Improve the energy efficiency of the buildings of the Criminal Office (Q84562): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Removed claim: summary (P836): The project will consist of the thermo-modernisation of the 15 buildings of the branch of the Krzywo-branch office with the use of RES, which will lead to a reduction of at least 25 % in final energy.The thermal modernisation work will consist of the replacement of two gas oil boilers that require an exchange due to the type of operation and unfavourable parameters, for two condensing boilers, operating in the cascade, with a power of 500 kW e...)
(‎Created claim: summary (P836): The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each...)
Property / summary
 
The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each and two air/water heat pumps with a capacity of 18 kW each. The heating network will also be upgraded (existing pipelines were installed in 2006) and with it a hot water system. Photovoltaic panels will be installed to reduce emissions of harmful substances into the atmosphere. The buildings are equipped with counters necessary for the proper presentation of data on consumption and production of heat and electricity. As part of the project, thermostats and upholstery valves will be installed. The applicant intends to modernise the lighting and replace traditional fluorescent lamps with LED lamps. Most of the buildings also need to be thermally modernised. In building 27, the renovation requires an oblique roof. It is also necessary to modernise the exterior walls of the buildings. It is necessary to make appropriately designed floors on the ground. The building for the gym (27) provides for the installation of mechanical ventilation with heat recovery. The eligible costs of the project also include information and promotion activities and preparatory work (preparation of necessary documentation) and construction supervision. (English)
Property / summary: The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each and two air/water heat pumps with a capacity of 18 kW each. The heating network will also be upgraded (existing pipelines were installed in 2006) and with it a hot water system. Photovoltaic panels will be installed to reduce emissions of harmful substances into the atmosphere. The buildings are equipped with counters necessary for the proper presentation of data on consumption and production of heat and electricity. As part of the project, thermostats and upholstery valves will be installed. The applicant intends to modernise the lighting and replace traditional fluorescent lamps with LED lamps. Most of the buildings also need to be thermally modernised. In building 27, the renovation requires an oblique roof. It is also necessary to modernise the exterior walls of the buildings. It is necessary to make appropriately designed floors on the ground. The building for the gym (27) provides for the installation of mechanical ventilation with heat recovery. The eligible costs of the project also include information and promotion activities and preparatory work (preparation of necessary documentation) and construction supervision. (English) / rank
 
Normal rank
Property / summary: The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each and two air/water heat pumps with a capacity of 18 kW each. The heating network will also be upgraded (existing pipelines were installed in 2006) and with it a hot water system. Photovoltaic panels will be installed to reduce emissions of harmful substances into the atmosphere. The buildings are equipped with counters necessary for the proper presentation of data on consumption and production of heat and electricity. As part of the project, thermostats and upholstery valves will be installed. The applicant intends to modernise the lighting and replace traditional fluorescent lamps with LED lamps. Most of the buildings also need to be thermally modernised. In building 27, the renovation requires an oblique roof. It is also necessary to modernise the exterior walls of the buildings. It is necessary to make appropriately designed floors on the ground. The building for the gym (27) provides for the installation of mechanical ventilation with heat recovery. The eligible costs of the project also include information and promotion activities and preparatory work (preparation of necessary documentation) and construction supervision. (English) / qualifier
 
point in time: 14 October 2020
Timestamp+2020-10-14T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:10, 14 October 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Improve the energy efficiency of the buildings of the Criminal Office
Project in Poland financed by DG Regio

    Statements

    0 references
    7,976,545.91 zloty
    0 references
    1,914,371.02 Euro
    13 January 2020
    0 references
    9,384,171.67 zloty
    0 references
    2,252,201.2 Euro
    13 January 2020
    0 references
    85.0 percent
    0 references
    1 January 2018
    0 references
    30 September 2022
    0 references
    ZAKŁAD KARNY W KRZYWAŃCU
    0 references
    0 references
    0 references
    Projekt będzie polegał na termomodernizacji 15 budynków Zakładu Karnego w Krzywańcu wraz z wykorzystaniem OZE, co doprowadzi do redukcji energii końcowej o co najmniej 25%. Prace termomodernizacyjne polegać będą na wymianie dwóch kotłów gazowo-olejowych, które wymagają wymiany ze względu na stopień eksploatacji i niekorzystne parametry, na dwa kotły kondensacyjne, pracujące w kaskadzie, o mocy 500 kW każdy i dwie pompy ciepła powietrze/woda o mocy 18 kW każda. Modernizacji zostanie poddana także sieć ciepłownicza (istniejące rurociągi zostały zainstalowane w 2006 r.), a wraz z nią system ciepłej wody użytkowej. Zainstalowane zostaną panele fotowoltaiczne, pozwalające na redukcję emisji szkodliwych substancji do atmosfery. W budynkach zainstalowane są liczniki niezbędne do prawidłowego prezentowania danych o zużyciu oraz produkcji ciepła i energii elektrycznej. W ramach projektu zostaną zainstalowane termostaty i zawory podpionowe. Wnioskodawca zamierza przeprowadzić modernizację oświetlenia, a w jej ramach wymianę tradycyjnych świetlówek na lampy LED. W większości budynków należy także przeprowadzić termomodernizację dachów. W budynku 27 modernizacji wymaga dach skośny. Konieczna jest również modernizacja ścian zewnętrznych budynków. Konieczne jest wykonanie odpowiednio zaprojektowanych podłóg na gruncie. W budynku dla sali gimnastycznej (27) przewiduje się zainstalowanie wentylacji mechanicznej z odzyskiem ciepła. W skład kosztów kwalifikowalnych projektu wchodzą także działania informacyjno-promocyjne i prace przygotowawcze (przygotowanie niezbędnej dokumentacji) oraz nadzór budowlany. (Polish)
    0 references
    The project will consist of the thermomodernisation of 15 buildings of the Criminal Facility in Cursaniec with the use of RES, which will lead to a reduction of final energy by at least 25 %. The thermal modernisation works will consist of the replacement of two gas-oil boilers, which require replacement due to the level of operation and unfavourable parameters, for two condensation boilers operating in a cascade, with a capacity of 500 kW each and two air/water heat pumps with a capacity of 18 kW each. The heating network will also be upgraded (existing pipelines were installed in 2006) and with it a hot water system. Photovoltaic panels will be installed to reduce emissions of harmful substances into the atmosphere. The buildings are equipped with counters necessary for the proper presentation of data on consumption and production of heat and electricity. As part of the project, thermostats and upholstery valves will be installed. The applicant intends to modernise the lighting and replace traditional fluorescent lamps with LED lamps. Most of the buildings also need to be thermally modernised. In building 27, the renovation requires an oblique roof. It is also necessary to modernise the exterior walls of the buildings. It is necessary to make appropriately designed floors on the ground. The building for the gym (27) provides for the installation of mechanical ventilation with heat recovery. The eligible costs of the project also include information and promotion activities and preparatory work (preparation of necessary documentation) and construction supervision. (English)
    14 October 2020
    0 references

    Identifiers

    POIS.01.03.01-00-0072/17
    0 references