Construction of the S19 Lublin — Rzeszów express road. - Q85871 (Q85871): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project aims to build the S19 Lublin — Rzeszów express road.41.93 km long.This draft consists of three implementation sections:1.Part No 1. — Thorn Węglin (no node) — in the Hold Duża (with interchange) from km 0 + 000,00 to km 12 + 046,36;2.(part No 2) — in the Nedzawka Duża (junction) — in the Kraśnik Północ (junction), from km 12 + 046,36 to km 32 + 000,00;3.Parts No 3 — in the North Kraśnik Północ (with interchange), from km 32 + 000,0...)
(‎Created claim: summary (P836): The project aims to build an expressway S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w. Kraśnik South with a length of 41.93 km. The project consists of three sections of the project: 1. Part no. 1 – w. Lublin Węglin (without a node) – w. Nie doorzwica Duża (with a node) – from km 0 + 000.00 to km 12 + 046,36; 2. Part No. 2 – w. Nie doorzwica Large (without a node) – w. Kraśnik Północ (without a node) – from km 12 + 046.36 to km 32 + 000,00; 3....)
Property / summary
 
The project aims to build an expressway S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w. Kraśnik South with a length of 41.93 km. The project consists of three sections of the project: 1. Part no. 1 – w. Lublin Węglin (without a node) – w. Nie doorzwica Duża (with a node) – from km 0 + 000.00 to km 12 + 046,36; 2. Part No. 2 – w. Nie doorzwica Large (without a node) – w. Kraśnik Północ (without a node) – from km 12 + 046.36 to km 32 + 000,00; 3. Part No. 3 – w. Kraśnik Północ (with a node) – w. Kraśnik Południe (with a knot) – from km 32 + 000.00 to km 41 + 934,40; The investment is implemented in the Design & Build system. A two-way cross-section with two lanes (and a reserve for additional lanes for the 2x3 lanes target section) and an emergency lane, adapted to the forecast traffic level, is provided for the entire section of the investment. The road junctions designed, as part of this investment, will allow safe communication and distribution of traffic on the rest of the road network and the operation of adjacent land through the network of service roads. The project, including the S19 expressway, is located in Lubelskie Voivodeship, Lublin County in the following areas: the communes of Konopnica, Niedrzwica Duża and Strzyżewice and in Kraśnik County, Wilkołaz and Kraśnik, and Kraśnik. (English)
Property / summary: The project aims to build an expressway S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w. Kraśnik South with a length of 41.93 km. The project consists of three sections of the project: 1. Part no. 1 – w. Lublin Węglin (without a node) – w. Nie doorzwica Duża (with a node) – from km 0 + 000.00 to km 12 + 046,36; 2. Part No. 2 – w. Nie doorzwica Large (without a node) – w. Kraśnik Północ (without a node) – from km 12 + 046.36 to km 32 + 000,00; 3. Part No. 3 – w. Kraśnik Północ (with a node) – w. Kraśnik Południe (with a knot) – from km 32 + 000.00 to km 41 + 934,40; The investment is implemented in the Design & Build system. A two-way cross-section with two lanes (and a reserve for additional lanes for the 2x3 lanes target section) and an emergency lane, adapted to the forecast traffic level, is provided for the entire section of the investment. The road junctions designed, as part of this investment, will allow safe communication and distribution of traffic on the rest of the road network and the operation of adjacent land through the network of service roads. The project, including the S19 expressway, is located in Lubelskie Voivodeship, Lublin County in the following areas: the communes of Konopnica, Niedrzwica Duża and Strzyżewice and in Kraśnik County, Wilkołaz and Kraśnik, and Kraśnik. (English) / rank
 
Normal rank
Property / summary: The project aims to build an expressway S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w. Kraśnik South with a length of 41.93 km. The project consists of three sections of the project: 1. Part no. 1 – w. Lublin Węglin (without a node) – w. Nie doorzwica Duża (with a node) – from km 0 + 000.00 to km 12 + 046,36; 2. Part No. 2 – w. Nie doorzwica Large (without a node) – w. Kraśnik Północ (without a node) – from km 12 + 046.36 to km 32 + 000,00; 3. Part No. 3 – w. Kraśnik Północ (with a node) – w. Kraśnik Południe (with a knot) – from km 32 + 000.00 to km 41 + 934,40; The investment is implemented in the Design & Build system. A two-way cross-section with two lanes (and a reserve for additional lanes for the 2x3 lanes target section) and an emergency lane, adapted to the forecast traffic level, is provided for the entire section of the investment. The road junctions designed, as part of this investment, will allow safe communication and distribution of traffic on the rest of the road network and the operation of adjacent land through the network of service roads. The project, including the S19 expressway, is located in Lubelskie Voivodeship, Lublin County in the following areas: the communes of Konopnica, Niedrzwica Duża and Strzyżewice and in Kraśnik County, Wilkołaz and Kraśnik, and Kraśnik. (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 14:53, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of the S19 Lublin — Rzeszów express road. - Q85871
Project in Poland financed by DG Regio

