(Removed claim: summary (P836): The aim of the project is to carry out regeneration, maintenance and construction works to protect the heritage object, increase the use of usable space in the facility, introduce new functions for external customers and allow better use of the institution and the facility and increase the facility’s standard. The architectural, technical and technological solutions used in the design correspond to the best practices in the field of constructi...) |
(Created claim: summary (P836): The aim of the project is to carry out revitalisation, conservation and construction works enabling the preservation of historical material of the facility, increasing the use of usable space in the building, introducing new functions aimed at external recipients and allowing better use of the institution’s resource and facility, as well as raising the standard of the facility. The architectural, technical and technological solutions used in the...) |
||||||||||||||
Property / summary | |||||||||||||||
The aim of the project is to carry out revitalisation, conservation and construction works enabling the preservation of historical material of the facility, increasing the use of usable space in the building, introducing new functions aimed at external recipients and allowing better use of the institution’s resource and facility, as well as raising the standard of the facility. The architectural, technical and technological solutions used in the project correspond to the best practices in the field of construction, taking into account the specific characteristics of the building and its specific characteristics resulting from the historic nature of the building. The project provides solutions and activities that will allow for maximum, with existing conditions, the acquisition of usable space through the application of design solutions related to the adaptation of the attic for use purposes, obtaining additional space in cellars excavating parts of the cellars and optimising the functional layout of the rooms. In the area of construction, there are solutions aimed at stabilising the building, the construction of which is in poor condition and further deteriorated after the renovation of the adjacent building several years ago. In the field of thermomodernisation, ecological solutions are provided, including limiting heat loss in the facility and protecting the building against destruction and moisture, as well as for improving the environmental impact by modernising the gas boiler room and eventually dismantling it after obtaining heat from MPEC. The project shall include the following elements: 1. Preparatory and design work The start of the design work was preceded by examinations of the construction state of the building and testing of the ground on which the object is located. C.3.1 (English) | |||||||||||||||
Property / summary: The aim of the project is to carry out revitalisation, conservation and construction works enabling the preservation of historical material of the facility, increasing the use of usable space in the building, introducing new functions aimed at external recipients and allowing better use of the institution’s resource and facility, as well as raising the standard of the facility. The architectural, technical and technological solutions used in the project correspond to the best practices in the field of construction, taking into account the specific characteristics of the building and its specific characteristics resulting from the historic nature of the building. The project provides solutions and activities that will allow for maximum, with existing conditions, the acquisition of usable space through the application of design solutions related to the adaptation of the attic for use purposes, obtaining additional space in cellars excavating parts of the cellars and optimising the functional layout of the rooms. In the area of construction, there are solutions aimed at stabilising the building, the construction of which is in poor condition and further deteriorated after the renovation of the adjacent building several years ago. In the field of thermomodernisation, ecological solutions are provided, including limiting heat loss in the facility and protecting the building against destruction and moisture, as well as for improving the environmental impact by modernising the gas boiler room and eventually dismantling it after obtaining heat from MPEC. The project shall include the following elements: 1. Preparatory and design work The start of the design work was preceded by examinations of the construction state of the building and testing of the ground on which the object is located. C.3.1 (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The aim of the project is to carry out revitalisation, conservation and construction works enabling the preservation of historical material of the facility, increasing the use of usable space in the building, introducing new functions aimed at external recipients and allowing better use of the institution’s resource and facility, as well as raising the standard of the facility. The architectural, technical and technological solutions used in the project correspond to the best practices in the field of construction, taking into account the specific characteristics of the building and its specific characteristics resulting from the historic nature