Reconstruction of 2 water treatment stations in Stepnica commune (Q137892): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in 2 languages: Changing unique label-description pair)
(‎Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement)
Property / financed by
 
Property / financed by: Directorate-General for Regional and Urban Policy / rank
Normal rank
 

Revision as of 20:18, 29 October 2020

Project Q137892 in Poland
Language Label Description Also known as
English
Reconstruction of 2 water treatment stations in Stepnica commune
Project Q137892 in Poland

    Statements

    0 references
    2,645,560.7 zloty
    0 references
    634,934.57 Euro
    13 January 2020
    0 references
    3,112,424.37 zloty
    0 references
    746,981.85 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    26 October 2016
    0 references
    30 August 2019
    0 references
    GMINA STEPNICA
    0 references
    Przedmiotem projektu jest przebudowa 2 stacji uzdatniania wody zlokalizowanych na terenie Gminy Stepnica (SUW Miłowo i SUW Łąka). Inwestycja będzie realizowana częściowo w formule „zaprojektuj i wybuduj” (w zakresie remontu i modernizacji instalacji technologicznych uzdatniania wody wraz z przeprowadzeniem prac remontowo-budowlanych obiektów SUW), a jej zakończenie zaplanowano na marzec 2019 r. Zakres projektu związany z posadowieniem zbiorników na wodę pitną będzie realizowany w formule „wybuduj” (gmina posiada pozwolenia na budowę w tym zakresie). W ramach projektu zaplanowano wykonanie 4 zadań: 1. Opracowanie dokumentacji aplikacyjnej dla projektu (Studium Wykonalności oraz wniosek) 2. Przygotowanie projektu budowlanego oraz roboty budowlane obejmujące (zakres jest analogiczny w odniesieniu do obydwu SUW): - opracowanie projektu budowlanego; - remont studni; - instalacje technologiczne; - instalacje sanitarne; - prace budowlane; - prace elektryczne i AKPiA; - posadowienie zbiorników na wodę pitną (dwóch zbiorników cylindrycznych membranowych posadowionych na płycie żelbetowej do magazynowania wody pitnej na terenie SUW – zakres realizowany na podstawie opracowanego już projektu budowlanego i pozwolenia na budowę). 3. Nadzór inwestorski 4. Promocję projektu Celem głównym projektu jest stanu poprawa jakości wody dostarczanej mieszkańcom Gminy Stepnica poprzez przebudowę dwóch stacji uzdatniania wody. Celami szczegółowymi są: - poprawa stanu zdrowia 4535 mieszkańców Gminy Stepnica; -zwiększenie poziomu zadowolenia turystów odwiedzających gminę. Projekt przyczyni się do realizacji następujących wskaźników: 1. produktu: - liczba wspartych stacji uzdatniania wody–2 szt.; - liczba dodatkowych osób korzystających z ulepszonego zaopatrzenia w wodę–4535 osób; 2. rezultatu: - przewidywana liczba osób korzystających z ulepszonego zaopatrzenia w wodę–4535 osób. Inwestycja będzie realizowana na terenie aglomeracji Stepnica o wielkości 6000 RLM. (Polish)
    0 references
    The subject of the project is the reconstruction of 2 water treatment stations located in the municipality of Stepnica (SUW Miłowo and SUW Łąka). The investment will be implemented in part in the formula “design and build” (within the scope of renovation and modernisation of water treatment installations with the completion of repair and construction works of SUW facilities) and its completion is scheduled for March 2019. The scope of the project related to the planting of drinking water tanks will be implemented in the “build” formula (the commune has construction permits in this regard). As part of the project, 4 tasks are planned: 1. Development of application documentation for the project (feasibility study and application) 2. Preparation of a construction project and works covering (the scope is analogous to both SUWs): — development of a construction project; — well repair; — technological installations; — sanitary installations; — construction work; — electrical and ACP work; — planting of drinking water tanks (two cylindrical membrane tanks placed on reinforced concrete plate for storage of drinking water in the SUW area – scope implemented on the basis of the already developed construction project and construction permit). 3. Investor Supervision 4. Project promotion The main objective of the project is to improve the quality of water supplied to residents of Stepnica commune by rebuilding two water treatment stations. The specific objectives shall be: — improvement of the health status of 4535 inhabitants of Stepnica commune; —increase the level of satisfaction of tourists visiting the commune. The project will contribute to the implementation of the following indicators: 1. of product: — number of water treatment stations supported by 2 pcs; — the number of additional persons benefiting from improved water supply-4535 persons; 2. result: — the expected number of people benefiting from improved water supply-4535 people. The investment will be carried out in the area of the Stepnica agglomeration of 6000 RLM. (English)
    21 October 2020
    0 references

    Identifiers

    RPZP.03.05.00-32-C005/18
    0 references