ELECTRIC STATION PICERNO (Q2021711): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Changed an Item)
Property / contained in NUTS
 
Property / contained in NUTS: Province of Potenza / rank
 
Normal rank

Revision as of 02:25, 16 July 2020

Project in Italy financed by DG Regio
Language Label Description Also known as
English
ELECTRIC STATION PICERNO
Project in Italy financed by DG Regio

    Statements

    0 references
    5,784,236.38 Euro
    0 references
    7,829,660.8 Euro
    0 references
    73.88 percent
    0 references
    6 September 2017
    0 references
    31 July 2019
    0 references
    TERNA - RETE ELETTRICA NAZIONALE
    0 references
    0 references

    40°38'18.46"N, 15°38'9.13"E
    0 references
    L'INTERVENTO RIGUARDA LA REALIZZAZIONE DI UNA NUOVA STAZIONE RTN IN DOPPIA SBARRA A 150 KV DA INSERIRE IN ENTRA-ESCE SUI NUOVI COLLEGAMENTI A 150 KV 'CP TITO SMISTAMENTO-CP AVIGLIANO' E 'CP TITO SMISTAMENTO-TANAGRO'.LA REALIZZAZIONE DI TALE STAZIONE SI RENDE NECESSARIA PER AUMENTARE L'AFFIDABILITà DELLA RTN IN UN'AREA NELLA QUALE VI Ê UN'ELEVATA RICHIESTA DI CONNESSIONI (STMG APPROVATE PER 479 MW) OLTRE A PREVENTIVI ACCETTATI DAL DISTRIBUTORE (63 MW SULLA RETE AT E 6 MW SULLA RETE BTBT) CHE, IN ASSENZA DELL'OPERA IN ESAME, NON POTREBBERO ESSERE IMMESSE IN RETE A CAUSA DELLA LIMITATA PORTATA DELLE DIRETTRICI 150 KV 'TANAGRO-POTENZA' E 'TANAGRO-TITO-POTENZA' CHE HANNO UNA CAPACITà DI TRASPORTO NOMINALE DI CIRCA 145 MW CIASCUNA, PER UN TOTALE COMPLESSIVO PARI A 290 MW.L'INTERVENTO OLTRE ALLA REALIZZAZIONE DELLA NUOVA S.E. RIGUARDERà ANCHE LA REALIZZAZIONE DEI RELATIVI RACCORDI I CUI TRACCIATI SI DIRAMANO DAI DUE ELETTRODOTTI ESISTENTI TITO SMISTAMENTO-AVIGLIANO E TITO SMISTAMENTO-TA (Italian)
    0 references
    THE INTERVENTION CONCERNS THE CONSTRUCTION OF A NEW 150 KV DOUBLE RAIL NETWORK STATION TO BE INTEGRATED INTO ENTRA-ESEC ON THE NEW 150 KV ‘CP TITO SMISTINGTO-CP AVILIANO’ AND ‘CP TITO SMISTINGTO-TANAGRO’. THE CONSTRUCTION OF THIS STATION IS NECESSARY TO INCREASE L’AFFIDABILITY IN AN AREA WHERE THERE IS A HIGH DEMAND FOR CONNECTIONS (479 MW ON THE TA NETWORK AND 6 MW ON THE BTBT NETWORK), WHICH, IN THE ABSENCE OF THE WORK IN QUESTION, CANNOT BE PLACED ON THE NETWORK BECAUSE OF THE LIMITED SCOPE OF THE 63 KV GUIDELINES ‘TANAGRO-JUDGMENT’ AND ‘TANAGRO-TITO-POWERED’, WHICH ALSO HAVE THE CONNECTIONS SET OUT IN THE TWO EXISTING LINES, TITO SMISTINGTO-AVIOGLIANO AND TITO SMISTINGTO-TA. (English)
    0 references

    Identifiers

    G83G17000880007
    0 references