Photovoltaic farm mites (Q137729): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed label, description and/or aliases in 2 languages: Changing unique label-description pair)
(‎Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement)
Property / financed by
 
Property / financed by: Directorate-General for Regional and Urban Policy / rank
Normal rank
 

Revision as of 20:07, 29 October 2020

Project Q137729 in Poland
Language Label Description Also known as
English
Photovoltaic farm mites
Project Q137729 in Poland

    Statements

    0 references
    1,554,005.88 zloty
    0 references
    372,961.41 Euro
    13 January 2020
    0 references
    2,009,133.12 zloty
    0 references
    482,191.95 Euro
    13 January 2020
    0 references
    77.35 percent
    0 references
    4 January 2016
    0 references
    25 June 2019
    0 references
    ROZTOCZE ENERGIA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references
    Przedmiotem planowej inwestycji jest budowa nowej farmy słonecznej (elektrowni fotowoltaicznej) o mocy do 1 MW ( 0,883 MWp) na terenie województwa zachodniopomorskiego w Gminie Choszczno. Na obszarze farmy planowane jest usytuowanie 3.300 sztuk paneli o mocy 295 Wp każdy. Panele zostaną zamontowane na konstrukcji wsporczej w zestawach połączonych przewodami i kablami w blok o mocy ok. 1 MWp. Zastosowane panele będą współpracowały z 30 inwerterami, które będą połączone złączami kablowymi z kontenerową stacją transformatorową, podłączoną bezpośrednio do sieci przesyłowej Krajowego Systemu Energetycznego. Projekt ma charakter stacjonarny i będzie realizowany w 2 etapach: 1) prace przygotowawcze; 2) Budowa farmy fotowoltaicznej. (Polish)
    0 references
    The object of the planned investment is the construction of a new solar farm (photovoltaic power plant) with a capacity of up to 1 MW (0.883 MWp) in the Zachodniopomorskie voivodship in the Choszczno commune. In the area of the farm, 3,300 units of panels with a capacity of 295 Wp are planned. The panels will be mounted on the support structure in sets connected by wires and cables into a block of approx. 1 MWp. The panels used will cooperate with 30 inverters, which will be connected to cable connectors with a container transformer station, connected directly to the transmission network of the National Energy System. The project is stationary and will be implemented in 2 stages: 1. preparatory work; 2) Construction of a photovoltaic farm. (English)
    21 October 2020
    0 references

    Identifiers

    RPZP.02.10.00-32-B015/17
    0 references