Modernisation of 110/15 kV Warszawa station in order to increase security of electricity supply (Q86100): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Changed label, description and/or aliases in pt)
 
(4 intermediate revisions by 2 users not shown)
label / ptlabel / pt
Modernização da estação de 110/15 kV Warszów para aumentar a segurança do fornecimento de eletricidade
Modernização da estação de 110/15 kV de Warszawa, a fim de aumentar a segurança do abastecimento de eletricidade
Property / summary: The project covers the modernisation of the power station of Warszów together with the accompanying infrastructure. The direct objective of the project is to improve the power supply of Świnoujście and the western part of the commune of Międzyzdroje, as well as the reliability of energy supply and increase the energy security of the region, by modernising the 110/15 kV station of Warszów. (English) / qualifier
 
readability score: 0.1362523612049379
Amount0.1362523612049379
Unit1
Property / summaryProperty / summary
O projeto abrange a modernização da central de Warszów, juntamente com a infraestrutura que o acompanha. O objetivo direto do projeto é melhorar o abastecimento de energia da cidade de Świnoujście e da parte ocidental da comuna de Międzyzdroje, bem como a fiabilidade do aprovisionamento energético e aumentar a segurança energética da região, através da modernização da estação de 110/15 kV de Warszów. (Portuguese)
O projeto abrange a modernização da central elétrica de Warszów, juntamente com a infraestrutura que a acompanha. O objetivo direto do projeto é melhorar o aprovisionamento energético de Świnoujście e da parte ocidental do município de Międzyzdroje, bem como a fiabilidade do aprovisionamento energético e aumentar a segurança energética da região, modernizando a estação de 110/15 kV de Warszów. (Portuguese)
Property / coordinate location: 53°49'37.2"N, 14°20'8.5"E / qualifier
 
Property / contained in NUTS: Szczeciński / qualifier
 
Property / contained in Local Administrative Unit
 
Property / contained in Local Administrative Unit: Świnoujście / rank
 
Normal rank
Property / contained in Local Administrative Unit: Świnoujście / qualifier
 

Latest revision as of 06:23, 13 October 2024

Project Q86100 in Poland
Language Label Description Also known as
English
Modernisation of 110/15 kV Warszawa station in order to increase security of electricity supply
Project Q86100 in Poland

    Statements

    0 references
    7,606,289.45 zloty
    0 references
    1,690,878.14 Euro
    13 January 2020
    0 references
    12,540,000.0 zloty
    0 references
    2,787,642.0 Euro
    13 January 2020
    0 references
    60.66 percent
    0 references
    1 January 2020
    0 references
    28 February 2022
    0 references
    ENEA OPERATOR SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references
    0 references

