Water and wastewater management in the Złotów agglomeration (Q85218): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): Project carried out within the boundaries of the Złotów agglomeration with a population of 20 639 p.e.The agglomeration is supported by the Sewage Treatment Plant (OWWTP), located in the town of Blharassed.Scope of the project:Development of a plant combined with comprehensive modernisation, including mechanical and biological parts, a settlement management node with the construction of a new biogas facility, a network infrastructure between o...)
(‎Created claim: summary (P836): The project is carried out within the Gold conurbation with a size of 20 639 RLM. The agglomeration is served by the sewage treatment plant located in Blękwit. Scope of the project: Extension of the treatment plant combined with comprehensive modernisation including mechanical and biological parts, sedimentary economy node with the construction of a new biogas plant, infrastructure of inter-site networks and road system. The capacity of the trea...)
Property / summary
 
The project is carried out within the Gold conurbation with a size of 20 639 RLM. The agglomeration is served by the sewage treatment plant located in Blękwit. Scope of the project: Extension of the treatment plant combined with comprehensive modernisation including mechanical and biological parts, sedimentary economy node with the construction of a new biogas plant, infrastructure of inter-site networks and road system. The capacity of the treatment plant will be increased from 29,752 RLM to 35 030 RLM. In addition, a generator and sampler will be purchased for the treatment plant for raw and purified wastewater sampling. Construction of a sewer network L= 1.99 km, including the second thread of the conveying network for the treatment plant L=0,88km. Reconstruction of sanitary sewage system L=2.85 km Reconstruction of network sewage pumping plants – 5 kpl. Construction of the water supply network L=2.20 km, including the water mains in ul. Queen Jadwiga Rogatka L=1.2 km Reconstruction of the water supply network L=10.06 km Number of new users of the sewage network who will join the network as a result of the project – 96 RLM Investments related to the reconstruction of the water supply system will help reduce water losses resulting from leakage of the distribution system, saving water used for rinsing the network, reducing failure. Total water savings 29000 m³/year. (English)
Property / summary: The project is carried out within the Gold conurbation with a size of 20 639 RLM. The agglomeration is served by the sewage treatment plant located in Blękwit. Scope of the project: Extension of the treatment plant combined with comprehensive modernisation including mechanical and biological parts, sedimentary economy node with the construction of a new biogas plant, infrastructure of inter-site networks and road system. The capacity of the treatment plant will be increased from 29,752 RLM to 35 030 RLM. In addition, a generator and sampler will be purchased for the treatment plant for raw and purified wastewater sampling. Construction of a sewer network L= 1.99 km, including the second thread of the conveying network for the treatment plant L=0,88km. Reconstruction of sanitary sewage system L=2.85 km Reconstruction of network sewage pumping plants – 5 kpl. Construction of the water supply network L=2.20 km, including the water mains in ul. Queen Jadwiga Rogatka L=1.2 km Reconstruction of the water supply network L=10.06 km Number of new users of the sewage network who will join the network as a result of the project – 96 RLM Investments related to the reconstruction of the water supply system will help reduce water losses resulting from leakage of the distribution system, saving water used for rinsing the network, reducing failure. Total water savings 29000 m³/year. (English) / rank
 
Normal rank
Property / summary: The project is carried out within the Gold conurbation with a size of 20 639 RLM. The agglomeration is served by the sewage treatment plant located in Blękwit. Scope of the project: Extension of the treatment plant combined with comprehensive modernisation including mechanical and biological parts, sedimentary economy node with the construction of a new biogas plant, infrastructure of inter-site networks and road system. The capacity of the treatment plant will be increased from 29,752 RLM to 35 030 RLM. In addition, a generator and sampler will be purchased for the treatment plant for raw and purified wastewater sampling. Construction of a sewer network L= 1.99 km, including the second thread of the conveying network for the treatment plant L=0,88km. Reconstruction of sanitary sewage system L=2.85 km Reconstruction of network sewage pumping plants – 5 kpl. Construction of the water supply network L=2.20 km, including the water mains in ul. Queen Jadwiga Rogatka L=1.2 km Reconstruction of the water supply network L=10.06 km Number of new users of the sewage network who will join the network as a result of the project – 96 RLM Investments related to the reconstruction of the water supply system will help reduce water losses resulting from leakage of the distribution system, saving water used for rinsing the network, reducing failure. Total water savings 29000 m³/year. (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 15:16, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Water and wastewater management in the Złotów agglomeration
Project in Poland financed by DG Regio

