(‎Removed claim: summary (P836): The project consists of the construction of a 400 kV high-voltage double voltage power line of 110 km (220 km of the current network) on the Ostrołęka — Stanisławów line.In this section, one station 400 (220)/110 kV Wyszków and an extended two stations will be built:400/220/110 kV Ostrołęka and 400 kV Stanisławów.The project aims to improve the safety and security of the National Power System in the north-eastern part of Poland, improve the se...)
Property / summary
The project consists of the construction of a 400 kV high-voltage double voltage power line of 110 km (220 km of the current network) on the Ostrołęka — Stanisławów line.In this section, one station 400 (220)/110 kV Wyszków and an extended two stations will be built:400/220/110 kV Ostrołęka and 400 kV Stanisławów.The project aims to improve the safety and security of the National Power System in the north-eastern part of Poland, improve the security of the Warsaw agglomeration and improve the security of the Warsaw 110 kV network:to create the conditions to increase electricity exchange capacity with the Lithuanian electricity system while ensuring secure operation of this link b) creating the conditions for the removal of power from conventional and renewable energy sources (English)
 
Property / summary: The project consists of the construction of a 400 kV high-voltage double voltage power line of 110 km (220 km of the current network) on the Ostrołęka — Stanisławów line.In this section, one station 400 (220)/110 kV Wyszków and an extended two stations will be built:400/220/110 kV Ostrołęka and 400 kV Stanisławów.The project aims to improve the safety and security of the National Power System in the north-eastern part of Poland, improve the security of the Warsaw agglomeration and improve the security of the Warsaw 110 kV network:to create the conditions to increase electricity exchange capacity with the Lithuanian electricity system while ensuring secure operation of this link b) creating the conditions for the removal of power from conventional and renewable energy sources (English) / rank
Normal rank
 

Revision as of 15:32, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of the Ostrołęka — Stanisławów line, together with the construction of the station of the Wyszkow station and the expansion of the station within that line line
Project in Poland financed by DG Regio

    Statements

    0 references
    0 references
    0 references
    0 references
    0 references
    0 references
    0 references
    39,870,000.0 zloty
    0 references
    9,568,800.0 Euro
    13 January 2020
    0 references
    134,661,763.77 zloty
    0 references
    32,318,823.3 Euro
    13 January 2020
    0 references
    29.61 percent
    0 references
    1 January 2014
    0 references
    31 December 2023
    0 references
    POLSKIE SIECI ELEKTROENERGETYCZNE S.A
    0 references

    52°9'25.2"N, 21°37'36.5"E
    0 references

    52°56'55.7"N, 21°45'31.3"E
    0 references

    53°4'40.8"N, 21°34'29.6"E
    0 references

    52°47'26.2"N, 19°51'23.0"E
    0 references

    52°29'13.9"N, 21°33'49.7"E
    0 references

    52°36'16.6"N, 21°28'5.9"E
    0 references
    Przedmiotem projektu jest budowa dwutorowej linii elektroenergetycznej wysokiego napięcia 400kV o długości 110 km (220 km sieci prądowej) na odcinku Ostrołęka - Stanisławów. W tym odcinku zostanie wybudowana jedna stacja 400 (220)/110 kV Wyszków i rozbudowane dwie stacje: 400/220/110 kV Ostrołęka oraz 400 kV Stanisławów. Celem Projektu jest poprawa pewności i bezpieczeństwa pracy Krajowego Systemu Elektroenergetycznego w północno-wschodniej części Polski, poprawa pewności zasilania aglomeracji warszawskiej oraz sieci 110 kV Pośrednim celem Projektu jest: a) stworzenie warunków do zwiększenia możliwości wymiany energii elektrycznej z litewskim systemem elektroenergetycznym przy zapewnieniu bezpiecznej pracy tego połączenia b) stworzenie warunków do wyprowadzenia mocy z konwencjonalnych i odnawialnych źródeł energii (Polish)
    0 references

    Identifiers

    POIS.07.01.00-00-0002/18
    0 references