Reconstruction of the rainwater drainage network ul. 3 – go Marca and St. Kosciuszko in Świdwin (Q137845): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in 1 language: remove_english_label) |
(Changed label, description and/or aliases in 1 language: translated_label) |
||
label / en | label / en | ||
Reconstruction of the rainwater drainage network ul. 3 – go Marca and St. Kosciuszko in Świdwin |
Revision as of 19:30, 21 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of the rainwater drainage network ul. 3 – go Marca and St. Kosciuszko in Świdwin |
Project in Poland financed by DG Regio |
Statements
1,553,482.2 zloty
0 references
1,827,626.12 zloty
0 references
85.0 percent
0 references
19 January 2016
0 references
30 November 2017
0 references
GMINA MIEJSKA ŚWIDWIN
0 references
Projekt dotyczył będzie przebudowy sieci kanalizacji deszczowej ul. 3 Marca i ul. Kościuszki w Świdwinie, która aktualnie znajdują się w bardzo złym stanie technicznym. Zakres rzeczowy inwestycji obejmuje prace przygotowawcze, w skład których wchodzi sporządzenie dokumentacji technicznych, uzyskanie decyzji o środowiskowych uwarunkowaniach zgody na realizacje inwestycji, uzyskanie pozwoleń na budowę oraz sporządzenie studium wykonalności. Wykonawcy dokumentacji technicznej oraz studium wykonalności wyłonieni zostali w ramach postępowania- zapytań ofertowych. Kolejnym etapem składającym się na zakres rzeczowy inwestycji są prace budowlane oraz procedury przetargowe z nimi związane. Projekt polegał będzie na przebudowie istniejącej sieci kanalizacji deszczowej, dla odwodnienia istniejącej ul. T. Kościuszki i ul. 3 Marca, w układzie grawitacyjnym. Sieć wykonana zostanie z rur PVC litych o klasie wytrzymałości 8kN łączonych na uszczelkę wargową. Przebudowę zaprojektowano po trasie istniejącej przebudowywanej sieci. Dla przebudowy zaprojektowano studnie rewizyjne o średnicach dn=1,2 m i dn=1,0 m, z gotową prefabrykowaną kinetą, przykryte pokrywą betonową oraz zamknięte włazem o klasie nośności 40 t. Studnie PVC dn=425 mm. Zaprojektowano także wpusty uliczne na trzonach betonowych średnicy dn=0,5 m z osadnikiem 0,5 m. Dla zwiększenia retencji kanałowej przewymiarowano, za zgodą inwestora, średnicę kolektora głównego. Długość projektowanej sieci w ul. T. Kościuszki z podziałem na średnice: - PVC O 630 – 519 m; - PVC O 315 – 4 m, - PVC O 200 – 210 m; Długość projektowanej sieci w ul. 3 Marca z podziałem na średnice: - PVC O 630 – 507 m; - PVC O 315 – 18 m; - PVC O 200 – 228 m. W zakres rzeczowy realizacji projektu wchodzić będzie również nadzór inwestorski. W celu wyboru osoby pełniącej funkcję inspektora nadzoru przeprowadzone zostanie wyłaniające wykonawcę. W ramach realizacji projektu przewidziano także działania informacyjno-promocyjne. (Polish)
0 references
The project will concern the reconstruction of the rainwater drainage network ul. 3 March and St. Kosciuszko in Świdwin, which is currently in a very poor technical condition. The material scope of the investment includes preparatory work, which consists of drawing up technical documentation, obtaining decisions on the environmental conditions of consent to the implementation of the investment, obtaining construction permits and drawing up a feasibility study. The contractors of the technical documentation and the feasibility study were selected as part of the tender procedure. The next stage of the investment’s material scope is the construction work and the tendering procedures. The project will consist of rebuilding the existing rainwater drainage network, to drain the existing street. T. Kosciuszko and St. March 3rd, in the gravitational system. The network will be made of PVC solid tubes with a strength class of 8kN connected to a lip seal. The reconstruction was designed on the route of the existing reconstructed network. For the reconstruction, revision wells with dn=1.2 m and dn=1.0 m diameters were designed, with prefabricated cinema, covered with concrete cover and closed with manhole with load class of 40 t. PVC wells dn=425 mm. Street drains were also designed on concrete shafts dn=0.5 m with a settler of 0.5 m. To increase the canal retention the diameter of the main manifold was oversized, with the investor’s agreement. Length of the design network in ul. T. Kościuszko with diameters: — PVC O 630-519 m; — PVC About 315-4 m, – PVC O 200-210 m; Length of the design network in ul. March 3, broken down by diameter: — PVC O 630-507 m; — PVC O 315-18 m; — PVC About 200-228 m. The real scope of the project will include investor supervision. In order to select the person acting as supervisory inspector, the selection of the contractor shall be carried out. Information and promotion activities are also foreseen as part of the project. (English)
21 October 2020
0 references
Identifiers
RPZP.03.03.00-32-A012/16
0 references