    Statements

    0 references
    25,976,455.49 zloty
    0 references
    6,234,349.32 Euro
    13 January 2020
    0 references
    30,560,535.88 zloty
    0 references
    7,334,528.61 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    23 October 2015
    0 references
    31 August 2021
    0 references
    MIEJSKI ZAKŁAD WODOCIĄGÓW I KANALIZACJI SPÓŁKA Z O.O.
    0 references
    0 references
    0 references
    Projekt realizowany w granicach aglomeracji Złotów o wielkości 20 639 RLM. Aglomerację obsługuje Oczyszczalnia Ścieków w zlokalizowana w miejscowości Blękwit. Zakres projektu: Rozbudowa oczyszczalni połączona z kompleksową modernizacją obejmująca część mechaniczną i biologiczną, węzeł gospodarki osadowej z budową nowej instalacji do biogazu, infrastrukturę sieci między obiektowych oraz układ drogowy. Nastąpi zwiększenie przepustowości oczyszczalni z 29 752 RLM do 35 030 RLM. Dodatkowo na potrzeby oczyszczalni zakupiony będzie agregat prądotwórczy i sampler do poboru prób ścieków surowych i oczyszczonych. Budowa sieci kanalizacyjnej L= 1,99 km, w tym druga nitka sieci przesyłowej tłocznej na oczyszczalnię L=0,88km. Przebudowa kanalizacji sanitarnej L=2,85 km Przebudowa sieciowych przepompowni ścieków – 5 kpl. Budowa sieci wodociągowej L=2,20 km, w tym magistrali wodociągowej w ul. Królowej Jadwigi Rogatki L=1,2 km Przebudowa sieci wodociągowej L=10,06 km Liczba nowych użytkowników sieci kanalizacyjnej, którzy przyłączą się do sieci w wyniku realizacji projektu - 96 RLM Inwestycje związane z przebudową sieci wodociągowej przyczynią się do zmniejszenia strat wody wynikających z nieszczelności systemu dystrybucyjnego, oszczędności wody zużywanej na płukanie sieci, zmniejszeniem awaryjności. Łączna oszczędność wody 29 000 m3/rok. (Polish)
    0 references
    The project is carried out within the Gold conurbation with a size of 20 639 RLM. The agglomeration is served by the sewage treatment plant located in Blękwit. Scope of the project: Extension of the treatment plant combined with comprehensive modernisation including mechanical and biological parts, sedimentary economy node with the construction of a new biogas plant, infrastructure of inter-site networks and road system. The capacity of the treatment plant will be increased from 29,752 RLM to 35 030 RLM. In addition, a generator and sampler will be purchased for the treatment plant for raw and purified wastewater sampling. Construction of a sewer network L= 1.99 km, including the second thread of the conveying network for the treatment plant L=0,88km. Reconstruction of sanitary sewage system L=2.85 km Reconstruction of network sewage pumping plants – 5 kpl. Construction of the water supply network L=2.20 km, including the water mains in ul. Queen Jadwiga Rogatka L=1.2 km Reconstruction of the water supply network L=10.06 km Number of new users of the sewage network who will join the network as a result of the project – 96 RLM Investments related to the reconstruction of the water supply system will help reduce water losses resulting from leakage of the distribution system, saving water used for rinsing the network, reducing failure. Total water savings 29000 m³/year. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.02.03.00-00-0034/17
    0 references