The use of renewable energy sources by the installation of solar panels and heat pump cascades by Dariusz Baginski. (Q131767): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Removed claim: summary (P836): This project consists of the purchase and installation of a roof photovoltaic power plant of 0.04992 MW and 2- air-to-water heat pumps with a total capacity of 0.136 MW in Oleko at ul. Gołdapska 12 in j.48 and 2.This project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid,...)
Property / summary
This project consists of the purchase and installation of a roof photovoltaic power plant of 0.04992 MW and 2- air-to-water heat pumps with a total capacity of 0.136 MW in Oleko at ul. Gołdapska 12 in j.48 and 2.This project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid, but due to the power of the installation (up to 50 kW) by the Renewable Energy Act of 20 February 2015 (Journal Journal of Laws 2015, item 478) and Article 2 (2) of the Act of 7 June 2018 amending the Renewable Energy Act and certain other acts (Journal of Laws 2018, item 1276.) it will be made on the basis of a notification without the beneficiary having to have a valid technical connection for all the energy sources included in the project for electricity generation. The applicant shall have a power connection at the end of 50 kW. The project meets all boundary conditions laid down in the SzOOP. The investment consists of the installation of 156 ‘mono-crystalline’ solar panels (mono-crystalline), which together with inverters, with the necessary wiring and fittings, are used to treat solar radiation for electrification. the solar photovoltaic is used to convert solar radiation into electricity. electricity connections provide energy to inverters, where power generation is changed into a variable current. power station will be connected to the grid, and there will be no need to install batteries and recharging regulators as the network is capable of absorbing all the energy produced by the photovoltaic system. The electricity produced will be used for its own purposes, including the supply of heat pumps and any surplus will be delivered to the network. the project also includes the installation of heat pumps with a heating capacity of 0.136 MW. (English)
 
Property / summary: This project consists of the purchase and installation of a roof photovoltaic power plant of 0.04992 MW and 2- air-to-water heat pumps with a total capacity of 0.136 MW in Oleko at ul. Gołdapska 12 in j.48 and 2.This project is part of the project type referred to in SzOOP ROP WiM 2014-2020 for 4.1-2 MWe of the solar installations. The installation as described in the SzooP will serve the needs of its own business and be connected to the grid, but due to the power of the installation (up to 50 kW) by the Renewable Energy Act of 20 February 2015 (Journal Journal of Laws 2015, item 478) and Article 2 (2) of the Act of 7 June 2018 amending the Renewable Energy Act and certain other acts (Journal of Laws 2018, item 1276.) it will be made on the basis of a notification without the beneficiary having to have a valid technical connection for all the energy sources included in the project for electricity generation. The applicant shall have a power connection at the end of 50 kW. The project meets all boundary conditions laid down in the SzOOP. The investment consists of the installation of 156 ‘mono-crystalline’ solar panels (mono-crystalline), which together with inverters, with the necessary wiring and fittings, are used to treat solar radiation for electrification. the solar photovoltaic is used to convert solar radiation into electricity. electricity connections provide energy to inverters, where power generation is changed into a variable current. power station will be connected to the grid, and there will be no need to install batteries and recharging regulators as the network is capable of absorbing all the energy produced by the photovoltaic system. The electricity produced will be used for its own purposes, including the supply of heat pumps and any surplus will be delivered to the network. the project also includes the installation of heat pumps with a heating capacity of 0.136 MW. (English) / rank
Normal rank
 

Revision as of 15:59, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
The use of renewable energy sources by the installation of solar panels and heat pump cascades by Dariusz Baginski.
Project in Poland financed by DG Regio

    Statements

    0 references
    0 references
    661,300.0 zloty
    0 references
    158,712.0 Euro
    13 January 2020
    0 references
    778,000.0 zloty
    0 references
    186,720.0 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    6 April 2020
    0 references
    31 December 2020
    0 references
    DARIUSZ BAGIŃSKI
    0 references
    0 references

    54°2'20.8"N, 22°29'37.7"E
    0 references
    Niniejszy projekt polega na zakupie i montażu dachowej elektrowni fotowoltaicznej o mocy 0,04992 MW oraz 2pomp ciepła powietrze-woda o łącznej mocy 0,136 MW w miejscowości Olecko przy ul. Gołdapskiej 12 na dz.48 obręb 2.Projekt wpisuje się w typ projektu wymieniony w SzOOP RPO WiM 2014-2020 dla działania 4.1-instalacji wykorzystujących energię słońca - do 2 MWe/MWth. Instalacja zgodnie z możliwością opisaną w SzOOP będzie służyła potrzebom własnym przedsiębiorstwa i będzie podłączona do sieci, jednakże ze względu na moc instalacji(do 50 kW)zgodnie ustawą z dnia 20 lutego 2015r. o odnawialnych źródłach energii(Dz. U. 2015 poz. 478)oraz z art. 2 pkt 2 ustawy z dnia 7 czerwca 2018r. o zmianie ustawy o odnawialnych źródłach energii oraz niektórych innych ustaw(Dz.U. 2018 poz. 1276.)będzie ona dokonywana na podstawie zgłoszenia bez konieczności posiadania przez beneficjenta ważnych technicznych warunków przyłączenia wszystkich ujętych w projekcie źródeł wytwarzania energii do sieci elektroenergetycznej. Wnioskodawca posiada przyłącze o mocy 50kW. Projekt spełnia wszystkie warunki brzegowe określone w SzOOP. Inwestycja polega na montażu 156szt.paneli fotowoltaicznych(monokrystalicznych)o mocy 320W. połączonych w samodzielne układy wraz z falownikami, z niezbędnym okablowaniem i osprzętem.Panele fotowoltaiczne wykorzystują zjawisko fotowoltaiczne do przetwarzania promieniowania słonecznego na energię elektryczną.Za pomocą połączeń kablowych przekazują one energię do falowników,gdzie następuje zmiana prądu stałego w prąd zmienny.Elektrownia będzie podłączona do sieci, natomiast nie będzie potrzeby instalowania akumulatorów oraz regulatorów ładowania, ponieważ sieć jest w stanie przyjąć całą energię wyprodukowaną przez system fotowoltaiczny. Wyprodukowana energia elektryczna będzie przeznaczona na potrzeby własne, w tym na zasilanie pomp ciepła, a ewentualna nadwyżka będzie oddawana do sieci.Projekt zakłada również montaż pomp ciepła o mocy grzewczej 0,136 MW. (Polish)
    0 references

    Identifiers

    RPWM.04.01.00-28-0104/18
    0 references