    53°49'37.2"N, 14°20'8.5"E
    0 references
    Projekt obejmuje swoim zakresem modernizację stacji elektroenergetycznej Warszów wraz z infrastrukturą towarzyszącą. Celem bezpośrednim projektu jest poprawa zasilania miasta Świnoujście oraz zachodniej części gminy Międzyzdroje, a także niezawodności dostaw energii i zwiększenie bezpieczeństwa energetycznego regionu, poprzez modernizację stacji 110/15 kV Warszów. (Polish)
    0 references
    The project covers the modernisation of the power station of Warszów together with the accompanying infrastructure. The direct objective of the project is to improve the power supply of Świnoujście and the western part of the commune of Międzyzdroje, as well as the reliability of energy supply and increase the energy security of the region, by modernising the 110/15 kV station of Warszów. (English)
    14 October 2020
    0.1362523612049379
    0 references
    Le projet couvre la modernisation de la centrale de Warszów ainsi que l’infrastructure qui l’accompagne. L’objectif direct du projet est d’améliorer l’alimentation électrique de la ville de Świnoujście et de la partie ouest de la commune Międzyzdroje, ainsi que la fiabilité de l’approvisionnement énergétique et d’accroître la sécurité énergétique de la région, grâce à la modernisation de la station 110/15 kV de Warszów. (French)
    30 November 2021
    0 references
    Das Projekt umfasst die Modernisierung des Kraftwerks Warszów zusammen mit der zugehörigen Infrastruktur. Das direkte Ziel des Projekts ist es, die Stromversorgung der Stadt Świnoujście und des westlichen Teils der Gemeinde Międzyzdroje sowie die Zuverlässigkeit der Energieversorgung und die Erhöhung der Energieversorgungssicherheit der Region durch die Modernisierung der 110/15 kV-Station von Warszów zu verbessern. (German)
    7 December 2021
    0 references
    Het project heeft betrekking op de modernisering van de energiecentrale van Warszów en de bijbehorende infrastructuur. Het directe doel van het project is het verbeteren van de stroomvoorziening van de stad Świnoujście en het westelijke deel van de gemeente Międzyzdroje, evenals de betrouwbaarheid van de energievoorziening en het vergroten van de energiezekerheid van de regio, door de modernisering van het 110/15 kV station van Warszów. (Dutch)
    16 December 2021
    0 references
    Il progetto riguarda l'ammodernamento della centrale elettrica di Varsavia insieme alle infrastrutture di accompagnamento. L'obiettivo diretto del progetto è migliorare l'approvvigionamento energetico della città di Świnoujście e della parte occidentale del comune di Międzyzdroje, nonché l'affidabilità dell'approvvigionamento energetico e aumentare la sicurezza energetica della regione, attraverso l'ammodernamento della stazione 110/15 kV di Varsavia. (Italian)
    16 January 2022
    0 references
    El proyecto cubre la modernización de la central eléctrica de Warszów junto con la infraestructura que lo acompaña. El objetivo directo del proyecto es mejorar el suministro de energía de la ciudad de Świnoujście y la parte occidental de la comuna Międzyzdroje, así como la fiabilidad del suministro de energía y aumentar la seguridad energética de la región, a través de la modernización de la estación 110/15 kV de Warszów. (Spanish)
    19 January 2022
    0 references
    Projekt hõlmab Warszówi elektrijaama moderniseerimist koos sellega kaasneva infrastruktuuriga. Projekti otsene eesmärk on parandada Świnoujście linna ja Międzyzdroje kommuuni lääneosa energiavarustust, samuti energiavarustuse usaldusväärsust ja suurendada piirkonna energiajulgeolekut Warszówi 110/15 kV jaama moderniseerimise kaudu. (Estonian)
    13 August 2022
    0 references
    Projektas apima Warszów elektrinės modernizavimą kartu su atitinkama infrastruktūra. Tiesioginis projekto tikslas – pagerinti Świnoujście miesto ir vakarinės Międzyzdroje komunos dalies elektros tiekimą, taip pat energijos tiekimo patikimumą ir padidinti regiono energetinį saugumą modernizuojant Varšuvo 110/15 kV stotį. (Lithuanian)
    13 August 2022
    0 references
    Projekt obuhvaća modernizaciju elektrane Warszów zajedno s pratećom infrastrukturom. Izravni cilj projekta je poboljšati opskrbu električnom energijom grada Świnoujściea i zapadnog dijela općine Międzyzdroje, kao i pouzdanost opskrbe energijom i povećati energetsku sigurnost regije kroz modernizaciju Warszów stanice 110/15 kV. (Croatian)
    13 August 2022
    0 references
    Το έργο καλύπτει τον εκσυγχρονισμό του σταθμού ηλεκτροπαραγωγής Warszów μαζί με τις συνοδευτικές υποδομές. Ο άμεσος στόχος του έργου είναι η βελτίωση της παροχής ηλεκτρικής ενέργειας στην πόλη και το δυτικό τμήμα της κοινότητας Międzyzdroje, καθώς και η αξιοπιστία του ενεργειακού εφοδιασμού και η αύξηση της ενεργειακής ασφάλειας της περιοχής, μέσω του εκσυγχρονισμού του σταθμού 110/15 kV του Warszów. (Greek)
    13 August 2022
    0 references
    Projekt zahŕňa modernizáciu elektrárne Warszów spolu so sprievodnou infraštruktúrou. Priamym cieľom projektu je zlepšiť zásobovanie energiou mesta Świnoujście a západnej časti obce Międzyzdroje, ako aj spoľahlivosť dodávok energie a zvýšiť energetickú bezpečnosť regiónu modernizáciou 110/15 kV stanice Warszów. (Slovak)
