(Removed claim: summary (P836): The project involves the creation of a handling and storage site for the renovation of the existing brownfield site and owned by VÚB a.s. and the construction of new production, assembly and administrative (factory production control, construction) building in the light of existing plant and assembly hall. a., remove_old_english_translation) |
(Created claim: summary (P836): The object of the project is to create a handling and storage space for reconstruction of the existing unusable building (brownfield) in the premises and owned by VÚB a.s. and the construction of new production, assembly and administrative (production control, construction) space in connection with the existing production and assembly hall of the engineering division. a., translated_summary) |
||||||||||||||
Property / summary | |||||||||||||||
The object of the project is to create a handling and storage space for reconstruction of the existing unusable building (brownfield) in the premises and owned by VÚB a.s. and the construction of new production, assembly and administrative (production control, construction) space in connection with the existing production and assembly hall of the engineering division. a. (English) | |||||||||||||||
Property / summary: The object of the project is to create a handling and storage space for reconstruction of the existing unusable building (brownfield) in the premises and owned by VÚB a.s. and the construction of new production, assembly and administrative (production control, construction) space in connection with the existing production and assembly hall of the engineering division. a. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The object of the project is to create a handling and storage space for reconstruction of the existing unusable building (brownfield) in the premises and owned by VÚB a.s. and the construction of new production, assembly and administrative (production control, construction) space in connection with the existing production and assembly hall of the engineering division. a. (English) / qualifier | |||||||||||||||
point in time: 22 October 2020
|
Revision as of 16:04, 22 October 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of brownfield of VÚB a.s. |
Project in Czech Republic financed by DG Regio |
Statements
19,755,629.47 Czech koruna
0 references
56,444,655.63 Czech koruna
0 references
35.0 percent
0 references
31 December 2022
0 references
VÚB a.s.
0 references
56201
0 references
Předmětem projektu je vytvoření manipulačních a skladovacích prostor rekonstrukcí stávajícího nevyužitelného objektu (brownfield) v areálu a ve vlastnictví VÚB a.s. a vybudování nových výrobních, montážních a administrativních (řízení výroby, konstrukce) prostor v návaznosti na stávající výrobní a montážní halu strojírenské divize. a. (Czech)
0 references
The object of the project is to create a handling and storage space for reconstruction of the existing unusable building (brownfield) in the premises and owned by VÚB a.s. and the construction of new production, assembly and administrative (production control, construction) space in connection with the existing production and assembly hall of the engineering division. a. (English)
22 October 2020
0 references
Identifiers
CZ.01.2.07/0.0/0.0/18_238/0016075
0 references