Design of an energy system to streamline the wood drying process by reconstructing the energy source with the possibility of cogeneration of electricity and heat (Q10626): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project is aimed at streamlining the wood drying process at the mill for wood treatment. In the current state, the wood dryers and the heat source for their supply are operated manually, a measurement system is not available. It is likely that dryers will consume significantly more energy than would have to be done. After the analysis, new sources of energy for biomass, including cogeneration in small scale biomass electricity production,...)
(‎Created claim: summary (P836): The project is aimed at streamlining the process of drying wood in a wood processing plant. In the current state, wood dryers and heat source are operated manually for their supply, no measuring system is available. It is likely that drying plants consume significantly more energy than would be necessary. After the analysis, it will be possible to properly dimension new energy sources to biomass, including the cogeneration production of electric...)
Property / summary
 
The project is aimed at streamlining the process of drying wood in a wood processing plant. In the current state, wood dryers and heat source are operated manually for their supply, no measuring system is available. It is likely that drying plants consume significantly more energy than would be necessary. After the analysis, it will be possible to properly dimension new energy sources to biomass, including the cogeneration production of electricity from biomass on a small scale. a. (English)
Property / summary: The project is aimed at streamlining the process of drying wood in a wood processing plant. In the current state, wood dryers and heat source are operated manually for their supply, no measuring system is available. It is likely that drying plants consume significantly more energy than would be necessary. After the analysis, it will be possible to properly dimension new energy sources to biomass, including the cogeneration production of electricity from biomass on a small scale. a. (English) / rank
 
Normal rank
Property / summary: The project is aimed at streamlining the process of drying wood in a wood processing plant. In the current state, wood dryers and heat source are operated manually for their supply, no measuring system is available. It is likely that drying plants consume significantly more energy than would be necessary. After the analysis, it will be possible to properly dimension new energy sources to biomass, including the cogeneration production of electricity from biomass on a small scale. a. (English) / qualifier
 
point in time: 22 October 2020
Timestamp+2020-10-22T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:18, 22 October 2020

Project in Czech Republic financed by DG Regio
Language Label Description Also known as
English
Design of an energy system to streamline the wood drying process by reconstructing the energy source with the possibility of cogeneration of electricity and heat
Project in Czech Republic financed by DG Regio

    Statements

    0 references
    245,512.5 Czech koruna
    0 references
    9,820.5 Euro
    10 January 2020
    0 references
    327,350.0 Czech koruna
    0 references
    13,094.0 Euro
    10 January 2020
    0 references
    75 percent
    0 references
    16 February 2017
    0 references
    27 March 2017
    0 references
    31 March 2017
    0 references
    KAISER s.r.o.
    0 references

    49°35'57.70"N, 13°51'54.68"E
    0 references
    26242
    0 references
    Projekt je cílen na zefektivnění procesu sušení dřeva v závodu na zpracování dřeva. Ve stávajícím stavu jsou sušárny dřeva a zdroj tepla pro jejich zásobování provozovány manuálně, není dostupný systém měření. Je pravděpodobné, že sušárny spotřebují výrazně více energie, než by bylo nutné. Po provedení analýzy bude možné správně dimenzovat nové zdroje energie na biomasu včetně kogenerační výroby elektřiny z biomasy v malém měřítku. a. (Czech)
    0 references
    The project is aimed at streamlining the process of drying wood in a wood processing plant. In the current state, wood dryers and heat source are operated manually for their supply, no measuring system is available. It is likely that drying plants consume significantly more energy than would be necessary. After the analysis, it will be possible to properly dimension new energy sources to biomass, including the cogeneration production of electricity from biomass on a small scale. a. (English)
    22 October 2020
    0 references

    Identifiers

    CZ.01.1.02/0.0/0.0/16_045/0008707
    0 references