    13 August 2022
    0 references
    Hanke kattaa Warszów-voimalan nykyaikaistamisen ja siihen liittyvän infrastruktuurin. Hankkeen välittömänä tavoitteena on parantaa Świnoujścien kaupungin ja Międzyzdrojen kunnan länsiosan sähkönsyöttöä sekä energian toimitusvarmuutta ja lisätä alueen energiavarmuutta uudistamalla Warszówin 110/15 kV:n asema. (Finnish)
    13 August 2022
    0 references
    A projekt a Warszówi erőmű korszerűsítésére és a kapcsolódó infrastruktúrára terjed ki. A projekt közvetlen célja Świnoujście város és Międzyzdroje település nyugati részének energiaellátásának javítása, valamint az energiaellátás megbízhatóságának javítása és a régió energiabiztonságának növelése Warszów 110/15 kV-os állomásának modernizálásával. (Hungarian)
    13 August 2022
    0 references
    Projekt zahrnuje modernizaci elektrárny Warszów spolu s doprovodnou infrastrukturou. Přímým cílem projektu je zlepšení dodávek energie města Świnoujście a západní části obce Międzyzdroje, jakož i spolehlivost dodávek energie a zvýšení energetické bezpečnosti regionu prostřednictvím modernizace stanice Warszów 110/15 kV. (Czech)
    13 August 2022
    0 references
    Projekts attiecas uz Warszów spēkstacijas modernizāciju kopā ar saistīto infrastruktūru. Projekta tiešais mērķis ir uzlabot Świnoujście pilsētas un Międzyzdroje komūnas rietumu daļas energoapgādi, kā arī energoapgādes uzticamību un palielināt reģiona energoapgādes drošību, modernizējot Warszów staciju 110/15 kV. (Latvian)
    13 August 2022
    0 references
    Clúdaíonn an tionscadal nuachóiriú stáisiún cumhachta Warszów mar aon leis an mbonneagar tionlacain. Is é cuspóir díreach an tionscadail ná feabhas a chur ar sholáthar cumhachta na cathrach i Χwinoujście agus an chuid thiar den chumann Międzyzdroje, chomh maith le hiontaofacht an tsoláthair fuinnimh agus slándáil fuinnimh an réigiúin a mhéadú, tríd an stáisiún 110/15 kV de Warszów a nuachóiriú. (Irish)
    13 August 2022
    0 references
    Projekt zajema posodobitev elektrarne Warszów skupaj s spremljevalno infrastrukturo. Neposredni cilj projekta je izboljšati oskrbo z električno energijo mesta Świnoujście in zahodnega dela občine Międzyzdroje ter zanesljivost oskrbe z energijo in povečati energetsko varnost regije s posodobitvijo postaje 110/15 kV Warszów. (Slovenian)
    13 August 2022
    0 references
    Проектът обхваща модернизацията на електроцентралата Warszów заедно с придружаващата я инфраструктура. Пряката цел на проекта е да се подобри електроснабдяването на град Швиноуйшче и западната част на община Międzyzdroje, както и надеждността на енергийните доставки и да се повиши енергийната сигурност на региона чрез модернизация на 110/15 kV станция Warszów. (Bulgarian)
    13 August 2022
    0 references
    Il-proġett ikopri l-modernizzazzjoni tal-impjant tal-enerġija ta’ Warszów flimkien mal-infrastruttura li takkumpanjah. L-għan dirett tal-proġett huwa li jtejjeb il-provvista tal-enerġija tal-belt ta’ Świnoujście u l-parti tal-Punent tal-komun Międzyzdroje, kif ukoll l-affidabbiltà tal-provvista tal-enerġija u jżid is-sigurtà tal-enerġija tar-reġjun, permezz tal-modernizzazzjoni tal-istazzjon 110/15 kV ta’ Warszów. (Maltese)
    13 August 2022
    0 references
    O projeto abrange a modernização da central elétrica de Warszów, juntamente com a infraestrutura que a acompanha. O objetivo direto do projeto é melhorar o aprovisionamento energético de Świnoujście e da parte ocidental do município de Międzyzdroje, bem como a fiabilidade do aprovisionamento energético e aumentar a segurança energética da região, modernizando a estação de 110/15 kV de Warszów. (Portuguese)
    13 August 2022
    0 references
    Projektet dækker moderniseringen af Warszów-kraftværket sammen med den tilhørende infrastruktur. Det direkte mål med projektet er at forbedre energiforsyningen i byen Świnoujście og den vestlige del af kommunen Międzyzdroje samt pålideligheden af energiforsyningen og øge energisikkerheden i regionen gennem modernisering af 110/15 kV station i Warszów. (Danish)
    13 August 2022
    0 references
    Proiectul acoperă modernizarea centralei electrice Warszów, împreună cu infrastructura aferentă. Obiectivul direct al proiectului este de a îmbunătăți alimentarea cu energie a orașului Świnoujście și partea de vest a comunei Międzyzdroje, precum și fiabilitatea aprovizionării cu energie și creșterea securității energetice a regiunii, prin modernizarea stației de 110/15 kV Warszów. (Romanian)
    13 August 2022
    0 references
    Projektet omfattar modernisering av Warszóws kraftverk tillsammans med tillhörande infrastruktur. Det direkta målet med projektet är att förbättra strömförsörjningen i staden Świnoujście och den västra delen av kommunen Międzyzdroje, samt tillförlitligheten i energiförsörjningen och öka energitryggheten i regionen genom moderniseringen av stationen 110/15 kV i Warszów. (Swedish)
    13 August 2022
    0 references
    WOJ.: ZACHODNIOPOMORSKIE, POW.: Świnoujście
    0 references
    24 May 2023
    0 references

    Identifiers

    POIS.07.01.00-00-0001/19
    0 references