Construction and upgrade of the power grid for SN and NN voltage power grid that allows for the connection of units of electricity generation from RES in the district of cancer and the Tatrzański stage 1 (Q112117): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The project is necessary to ensure the correct operation of the power grid in the district of: cancer and Tatar. In the municipalities where the project is located, there is a significant increase in the number of RES installations producing electricity. the project is made up of 3 projects for the construction of links between lines: activity 1. Construction of overhead 15 kV overhead cable network: station 6733 Forestry 5 pillar C 231 in ord...) |
(Created claim: summary (P836): Implementation of the project is necessary to ensure the proper functioning of the electricity grid in the district of powiats: it’s New and Tatra. In communes where the project is located, a significant increase in the number of RES installations producing electricity is planned.The project consists of 3 tasks of building linear lines:Task 1. Construction of the overhead cable network SN 15 kV of relations: station 6733 Leśnica 5 column C 231 i...) |
||||||||||||||
Property / summary | |||||||||||||||
Implementation of the project is necessary to ensure the proper functioning of the electricity grid in the district of powiats: it’s New and Tatra. In communes where the project is located, a significant increase in the number of RES installations producing electricity is planned.The project consists of 3 tasks of building linear lines:Task 1. Construction of the overhead cable network SN 15 kV of relations: station 6733 Leśnica 5 column C 231 in order to link line lines between GPZ Białka Tatrzańska and GPZ Szaflary and reconstruction of line nN in Groń and Leśnica commune Bukowina Tatrzańska;Task 2. Construction of line SN 15 kV relations: station 5257 Suche Lachy station 5292 Tooth 11 Church to link line lines between GPZ Bukowina p. 27 line Poronin and GPZ Szaflary p. 15 Bańska Line in Ząb and Suche Municipality Poronin;Task 3. Construction of cable line SN 15 kV with fiber optic pipeline at ul. The project will allow linking existing line lines, which will result in the power supply of the two-sided branch of the line, where there are many transformer stations, while at the same time it will allow to book selected relationships. The investment will allow the Applicant to manage more effectively the electricity generated within the RES.Construction of sections of the electricity distribution network SN and nN lines and reconstruction of necessary connections together with elements accompanying switchgears, posts, transformer stations and cable connectors will enable connection of electricity generation units from renewable sources in dispersion. Selected technical and architectural solutions, the construction of cable lines where necessary, are solutions developed in the course of negotiations with landowners. The most cost-effective and at the same time acceptable solutions were chosen by landowners. (English) | |||||||||||||||
Property / summary: Implementation of the project is necessary to ensure the proper functioning of the electricity grid in the district of powiats: it’s New and Tatra. In communes where the project is located, a significant increase in the number of RES installations producing electricity is planned.The project consists of 3 tasks of building linear lines:Task 1. Construction of the overhead cable network SN 15 kV of relations: station 6733 Leśnica 5 column C 231 in order to link line lines between GPZ Białka Tatrzańska and GPZ Szaflary and reconstruction of line nN in Groń and Leśnica commune Bukowina Tatrzańska;Task 2. Construction of line SN 15 kV relations: station 5257 Suche Lachy station 5292 Tooth 11 Church to link line lines between GPZ Bukowina p. 27 line Poronin and GPZ Szaflary p. 15 Bańska Line in Ząb and Suche Municipality Poronin;Task 3. Construction of cable line SN 15 kV with fiber optic pipeline at ul. The project will allow linking existing line lines, which will result in the power supply of the two-sided branch of the line, where there are many transformer stations, while at the same time it will allow to book selected relationships. The investment will allow the Applicant to manage more effectively the electricity generated within the RES.Construction of sections of the electricity distribution network SN and nN lines and reconstruction of necessary connections together with elements accompanying switchgears, posts, transformer stations and cable connectors will enable connection of electricity generation units from renewable sources in dispersion. Selected technical and architectural solutions, the construction of cable lines where necessary, are solutions developed in the course of negotiations with landowners. The most cost-effective and at the same time acceptable solutions were chosen by landowners. