Construction of a combined heat and power station in Minsk Mazowiecki (Q84890): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): This project is linked to the installation of a cogeneration system within the existing boiler of PEC Sp. z o. o. in Minsk Mazowiecki.As a result of the investment, the current boiler in Minsk Mazowiecki at ul.1 PLM Warszawa 1 will be converted into a combined heat and power plant.The project assumes the use of natural gas as a fuel.The electricity produced will be used for own purposes and the surplus will be sold to the Energy Plant.The proj...)
(‎Created claim: summary (P836): This project is connected with the installation of the cogeneration system within the existing boiler room belonging to PEC Sp. z o. o. in Minsk Mazowiecki. As a result of the investment, the current boiler room operating in Minsk Mazowiecki on ul. 1 PLM Warszawa 1 will be transformed into a CHP plant. The project assumes the use of natural gas as fuel. The electricity produced will be used for own use and its excess will be sold to the Energy P...)
Property / summary
 
This project is connected with the installation of the cogeneration system within the existing boiler room belonging to PEC Sp. z o. o. in Minsk Mazowiecki. As a result of the investment, the current boiler room operating in Minsk Mazowiecki on ul. 1 PLM Warszawa 1 will be transformed into a CHP plant. The project assumes the use of natural gas as fuel. The electricity produced will be used for own use and its excess will be sold to the Energy Plant. The project will be implemented in Mazowieckie Voivodeship, Minsk County, the city of Mińsk Mazowiecki, on ul. 1PLM Warszawa 1, on land with geodesic number 2476/3, within the registration area 0001 Mińsk Mazowiecki. (English)
Property / summary: This project is connected with the installation of the cogeneration system within the existing boiler room belonging to PEC Sp. z o. o. in Minsk Mazowiecki. As a result of the investment, the current boiler room operating in Minsk Mazowiecki on ul. 1 PLM Warszawa 1 will be transformed into a CHP plant. The project assumes the use of natural gas as fuel. The electricity produced will be used for own use and its excess will be sold to the Energy Plant. The project will be implemented in Mazowieckie Voivodeship, Minsk County, the city of Mińsk Mazowiecki, on ul. 1PLM Warszawa 1, on land with geodesic number 2476/3, within the registration area 0001 Mińsk Mazowiecki. (English) / rank
 
Normal rank
Property / summary: This project is connected with the installation of the cogeneration system within the existing boiler room belonging to PEC Sp. z o. o. in Minsk Mazowiecki. As a result of the investment, the current boiler room operating in Minsk Mazowiecki on ul. 1 PLM Warszawa 1 will be transformed into a CHP plant. The project assumes the use of natural gas as fuel. The electricity produced will be used for own use and its excess will be sold to the Energy Plant. The project will be implemented in Mazowieckie Voivodeship, Minsk County, the city of Mińsk Mazowiecki, on ul. 1PLM Warszawa 1, on land with geodesic number 2476/3, within the registration area 0001 Mińsk Mazowiecki. (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 14:43, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of a combined heat and power station in Minsk Mazowiecki
Project in Poland financed by DG Regio

    Statements

    0 references
    8,911,870.0 zloty
    0 references
    2,138,848.8 Euro
    13 January 2020
    0 references
    21,216,380.0 zloty
    0 references
    5,091,931.2 Euro
    13 January 2020
    0 references
    42.0 percent
    0 references
    29 January 2018
    0 references
    30 June 2020
    0 references
    PRZEDSIĘBIORSTWO ENERGETYKI CIEPLNEJ SPÓŁKA Z OGRANICZONA ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references
    0 references
    Niniejsze przedsięwzięcie związane jest z instalacją układu kogeneracji w ramach istniejącej kotłowni należącej do PEC Sp. z o. o. w Mińsku Mazowieckim. W wyniku realizacji inwestycji obecna kotłownia funkcjonująca w Mińsku Mazowieckim przy ul. 1 PLM Warszawa 1 przekształci się w elektrociepłownię. W projekcie założono zastosowanie gazu ziemnego jako paliwa. Produkowana energia elektryczna będzie wykorzystywana na potrzeby własne, a jej nadmiar zostanie sprzedany do Zakładu Energetycznego. Projekt będzie realizowany w województwie mazowieckim, powiecie mińskim, mieście Mińsk Mazowiecki, przy ul. 1PLM Warszawa 1, na działce o numerze geodezyjnym 2476/3, w obrębie ewidencyjnym 0001 Mińsk Mazowiecki. (Polish)
    0 references
    This project is connected with the installation of the cogeneration system within the existing boiler room belonging to PEC Sp. z o. o. in Minsk Mazowiecki. As a result of the investment, the current boiler room operating in Minsk Mazowiecki on ul. 1 PLM Warszawa 1 will be transformed into a CHP plant. The project assumes the use of natural gas as fuel. The electricity produced will be used for own use and its excess will be sold to the Energy Plant. The project will be implemented in Mazowieckie Voivodeship, Minsk County, the city of Mińsk Mazowiecki, on ul. 1PLM Warszawa 1, on land with geodesic number 2476/3, within the registration area 0001 Mińsk Mazowiecki. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.01.06.01-00-0020/18
    0 references