Improving the energy efficiency of the buildings of the Criminal Facility in Krzywaniec (Q84562): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in 2 languages: Changing unique label-description pair) |
(Removed claim: financed by (P890): Directorate-General for Regional and Urban Policy (Q8361), Removing unnecessary financed by statement) |
||
Property / financed by | |||
Property / financed by: Directorate-General for Regional and Urban Policy / rank | |||
Revision as of 05:53, 29 October 2020
Project Q84562 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Improving the energy efficiency of the buildings of the Criminal Facility in Krzywaniec |
Project Q84562 in Poland |
Statements
7,976,545.91 zloty
0 references
9,384,171.67 zloty
0 references
85.0 percent
0 references
1 January 2018
0 references
30 September 2022
0 references
ZAKŁAD KARNY W KRZYWAŃCU
0 references
Projekt będzie polegał na termomodernizacji 15 budynków Zakładu Karnego w Krzywańcu wraz z wykorzystaniem OZE, co doprowadzi do redukcji energii końcowej o co najmniej 25%. Prace termomodernizacyjne polegać będą na wymianie dwóch kotłów gazowo-olejowych, które wymagają wymiany ze względu na stopień eksploatacji i niekorzystne parametry, na dwa kotły kondensacyjne, pracujące w kaskadzie, o mocy 500 kW każdy i dwie pompy ciepła powietrze/woda o mocy 18 kW każda. Modernizacji zostanie poddana także sieć ciepłownicza (istniejące rurociągi zostały zainstalowane w 2006 r.), a wraz z nią system ciepłej wody użytkowej. Zainstalowane zostaną panele fotowoltaiczne, pozwalające na redukcję emisji szkodliwych substancji do atmosfery. W budynkach zainstalowane są liczniki niezbędne do prawidłowego prezentowania danych o zużyciu oraz produkcji ciepła i energii elektrycznej. W ramach projektu zostaną zainstalowane termostaty i zawory podpionowe. Wnioskodawca zamierza przeprowadzić modernizację oświetlenia, a w jej ramach wymianę tradycyjnych świetlówek na lampy LED. W większości budynków należy także przeprowadzić termomodernizację dachów. W budynku 27 modernizacji wymaga dach skośny. Konieczna jest również modernizacja ścian zewnętrznych budynków. Konieczne jest wykonanie odpowiednio zaprojektowanych podłóg na gruncie. W budynku dla sali gimnastycznej (27) przewiduje się zainstalowanie wentylacji mechanicznej z odzyskiem ciepła. W skład kosztów kwalifikowalnych projektu wchodzą także działania informacyjno-promocyjne i prace przygotowawcze (przygotowanie niezbędnej dokumentacji) oraz nadzór budowlany. (Polish)
0 references
The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each and two air/water heat pumps with a capacity of 18 kW each. The heating network will also be upgraded (existing pipelines were installed in 2006) and with it a hot water system. Photovoltaic panels will be installed to reduce emissions of harmful substances into the atmosphere. The buildings are equipped with counters necessary for the proper presentation of data on consumption and production of heat and electricity. As part of the project, thermostats and upholstery valves will be installed. The applicant intends to modernise the lighting and replace traditional fluorescent lamps with LED lamps. Most of the buildings also need to be thermally modernised. In building 27, the renovation requires an oblique roof. It is also necessary to modernise the exterior walls of the buildings. It is necessary to make appropriately designed floors on the ground. The building for the gym (27) provides for the installation of mechanical ventilation with heat recovery. The eligible costs of the project also include information and promotion activities and preparatory work (preparation of necessary documentation) and construction supervision. (English)
14 October 2020
0 references
Identifiers
POIS.01.03.01-00-0072/17
0 references