia elektryczna będzie wykorzystywana bezpośrednio na potrzeby własne a ewentualna nadwyżka będzie wprowadzona do sieci. (Polish)
    0 references
    The investment consists of the purchase and installation of a photovoltaic power plant with a total power output of 36.14 kW at 2 locations: Piecki ul. 36H victory on plot No 1120 and at ul. Victory for 36K on plot No 1123. The project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid, but due to the power of the installation (up to 40 kW) in accordance with Article 5 of the Renewable Energy Act (Journal of Laws 2015, item (478) and Article 7 (1) 8d with 4-9 Act — Energy Law (Journal of Laws 1997/54, item) (348) it will be made on the basis of the notification without the beneficiary having to have a valid technical connection for all the energy sources included in the project for electricity generation. The project fulfils all the conditions laid down in the SzocOP ROP WiM 2014-2020. This project involves the supply and installation of solar photovoltaic installations using polycrystalline technology for the production of electricity. The investment consists of the installation of a total of 139 photovoltaic panels with a combined output of 36.14 kW in separate systems with inverters and the necessary cabling and fittings. Solar panels are using solar radiation to convert solar radiation into electricity. By cable, they transmit energy to inverters where there is a change in direct current into alternating current. The plant will be connected to the grid and there will be no need to install batteries and recharging regulators as the network is capable of absorbing all the energy produced by the photovoltaic system. The electricity produced will be used directly for own account and any surplus will be entered into the grid. (English)
    0 references

    Identifiers

    RPWM.04.01.00-28-0168/16
    0 references