Reconstruction of the heat generation system using renewable energies — heat pump with ground heat exchanger — SP in Sławsk, Gmina Sławno (Q137800): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item) |
(Removed claim: EU contribution (P835): 177,720.312 euro) |
||||||||||||||
Property / EU contribution | |||||||||||||||
| |||||||||||||||
Property / EU contribution: 177,720.312 Euro / rank | |||||||||||||||
Property / EU contribution: 177,720.312 Euro / qualifier | |||||||||||||||
| |||||||||||||||
Property / EU contribution: 177,720.312 Euro / qualifier | |||||||||||||||
|
Revision as of 14:49, 24 September 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Reconstruction of the heat generation system using renewable energies — heat pump with ground heat exchanger — SP in Sławsk, Gmina Sławno |
Project in Poland financed by DG Regio |
Statements
740,501.3 zloty
0 references
871,178.0 zloty
0 references
85.0 percent
0 references
24 June 2016
0 references
28 June 2019
0 references
GMINA SŁAWNO
0 references
Zakres przedmiotowego projektu obejmuje przebudowę kotłowni olejowej na instalację pompy ciepła wspomaganą kotłem olejowym w Zespole Szkół w Sławsku. Obecnie system wytwarzania energii cieplnej Zespołu Szkół w Sławsku składa się z dwóch kotłów olejowych działających w kaskadzie o mocy 130 KW każdy. Planowana inwestycja zakłada pozostawienie jednego z kotłów olejowych jako źródła szczytowego i wykonanie odnawialnego źródła energii w postaci pompy ciepła o mocy 106,6 kW. Dolnym źródłem instalacji pompy ciepła będą odwierty pionowe w liczbie 19 szt. Każdy o głębokości 100m.W ramach projektu przewidziano następujące etapy:1)przygotowanie dokumentacji technicznej i kosztorysowej wraz ze zgłoszeniem oraz następnie studium wykonalności, 2)wyłonienie firmy oraz przeprowadzenie prac budowlano-montażowych pompy ciepła zgodnie z projektem. 3)nadzór nad inwestycją przez inspektora nadzoru oraz 4)promocja projektu. Ostatecznie inwestycja ma na celu zmniejszenie kosztów ogrzewania obiektu, zastąpienie jednego z kotłów odnawialnymi źródłami energii oraz tym samym zmniejszenie emisji gazów cieplarnianych do atmosfery. Szczegółowy zakres rzeczowy przedstawiono w rozdziale 4.1.3.2 studium wykonalności.Inwestycja zostanie wdrożona w życie po przeprowadzeniu przetargu nieograniczonego,w ramach którego zostanie wyłoniona firma,która przeprowadzi prace projektowe oraz budowlano-montażowe. Po zakończeniu projektu możliwe będzie wykorzystanie pełnej funkcjonalności infrastruktury powstałej w ramach realizacji projektu i nie będzie to wymagało już dodatkowych działań ani wdrażania innych projektów. Gmina Sławno posiada i zapewni na swoim obszarze zasoby techniczne,kadrowe i wiedzę gwarantującą uruchomienie funkcjonowania infrastruktury po zakończeniu projektu.Będą to osoby zatrudnione obecnie w Gminie z wieloletnim doświadczeniem we wdrażaniu podobnych inwestycji.Charakter inwestycji jest stacjonarny o czym świadczy wskazanie lokalizacji projektu. (Polish)
0 references
The scope of the project involves converting the oil boiler plant to the installation of a heat pump for the oil boiler in the District of Sławsk. At present, the district heating system in Sławsko is composed of two oil boilers operating within the cascade of 130 KW each. The planned investment will leave one of the oil boilers as a source of peak and a renewable energy source in the form of a heat pump with a power of 106.6 kW. The lower source of the heat pump installation will be 19 vertical wells. At a depth of 100 M.As part of the project, the project envisages the following steps: (1) the preparation of the technical documentation and the financial statement together with the notification and subsequent feasibility study, 2) the company to be selected and the construction and assembly of the heat pump to be carried out in accordance with the project. (3) the supervision of the investment by the supervisory inspector and (4) the promotion of the project. Ultimately, the investment aims at reducing the costs of heating the site, replacing one of the boilers with renewable energy sources and reducing the greenhouse gas emissions to the atmosphere. Detailed material scope is provided in chapter 4.1.3.2 of the feasibility study. the investment will be put into effect following an open tender in which the company that will carry out the design and construction and assembly works will be selected. At the end of the project, it will be possible to make use of the full functionality of the infrastructure created by the project and this will not require any further action or implementation of other projects. The Municipality of Sławno has and will provide technical resources, human resources and knowledge to ensure that the infrastructure is operational upon completion of the project.These are the persons currently employed in the municipality with years of experience in implementing similar investments. the nature of the investment is a stationary indication of the location of the project. (English)
0 references
Identifiers
RPZP.02.10.00-32-B174/17
0 references