    Statements

    0 references
    0 references
    0 references
    0 references
    0 references
    0 references
    736,586,673.09 zloty
    0 references
    176,780,801.54 Euro
    13 January 2020
    0 references
    866,572,556.58 zloty
    0 references
    207,977,413.58 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2014
    0 references
    31 December 2022
    0 references
    GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD
    0 references
    0 references

    50°56'36.6"N, 22°12'30.2"E
    0 references

    50°59'11.8"N, 22°19'40.8"E
    0 references

    51°13'34.3"N, 22°27'41.4"E
    0 references

    51°6'51.1"N, 22°23'16.1"E
    0 references

    51°2'49.9"N, 22°26'12.1"E
    0 references
    Projekt ma na celu budowę drogi ekspresowej S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w . Kraśnik Południe o długości 41,93 km. Przedmiotowy Projekt, składa się z trzech odcinków realizacyjnych: 1. Część nr 1 - w. Lublin Węglin (bez węzła) – w. Niedrzwica Duża (z węzłem) – od km 0+000,00 do km 12+046,36; 2. Części nr 2 - w. Niedrzwica Duża (bez węzła) – w. Kraśnik Północ (bez węzła) – od km 12+046,36 do km 32+000,00; 3. Części nr 3 - w. Kraśnik Północ (z węzłem) – w. Kraśnik Południe (z węzłem) – od km 32+000,00 do km 41+934,40; Inwestycja jest realizowana w systemie Projektuj & Buduj. Na całym odcinku przedmiotowej inwestycji przewidziano przekrój dwujezdniowy z dwoma pasami ruchu (i rezerwą na dodatkowy pas ruchu, do przekroju docelowego 2x3 pasy ruchu) oraz pasem awaryjnym, dostosowany do prognozowanego poziomu ruchu. Zaprojektowane, w ramach przedmiotowej inwestycji, węzły drogowe, umożliwią bezpieczną komunikację i rozprowadzenie ruchu po pozostałej sieci drogowej oraz obsługę przyległego terenu poprzez sieć dróg serwisowych. Przedmiotowy Projekt, obejmujący drogę ekspresową S19, zlokalizowany jest w województwie lubelskim, w powiecie lubelskim na terenie: gminy Konopnica, Niedrzwica Duża i Strzyżewice oraz w powiecie kraśnickim na terenie gminy Wilkołaz i Kraśnik oraz na terenie miasta Kraśnik. (Polish)
    0 references
    The project aims to build an expressway S19 Lublin – Rzeszów, odc. w. Lublin Węglin – w. Kraśnik South with a length of 41.93 km. The project consists of three sections of the project: 1. Part no. 1 – w. Lublin Węglin (without a node) – w. Nie doorzwica Duża (with a node) – from km 0 + 000.00 to km 12 + 046,36; 2. Part No. 2 – w. Nie doorzwica Large (without a node) – w. Kraśnik Północ (without a node) – from km 12 + 046.36 to km 32 + 000,00; 3. Part No. 3 – w. Kraśnik Północ (with a node) – w. Kraśnik Południe (with a knot) – from km 32 + 000.00 to km 41 + 934,40; The investment is implemented in the Design & Build system. A two-way cross-section with two lanes (and a reserve for additional lanes for the 2x3 lanes target section) and an emergency lane, adapted to the forecast traffic level, is provided for the entire section of the investment. The road junctions designed, as part of this investment, will allow safe communication and distribution of traffic on the rest of the road network and the operation of adjacent land through the network of service roads. The project, including the S19 expressway, is located in Lubelskie Voivodeship, Lublin County in the following areas: the communes of Konopnica, Niedrzwica Duża and Strzyżewice and in Kraśnik County, Wilkołaz and Kraśnik, and Kraśnik. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.03.01.00-00-0051/19
    0 references