of the building. The project provides solutions and activities that will allow for maximum, with existing conditions, the acquisition of usable space through the application of design solutions related to the adaptation of the attic for use purposes, obtaining additional space in cellars excavating parts of the cellars and optimising the functional layout of the rooms. In the area of construction, there are solutions aimed at stabilising the building, the construction of which is in poor condition and further deteriorated after the renovation of the adjacent building several years ago. In the field of thermomodernisation, ecological solutions are provided, including limiting heat loss in the facility and protecting the building against destruction and moisture, as well as for improving the environmental impact by modernising the gas boiler room and eventually dismantling it after obtaining heat from MPEC. The project shall include the following elements: 1. Preparatory and design work The start of the design work was preceded by examinations of the construction state of the building and testing of the ground on which the object is located. C.3.1 (English) / qualifier | |||||||||||||||
point in time: 20 October 2020
|
Revision as of 12:42, 20 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | “Modernisation and revitalisation of the buildings of the Opera in Krakow, ul. St. St. Tomasz 37 w Krakowie’ |
Project in Poland financed by DG Regio |
Statements
4,406,218.59 zloty
0 references
6,294,598.0 zloty
0 references
70.0 percent
0 references
20 October 2015
0 references
30 June 2019
0 references
OPERA KRAKOWSKA W KRAKOWIE
0 references
Celem projektu jest przeprowadzenie prac rewitalizacyjnych, konserwatorskich i budowlanych pozwalających na zabezpieczenie zabytkowej materii obiektu, zwiększenie wykorzystania powierzchni użytkowej w obiekcie, wprowadzenie nowych funkcji skierowanych do odbiorców zewnętrznych i pozwalających na lepsze wykorzystanie zasobu instytucji i obiektu, a także podniesienie standardu obiektu. Zastosowane w projekcie rozwiązania architektoniczne, techniczne i technologiczne odpowiadają najlepszym praktykom w dziedzinie budownictwa, uwzględniając specyfikę budynku oraz jego szczególne uwarunkowania wynikające z zabytkowego charakteru obiektu. W projekcie przewidziano rozwiązania i działania, które pozwolą na maksymalne, przy istniejących obecnie uwarunkowaniach, pozyskanie powierzchni użytkowej poprzez zastosowanie rozwiązań projektowych związanych z adaptacją poddasza na cele użytkowe, pozyskaniem dodatkowej powierzchni w piwnicach odkopanie części piwnic oraz optymalizacją układu funkcjonalnego pomieszczeń. W zakresie konstrukcyjnym przewidziano rozwiązania mające na celu stabilizację budynku, którego konstrukcja jest w słabym stanie i dodatkowo uległa pogorszeniu po przeprowadzonym kilkanaście lat temu remoncie sąsiadującego budynku. W zakresie termomodernizacyjnym przewidziano rozwiązania proekologiczne, m.in. ograniczające straty ciepła w obiekcie oraz zabezpieczające budynek przed niszczeniem i zawilgoceniem, a także służące poprawie oddziaływania na środowisko poprzez unowocześnienie kotłowni gazowej i docelowo jej likwidację po uzyskaniu ciepła z MPEC. Projekt obejmuje następujące elementy: 1. Prace przygotowawczo projektowe Rozpoczęcie prac projektowych poprzedzone zostało badaniami stanu konstrukcyjnego budynku oraz badania mi podłoża na jakim posadowiony jest obiekt.Ciąg dlaszy w częśći: C.3.1 (Polish)
0 references
The aim of the project is to carry out revitalisation, conservation and construction works enabling the preservation of historical material of the facility, increasing the use of usable space in the building, introducing new functions aimed at external recipients and allowing better use of the institution’s resource and facility, as well as raising the standard of the facility. The architectural, technical and technological solutions used in the project correspond to the best practices in the field of construction, taking into account the specific characteristics of the building and its specific characteristics resulting from the historic nature of the building. The project provides solutions and activities that will allow for maximum, with existing conditions, the acquisition of usable space through the application of design solutions related to the adaptation of the attic for use purposes, obtaining additional space in cellars excavating parts of the cellars and optimising the functional layout of the rooms. In the area of construction, there are solutions aimed at stabilising the building, the construction of which is in poor condition and further deteriorated after the renovation of the adjacent building several years ago. In the field of thermomodernisation, ecological solutions are provided, including limiting heat loss in the facility and protecting the building against destruction and moisture, as well as for improving the environmental impact by modernising the gas boiler room and eventually dismantling it after obtaining heat from MPEC. The project shall include the following elements: 1. Preparatory and design work The start of the design work was preceded by examinations of the construction state of the building and testing of the ground on which the object is located. C.3.1 (English)
20 October 2020
0 references
Identifiers
RPMP.06.01.01-12-0114/16
0 references