(‎Removed claim: summary (P836): The project consists of the construction of a sewage system, a press sewer, the construction of one new sewage pumping station and the reconstruction of the two existing sewage pumping stations. As a result of the implementation of the sanitary sewerage network, households will be connected as well as public buildings, i.e. offices, schools, health services and commercial premises. The aim of the project is to increase the percentage of the po...)
(‎Created claim: summary (P836): The project consists of the construction of sanitary sewerage, the construction of one new sanitary drainage pumping plant and the reconstruction of two existing sewage pumping plants. As a result of the implementation of the sanitary sewage system, households as well as public buildings, i.e. offices, schools, health care institutions and commercial and service facilities will be connected. The aim of the project is to increase the proportion o...)
Property / summary
 
The project consists of the construction of sanitary sewerage, the construction of one new sanitary drainage pumping plant and the reconstruction of two existing sewage pumping plants. As a result of the implementation of the sanitary sewage system, households as well as public buildings, i.e. offices, schools, health care institutions and commercial and service facilities will be connected. The aim of the project is to increase the proportion of the population of Koniecpol commune using a sewage treatment system in accordance with the municipal waste water directive by developing a sanitary sewer system in Koniecpol municipality. As a result of the project, the number of people using the sewage system will increase. Ultimately, pressure on the environment will be reduced by reducing the number of wastes introduced into the environment, as well as increasing the percentage of purified municipal wastes. (English)
Property / summary: The project consists of the construction of sanitary sewerage, the construction of one new sanitary drainage pumping plant and the reconstruction of two existing sewage pumping plants. As a result of the implementation of the sanitary sewage system, households as well as public buildings, i.e. offices, schools, health care institutions and commercial and service facilities will be connected. The aim of the project is to increase the proportion of the population of Koniecpol commune using a sewage treatment system in accordance with the municipal waste water directive by developing a sanitary sewer system in Koniecpol municipality. As a result of the project, the number of people using the sewage system will increase. Ultimately, pressure on the environment will be reduced by reducing the number of wastes introduced into the environment, as well as increasing the percentage of purified municipal wastes. (English) / rank
 
Normal rank
Property / summary: The project consists of the construction of sanitary sewerage, the construction of one new sanitary drainage pumping plant and the reconstruction of two existing sewage pumping plants. As a result of the implementation of the sanitary sewage system, households as well as public buildings, i.e. offices, schools, health care institutions and commercial and service facilities will be connected. The aim of the project is to increase the proportion of the population of Koniecpol commune using a sewage treatment system in accordance with the municipal waste water directive by developing a sanitary sewer system in Koniecpol municipality. As a result of the project, the number of people using the sewage system will increase. Ultimately, pressure on the environment will be reduced by reducing the number of wastes introduced into the environment, as well as increasing the percentage of purified municipal wastes. (English) / qualifier
 
point in time: 21 October 2020
Timestamp+2020-10-21T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 09:55, 21 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of the sanitary sewerage network in Koniecfield ul. ŻeRoma-Charastowska
Project in Poland financed by DG Regio

    Statements

    0 references
    527,082.23 zloty
    0 references
    126,499.74 Euro
    13 January 2020
    0 references
    794,995.83 zloty
    0 references
    190,799.0 Euro
    13 January 2020
    0 references
    66.3 percent
    0 references
    22 December 2017
    0 references
    30 June 2018
    0 references
    GMINA KONIECPOL
    0 references

    50°46'21.0"N, 19°40'37.2"E
    0 references
    Projekt polega na budowie kanalizacji sanitarnej, kanalizacji tłocznej, budowie jednej nowej przepompowni ścieków sanitarnych oraz przebudowie dwóch istniejących przepompowni ścieków. W wyniku realizacji do sieci kanalizacji sanitarnej będą podłączone gospodarstwa domowe, jak również budynki użyteczności publicznej, tj. urzędy, szkoła, placówki ochrony zdrowia oraz obiekty handlowo-usługowe. Celem projektu jest zwiększony odsetek ludności gminy Koniecpol korzystającej z systemu oczyszczania ścieków zgodnego z dyrektywą dotyczącą ścieków komunalnych poprzez rozwój systemu kanalizacji sanitarnej w gminie Koniecpol. W wyniku realizacji przedsięwzięcia zwiększy się liczba osób korzystających z systemu kanalizacji. Docelowo nasta?pi ograniczenie presji na s´rodowisko naturalne poprzez zmniejszenie ilos´ci s´cieko´w nieoczyszczonych wprowadzanych do środowiska, a takz˙e zwie?kszenie odsetka oczyszczonych s´cieko´w komunalnych. (Polish)
    0 references
    The project consists of the construction of sanitary sewerage, the construction of one new sanitary drainage pumping plant and the reconstruction of two existing sewage pumping plants. As a result of the implementation of the sanitary sewage system, households as well as public buildings, i.e. offices, schools, health care institutions and commercial and service facilities will be connected. The aim of the project is to increase the proportion of the population of Koniecpol commune using a sewage treatment system in accordance with the municipal waste water directive by developing a sanitary sewer system in Koniecpol municipality. As a result of the project, the number of people using the sewage system will increase. Ultimately, pressure on the environment will be reduced by reducing the number of wastes introduced into the environment, as well as increasing the percentage of purified municipal wastes. (English)
    21 October 2020
    0 references

    Identifiers

    RPSL.05.01.02-24-0793/16
    0 references