Reconstruction of heat networks in Cieszyn, with the construction of connections and district heating stations in order to eliminate block nodes. (Q85005): Difference between revisions
Jump to navigation
Jump to search
(Removed claim: summary (P836): The planned project will be implemented by the replacement of a heat network to preinsulated underground heat, the construction of a preinsulated heat network on new legs or through an exchange of thermal insulation on existing air heat networks pipelines, including the necessary maintenance and repair of the steel support steel and pipe structures.The project will result in the removal of district heating chambers.In addition, links will be b...) |
(Created claim: summary (P836): The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the...) |
||||||||||||||
Property / summary | |||||||||||||||
The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the underground heat cut will be carried out. In addition, connections to existing buildings with individual nodes will be built, so that group nodes can be removed. (English) | |||||||||||||||
Property / summary: The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the underground heat cut will be carried out. In addition, connections to existing buildings with individual nodes will be built, so that group nodes can be removed. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the underground heat cut will be carried out. In addition, connections to existing buildings with individual nodes will be built, so that group nodes can be removed. (English) / qualifier | |||||||||||||||
point in time: 14 October 2020
|
Revision as of 14:51, 14 October 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of heat networks in Cieszyn, with the construction of connections and district heating stations in order to eliminate block nodes. |
Project in Poland financed by DG Regio |
Statements
8,396,296.13 zloty
0 references
18,276,716.5 zloty
0 references
45.94 percent
0 references
29 May 2017
0 references
31 January 2021
0 references
ENERGETYKA CIESZYŃSKA SP. Z O.O.
0 references
Projektowane przedsięwzięcie realizowane będzie poprzez wymianę kanałowej sieci cieplnej na preizolowaną podziemną cieć cieplną, budowę preizolowanej sieci cieplnej na nowych odcinkach lub przez wymianę izolacji termicznej na istniejących napowietrzonych rurociągach sieci cieplnej wraz z wykonaniem niezbędnych konserwacji i napraw konstrukcji wsporczej stalowej i żelbetowej rurociągów. W ramach przedsięwzięcia wykonana zostanie likwidacja komór ciepłowniczych podziemnej cieci cieplnej. Ponadto zostaną wybudowane przyłącza do istniejących budynków wraz z węzłami indywidulanymi, dzięki czemu możliwa będzie likwidacja węzłów grupowych. (Polish)
0 references
The project will be implemented through the replacement of the channel heat network with pre-insulated underground heat cuts, the construction of a pre-insulated thermal network on new sections or by replacing thermal insulation on existing aerated thermal network pipelines with the necessary maintenance and repair of the steel and reinforced concrete structure of pipelines. As part of the project, the liquidation of the heating chambers of the underground heat cut will be carried out. In addition, connections to existing buildings with individual nodes will be built, so that group nodes can be removed. (English)
14 October 2020
0 references
Identifiers
POIS.01.07.02-00-0001/17
0 references