(‎Removed claim: summary (P836): The project is a set of activities leading to the introduction of arrangements for the management of the group of industrial enterprises CZECHHOHOHOAK GROUP a.s. (CSG). All the implemented measures came from the converted audit management, which was the main basis for the processing of the application. The recommended measures will increase the working capacity of the staff of the different companies in the CSG, currently almost 7 000., remove...)
(‎Created claim: summary (P836): The project is a set of activities that will lead to the introduction of age management measures in the group of industrial enterprises CZECHOSLOVAK GROUP a.s. (hereinafter referred to as CSG). All the measures introduced came from the prepared agenda management audit, which was the main basis for processing the application. The implementation of the recommended measures will increase the work capacity of individual CSG companies, which are curr...)
Property / summary
 
The project is a set of activities that will lead to the introduction of age management measures in the group of industrial enterprises CZECHOSLOVAK GROUP a.s. (hereinafter referred to as CSG). All the measures introduced came from the prepared agenda management audit, which was the main basis for processing the application. The implementation of the recommended measures will increase the work capacity of individual CSG companies, which are currently almost 7 thousand. (English)
Property / summary: The project is a set of activities that will lead to the introduction of age management measures in the group of industrial enterprises CZECHOSLOVAK GROUP a.s. (hereinafter referred to as CSG). All the measures introduced came from the prepared agenda management audit, which was the main basis for processing the application. The implementation of the recommended measures will increase the work capacity of individual CSG companies, which are currently almost 7 thousand. (English) / rank
 
Normal rank
Property / summary: The project is a set of activities that will lead to the introduction of age management measures in the group of industrial enterprises CZECHOSLOVAK GROUP a.s. (hereinafter referred to as CSG). All the measures introduced came from the prepared agenda management audit, which was the main basis for processing the application. The implementation of the recommended measures will increase the work capacity of individual CSG companies, which are currently almost 7 thousand. (English) / qualifier
 
point in time: 23 October 2020
Timestamp+2020-10-23T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 11:22, 23 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Implementation of management measures in the CSG of the CSG
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    0 references
    1,869,525.0 Czech koruna
    0 references
    74,781.0 Euro
    10 January 2020
    0 references
    3,739,050.0 Czech koruna
    0 references
    149,562.0 Euro
    10 January 2020
    0 references
    50 percent
    0 references
    1 January 2019
    0 references
    30 June 2020
    0 references
    CSGM a.s.
    0 references
    0 references
    0 references
    0 references

    50°5'34.73"N, 14°27'5.98"E
    0 references
    18600
    0 references
    Projekt je souborem aktivit, které povedou k zavedení opatření age managementu ve skupině průmyslových podniků CZECHOSLOVAK GROUP a.s. (dále jen CSG). Všechna zaváděná opatření vzešla ze zpracovaného age management auditu, který byl hlavním podkladem pro zpracování žádosti. Díky zavedení doporučených opatření dojde ke zvýšení pracovních schopností zaměstnanců jednotlivých podniků skupiny CSG, kterých je v současnosti téměř 7 tis. (Czech)
    0 references
    The project is a set of activities that will lead to the introduction of age management measures in the group of industrial enterprises CZECHOSLOVAK GROUP a.s. (hereinafter referred to as CSG). All the measures introduced came from the prepared agenda management audit, which was the main basis for processing the application. The implementation of the recommended measures will increase the work capacity of individual CSG companies, which are currently almost 7 thousand. (English)
    23 October 2020
    0 references

    Identifiers

    CZ.03.1.52/0.0/0.0/17_079/0009581
    0 references