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: Implementation of the project is necessary to ensure the proper functioning of the electricity grid in the district of powiats: it’s New and Tatra. In communes where the project is located, a significant increase in the number of RES installations producing electricity is planned.The project consists of 3 tasks of building linear lines:Task 1. Construction of the overhead cable network SN 15 kV of relations: station 6733 Leśnica 5 column C 231 in order to link line lines between GPZ Białka Tatrzańska and GPZ Szaflary and reconstruction of line nN in Groń and Leśnica commune Bukowina Tatrzańska;Task 2. Construction of line SN 15 kV relations: station 5257 Suche Lachy station 5292 Tooth 11 Church to link line lines between GPZ Bukowina p. 27 line Poronin and GPZ Szaflary p. 15 Bańska Line in Ząb and Suche Municipality Poronin;Task 3. Construction of cable line SN 15 kV with fiber optic pipeline at ul. The project will allow linking existing line lines, which will result in the power supply of the two-sided branch of the line, where there are many transformer stations, while at the same time it will allow to book selected relationships. The investment will allow the Applicant to manage more effectively the electricity generated within the RES.Construction of sections of the electricity distribution network SN and nN lines and reconstruction of necessary connections together with elements accompanying switchgears, posts, transformer stations and cable connectors will enable connection of electricity generation units from renewable sources in dispersion. Selected technical and architectural solutions, the construction of cable lines where necessary, are solutions developed in the course of negotiations with landowners. The most cost-effective and at the same time acceptable solutions were chosen by landowners. (English) / qualifier | |||||||||||||||
point in time: 20 October 2020
|
Revision as of 10:55, 20 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction and upgrade of the power grid for SN and NN voltage power grid that allows for the connection of units of electricity generation from RES in the district of cancer and the Tatrzański stage 1 |
Project in Poland financed by DG Regio |
Statements
738,754.77 zloty
0 references
1,667,618.0 zloty
0 references
44.3 percent
0 references
20 May 2018
0 references
30 October 2018
0 references
TAURON DYSTRYBUCJA SPÓŁKA AKCYJNA
0 references
Realizacja projektu jest niezbędna do zapewnienia prawidłowego funkcjonowania sieci elektroenergetycznej w rejonie powiatów: nowotarskiego i tatrzańskiego. W gminach gdzie zlokalizowany jest projektu planowany jest znaczący wzrost ilości instalacji OZE wytwarzających energię elektryczną.Projekt składa się z 3 zadań budowy powiązań ciągów liniowych:Zadanie 1. Budowa napowietrznokablowej sieci SN 15kV relacji: stacja 6733 Leśnica 5 słup C 231 w celu powiązania ciągów liniowych pomiędzy GPZ Białka Tatrzańska i GPZ Szaflary oraz przebudowa linii nN w miejscowości Groń i Leśnica gmina Bukowina Tatrzańska;Zadanie 2. Budowa linii SN 15kV relacji: stacja 5257 Suche Lachy stacja 5292 Ząb 11 Kościół w celu powiązania ciągów liniowych pomiędzy GPZ Bukowina p. 27 linia Poronin i GPZ Szaflary p. 15 Linia Bańska w miejscowości Ząb i Suche gmina Poronin;Zadanie 3. Budowa linii kablowej SN 15kV wraz z rurociągiem światłowodowym przy ul. Ludźmierskiej w miejscowości Nowy Targ miasto Nowy Targ.Projekt umożliwi powiązanie istniejących ciągów liniowych, co da efekt w postaci zasilania dwustronnego odgałęzień linii, na których znajduje się wiele stacji transformatorowych, a równocześnie pozwoli to na rezerwowanie wybranych relacji. Inwestycje pozwolą Wnioskodawcy skuteczniej zarządzać energią elektryczną wytworzoną w ramach OZE.Budowa odcinków elektroenergetycznej sieci dystrybucyjnej linie SN i nN oraz przebudowa niezbędnych przyłączy wraz z elementami towarzyszącymi rozdzielnicami, stanowiskami słupowymi, stacjami transformatorowymi, złączami kablowymi umożliwi przyłączanie jednostek wytwarzania energii elektrycznej ze źródeł odnawialnych w rozproszeniu. Wybrane rozwiązania techniczne oraz architektoniczne, budowa tam gdzie było to konieczne linii kablowych, są rozwiązaniami wypracowanymi w toku negocjacji z właścicielami gruntów. Wybrano rozwiązania najbardziej korzystne kosztowo i jednocześnie akceptowalne przez właścicieli gruntów.Ciąg dalszy w pkt Q. (Polish)
0 references
Implementation of the project is necessary to ensure the proper functioning of the electricity grid in the district of powiats: it’s New and Tatra. In communes where the project is located, a significant increase in the number of RES installations producing electricity is planned.The project consists of 3 tasks of building linear lines:Task 1. Construction of the overhead cable network SN 15 kV of relations: station 6733 Leśnica 5 column C 231 in order to link line lines between GPZ Białka Tatrzańska and GPZ Szaflary and reconstruction of line nN in Groń and Leśnica commune Bukowina Tatrzańska;Task 2. Construction of line SN 15 kV relations: station 5257 Suche Lachy station 5292 Tooth 11 Church to link line lines between GPZ Bukowina p. 27 line Poronin and GPZ Szaflary p. 15 Bańska Line in Ząb and Suche Municipality Poronin;Task 3. Construction of cable line SN 15 kV with fiber optic pipeline at ul. The project will allow linking existing line lines, which will result in the power supply of the two-sided branch of the line, where there are many transformer stations, while at the same time it will allow to book selected relationships. The investment will allow the Applicant to manage more effectively the electricity generated within the RES.Construction of sections of the electricity distribution network SN and nN lines and reconstruction of necessary connections together with elements accompanying switchgears, posts, transformer stations and cable connectors will enable connection of electricity generation units from renewable sources in dispersion. Selected technical and architectural solutions, the construction of cable lines where necessary, are solutions developed in the course of negotiations with landowners. The most cost-effective and at the same time acceptable solutions were chosen by landowners. (English)
20 October 2020
0 references
Identifiers
RPMP.04.01.02-12-1164/17
0 references