(‎Removed claim: summary (P836): The project is a continuation of the investment project for the construction of community centres. The present project therefore aims at implementing the activities of direct community social work with CS, where the premises of the new KC will be used. The key activities are based on CS needs, which were identified in the preparation phase of the project. These are: (1) Implementation of programmes in the so-called community wave 2) Implement...)
(‎Created claim: summary (P836): The project builds on an investment project to build community centres. The submitted project is therefore focused on the implementation of activities of direct community social work with CS, where the premises of the new KC will be used. Key activities are based on CS needs, which were identified in the preparatory phase of the project. These are:1) Implementation of programmes in the so-called Community Club 2) Implementation of programmes ai...)
Property / summary
 
The project builds on an investment project to build community centres. The submitted project is therefore focused on the implementation of activities of direct community social work with CS, where the premises of the new KC will be used. Key activities are based on CS needs, which were identified in the preparatory phase of the project. These are:1) Implementation of programmes in the so-called Community Club 2) Implementation of programmes aimed at acquiring and training new skills 3) Implementation of programmes focused on community cultural activities (English)
Property / summary: The project builds on an investment project to build community centres. The submitted project is therefore focused on the implementation of activities of direct community social work with CS, where the premises of the new KC will be used. Key activities are based on CS needs, which were identified in the preparatory phase of the project. These are:1) Implementation of programmes in the so-called Community Club 2) Implementation of programmes aimed at acquiring and training new skills 3) Implementation of programmes focused on community cultural activities (English) / rank
 
Normal rank
Property / summary: The project builds on an investment project to build community centres. The submitted project is therefore focused on the implementation of activities of direct community social work with CS, where the premises of the new KC will be used. Key activities are based on CS needs, which were identified in the preparatory phase of the project. These are:1) Implementation of programmes in the so-called Community Club 2) Implementation of programmes aimed at acquiring and training new skills 3) Implementation of programmes focused on community cultural activities (English) / qualifier
 
point in time: 23 October 2020
Timestamp+2020-10-23T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 19:03, 23 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Community Centre of New Hrady
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    900,017.18 Czech koruna
    0 references
    36,000.69 Euro
    10 January 2020
    0 references
    1,058,843.75 Czech koruna
    0 references
    42,353.75 Euro
    10 January 2020
    0 references
    85.0 percent
    0 references
    1 August 2018
    0 references
    31 January 2020
    0 references
    Město Nové Hrady
    0 references
    0 references
    0 references

    48°47'20.94"N, 14°47'4.78"E
    0 references
    37333
    0 references
    Projekt navazuje na investiční projekt vybudování komunitních centra. Předkládaný projekt je proto zaměřen na realizaci aktivit přímé komunitní sociální práce s CS, při kterých budou využity prostory nového KC. Klíčové aktivity vychází z potřeb CS, které byly zjišťovány v přípravné fázi projektu. Jde o tyto:1) Realizace programů v tzv. Komunitním klubíku 2) Realizace programů zaměřených na získávání a nácvik nových dovedností 3) Realizace programů zaměřených na komunitní kulturní aktivity (Czech)
    0 references
    The project builds on an investment project to build community centres. The submitted project is therefore focused on the implementation of activities of direct community social work with CS, where the premises of the new KC will be used. Key activities are based on CS needs, which were identified in the preparatory phase of the project. These are:1) Implementation of programmes in the so-called Community Club 2) Implementation of programmes aimed at acquiring and training new skills 3) Implementation of programmes focused on community cultural activities (English)
    23 October 2020
    0 references

    Identifiers

    CZ.03.2.65/0.0/0.0/16_047/0008136
    0 references