(Removed claim: summary (P836): The primary objective of the project is the production of electricity from the newly built renewable installation, in the case of the Applicant — solar energy. The applicant will contribute to the creation of a competitive market for renewable energy, ensure diversification of supplies and increase the energy security of the region, including its company. The project will contribute to increasing the use of unconventional sources of energy (RE...) |
(Created claim: summary (P836): The primary objective of the project is to produce electricity from a newly built RES installation, in the case of the Applicant – solar energy. Through the implementation of the project, the applicant will participate in the creation of a competitive market for renewable energy, ensure diversification of supply and increase the energy security of the region, including its company. The project will increase the use of unconventional energy sourc...) |
||||||||||||||
Property / summary | |||||||||||||||
The primary objective of the project is to produce electricity from a newly built RES installation, in the case of the Applicant – solar energy. Through the implementation of the project, the applicant will participate in the creation of a competitive market for renewable energy, ensure diversification of supply and increase the energy security of the region, including its company. The project will increase the use of unconventional energy sources (RES) in the overall balance sheet. The project will be carried out in 1 task, which is described in detail in point. D1 of the application for co-financing (Intrinsic and Financial Scope). Project indicators are indicated and described in point. CII and CIII of the proposal. Target groups: it’s not relevant. Technical and economic description of the products to be produced during the implementation of the project: It’s not relevant. After the project, the applicant will produce electricity for its own business. (English) | |||||||||||||||
Property / summary: The primary objective of the project is to produce electricity from a newly built RES installation, in the case of the Applicant – solar energy. Through the implementation of the project, the applicant will participate in the creation of a competitive market for renewable energy, ensure diversification of supply and increase the energy security of the region, including its company. The project will increase the use of unconventional energy sources (RES) in the overall balance sheet. The project will be carried out in 1 task, which is described in detail in point. D1 of the application for co-financing (Intrinsic and Financial Scope). Project indicators are indicated and described in point. CII and CIII of the proposal. Target groups: it’s not relevant. Technical and economic description of the products to be produced during the implementation of the project: It’s not relevant. After the project, the applicant will produce electricity for its own business. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The primary objective of the project is to produce electricity from a newly built RES installation, in the case of the Applicant – solar energy. Through the implementation of the project, the applicant will participate in the creation of a competitive market for renewable energy, ensure diversification of supply and increase the energy security of the region, including its company. The project will increase the use of unconventional energy sources (RES) in the overall balance sheet. The project will be carried out in 1 task, which is described in detail in point. D1 of the application for co-financing (Intrinsic and Financial Scope). Project indicators are indicated and described in point. CII and CIII of the proposal. Target groups: it’s not relevant. Technical and economic description of the products to be produced during the implementation of the project: It’s not relevant. After the project, the applicant will produce electricity for its own business. (English) / qualifier | |||||||||||||||
point in time: 17 October 2020
|
Revision as of 17:07, 17 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of the installation of a renewable energy source at the company Luksja Sp. z o.o. |
Project in Poland financed by DG Regio |
Statements
393,994.03 zloty
0 references
716,352.79 zloty
0 references
55.0 percent
0 references
1 October 2018
0 references
30 December 2019
0 references
ŁUKSJA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Podstawowym celem projektu jest produkcja energii elektrycznej z nowo wybudowanej instalacji wykorzystującej OZE, w przypadku Wnioskodawcy - energii słonecznej. Wnioskodawca poprzez realizacje projektu weźmie udział w tworzeniu konkurencyjnego rynku energii odnawialnej, zapewni dywersyfikację dostaw oraz wpłynie na zwiększenie bezpieczeństwa energetycznego regionu, w tym swojego przedsiębiorstwa. Projekt przyczyni się do zwiększenia wykorzystania niekonwencjonalnych źródeł energii (OZE) w bilansie ogólnym. Projekt zostanie zrealizowany w 1 zadaniu, które szczegółowo opisano w pkt. D1 wniosku o dofinansowanie (Zakres rzeczowo-finansowy). Wskaźniki projektu zostały wskazane oraz opisane w pkt. CII i CIII wniosku. Grupy docelowe: nie dotyczy. Opis techniczno-ekonomiczny produktów, które zostaną wytworzone w trakcie realizacji projektu: Nie dotyczy. Po realizacji projektu Wnioskodawca będzie produkował energię elektryczną na potrzeby własnej działalności. (Polish)
0 references
The primary objective of the project is to produce electricity from a newly built RES installation, in the case of the Applicant – solar energy. Through the implementation of the project, the applicant will participate in the creation of a competitive market for renewable energy, ensure diversification of supply and increase the energy security of the region, including its company. The project will increase the use of unconventional energy sources (RES) in the overall balance sheet. The project will be carried out in 1 task, which is described in detail in point. D1 of the application for co-financing (Intrinsic and Financial Scope). Project indicators are indicated and described in point. CII and CIII of the proposal. Target groups: it’s not relevant. Technical and economic description of the products to be produced during the implementation of the project: It’s not relevant. After the project, the applicant will produce electricity for its own business. (English)
17 October 2020
0 references
Identifiers
RPLU.04.02.00-06-0036/17
0 references