Revision as of 23:24, 27 October 2022

Project Q4419558 in Poland
Language Label Description Also known as
English
Construction of a photovoltaic installation for the needs of MAX-PLON Sp. z o.o.
Project Q4419558 in Poland

    Statements

    0 references
    94,210.23 zloty
    0 references
    20,942.93 Euro
    0 references
    171,291.34 zloty
    0 references
    38,078.06 Euro
    0 references
    55.0 percent
    0 references
    1 August 2022
    0 references
    31 December 2022
    0 references
    MAX-PLON SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references

    50°42'27.97"N, 23°50'55.75"E
    0 references
    Istotą projektu jest budowa instalacji fotowoltaicznej o mocy 49,20 kWp na dachu nieruchomości, w której prowadzona jest działalność gospodarcza wnioskodawcy - budynek produkcyjno-magazynowy w m. Teratyn 130, gmina Uchanie. Cele projektu: a) obniżenie kosztów funkcjonowania firmy; b) zwiększenie bezpieczeństwa energetycznego firmy; c) redukcja zanieczyszczeń emitowanych do środowiska. Powyższe cele zostaną osiągnięte dzięki realizacji zadań: a) budowa instalacji fotowoltaicznej na dachu budynku; b) przeprowadzenie działań informacyjnych. Grupy docelowe, do których skierowany będzie projekt, to: a) mieszkańcy gminy Uchanie - w zakresie korzystania z produktów firmy wnioskodawcy, jak i w zakresie działań informacyjnych; b) dotychczasowi klienci firmy. Opis techniczno-ekonomiczny produktów: system fotowoltaiczny o mocy 49,20 kWp w skład którego wchodzą: moduły fotowoltaiczne (PV) o mocy 410 Wp: 120 szt.; inwertery (falowniki): 2 szt.; system montażowy: 1 kpl.; okablowanie do połączenia modułów; zabezpieczenia DC i AC; układ TIK. Czas realizacji inwestycji: od 01.02.2023 do 30.12.2023. Wskaźniki produktu: 1) Dodatkowa zdolność wytwarzania energii elektrycznej ze źródeł odnawialnych - 0,05 MWe; 2) Liczba przedsiębiorstw otrzymujących wsparcie (CI1) - 1; 3) Liczba wybudowanych jednostek wytwarzania energii z OZE - 1. Wskaźniki rezultatu: 1) Szacowany roczny spadek emisji gazów cieplarnianych (CI34) [tony równoważnika CO2/rok] - 18,21; 2) Produkcja energii elektrycznej z nowo wybudowanych instalacji wykorzystujących OZE [MWhe/rok] - 54,12. (Polish)
    0 references
    The essence of the project is the construction of a photovoltaic installation with a capacity of 49.20 kWp on the roof of the property, in which the applicant’s economic activity is carried out — a production and warehouse building in Teratyn 130, the municipality of Uchanie. Objectives of the project: a) reducing the operating costs of the company; B) increasing the energy security of the company; C) Reduction of pollutants emitted into the environment. The above objectives will be achieved through the implementation of the tasks: the construction of a photovoltaic installation on the roof of the building; B) carry out information activities. The target groups to which the project will be addressed are: a) residents of the municipality of Uchanie — in terms of using the products of the applicant’s company, as well as in the field of information activities; B) existing customers of the company. Technical and economic description of the products: a photovoltaic system with a power of 49.20 kWp consisting of: 410Wp photovoltaic (PV) modules: 120 pcs.; inverters (inverters): 2 pcs.; mounting system: 1 pc.; wiring for connecting modules; DC and AC protections; the ICT system. Time of implementation of the investment: from 01.02.2023 to 30.12.2023. Product indicators: 1) Additional capacity for generating electricity from renewable sources — 0.05 MWe; 2) Number of enterprises receiving support (CI1) — 1; 3) Number of RES power generation units built — 1. Result indicators: 1) Estimated annual decrease in greenhouse gas emissions (CI34) [tonnes of CO2/year] — 18.21; 2) Production of electricity from newly built RES installations [MWhe/year] — 54,12. (English)
    21 October 2022
    0 references
    WOJ.: LUBELSKIE, POW.: hrubieszowski
    0 references
    0 references

    Identifiers

    RPLU.15.01.00-06-0011/22
    0 references