MUNICIPALITY OF TORELLA DEI LOMBARDI (AV) — WORKS TO COMPLETE THE SEWAGE SYSTEM IN THE SERVICE OF THE MUNICIPAL AND MUNICIPAL VILLAGES — 3° LOTTO (Q2023270): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: import item from Italy)
(‎Removed claims)
Property / EU contribution
1,050,032.53 Euro
Amount1,050,032.53 Euro
UnitEuro
 
Property / EU contribution: 1,050,032.53 Euro / rank
Normal rank
 
Property / budget
1,400,043.38 Euro
Amount1,400,043.38 Euro
UnitEuro
 
Property / budget: 1,400,043.38 Euro / rank
Normal rank
 
Property / co-financing rate
75.0 percent
Amount75.0 percent
Unitpercent
 
Property / co-financing rate: 75.0 percent / rank
Normal rank
 

Revision as of 15:39, 12 February 2022

Project Q2023270 in Italy
Language Label Description Also known as
English
MUNICIPALITY OF TORELLA DEI LOMBARDI (AV) — WORKS TO COMPLETE THE SEWAGE SYSTEM IN THE SERVICE OF THE MUNICIPAL AND MUNICIPAL VILLAGES — 3° LOTTO
Project Q2023270 in Italy

    Statements

    0 references
    1 September 2013
    0 references
    30 June 2018
    0 references
    COMUNE DI TORELLA DEI LOMBARDI
    0 references
    0 references

    40°56'22.99"N, 15°6'54.18"E
    0 references
    IL PROGETTO PROPOSTO COSTITUISCE IL 3° LOTTO FUNZIONALE DELL'INTERVENTO DI COSTRUZIONE DELLA RETE FOGNARIA A SERVIZIO DELLE CONTRADE E BORGATE COMUNALI: CON GLI ALTRI DUE LOTTI, PER CARENZA DI COPERTURA FINANZIARIA, FU PREVISTA LA REALIZZAZIONE FUNZIONALE DELL'IMPIANTO DI DEPURAZIONE PER UN NUMERO DI 600 ABITANTI A FRONTE DELLA POPOLAZIONE TOTALE PRESUNTA DI 900 ABITANTI E DI ALTRI TRATTI DI RETE FOGNARIA A SERVIZIO DELLE BORGATE COMUNALI.LE OPERE PREVISTE CON IL PROGETTO PROPOSTO A FINANZIAMENTO CONSENTONO LA REALIZZAZIONE DEI COLLETTORI DI COLLEGAMENTO ALL'ESISTENTE IMPIANTO DI DEPURAZIONE. (Italian)
    0 references
    THE PROPOSED PROJECT IS THE 3ND CONSTITUENT PART OF THE CONSTRUCTION OF THE SEWAGE SYSTEM AT THE SERVICE OF THE DISTRICT AND MUNICIPAL GATE: WITH THE OTHER TWO LOTS, DUE TO A LACK OF FINANCIAL COVER, THE OPERATION OF THE TREATMENT PLANT WAS PROVIDED FOR A NUMBER OF 600 INHABITANTS IN THE FACE OF THE PRESUMED TOTAL POPULATION OF 900 INHABITANTS AND OTHER SEWER SYSTEMS AT THE SERVICE OF THE VILLAGES OF THE PROJECT PROPOSED FOR FINANCING, ALLOWING THE CONNECTIONS TO THE EXISTING WATER TREATMENT PLANT TO BE CARRIED OUT. (English)
    0 references
    LE PROJET PROPOSÉ CONSTITUE LE 3ÈME LOT FONCTIONNEL DE LA CONSTRUCTION DU RÉSEAU D’ASSAINISSEMENT POUR DESSERVIR LES DISTRICTS ET LES VILLAGES MUNICIPAUX: AVEC LES DEUX AUTRES LOTS, EN RAISON D’UN MANQUE DE COUVERTURE FINANCIÈRE, LA STATION D’ÉPURATION DES EAUX USÉES DEVAIT ÊTRE CONSTRUITE POUR 600 HABITANTS, ALORS QUE LA POPULATION TOTALE ESTIMÉE À 900 HABITANTS ET D’AUTRES TRONÇONS D’ASSAINISSEMENT DESSERVAIENT LES VILLAGES COMMUNAUTAIRES.LES TRAVAUX PRÉVUS AVEC LE PROJET PROPOSÉ POUR FINANCER LA CONSTRUCTION DES COLLECTEURS RACCORDÉS À LA STATION D’ÉPURATION EXISTANTE. (French)
    14 December 2021
    0 references
    HET VOORGESTELDE PROJECT VORMT HET 3E FUNCTIONELE PERCEEL VAN DE AANLEG VAN HET RIOLERINGSNETWERK TEN BEHOEVE VAN DE DISTRICTEN EN GEMEENTELIJKE DORPEN: MET DE ANDERE TWEE PERCELEN, WEGENS EEN GEBREK AAN FINANCIËLE DEKKING, WAS DE BOUW VAN DE RIOOLWATERZUIVERINGSINSTALLATIE GEPLAND VOOR 600 INWONERS, VERGELEKEN MET DE GESCHATTE TOTALE BEVOLKING VAN 900 INWONERS EN ANDERE RIOLERINGSSECTIES TEN DIENSTE VAN DE GEMEENSCHAP VILLAGES.THE-WERKZAAMHEDEN GEPLAND IN HET KADER VAN HET VOORGESTELDE PROJECT VOOR DE FINANCIERING VAN DE BOUW VAN DE VERZAMELAARS DIE AANSLUITEN OP DE BESTAANDE ZUIVERINGSINSTALLATIE. (Dutch)
    23 December 2021
    0 references
    DAS VORGESCHLAGENE PROJEKT STELLT DAS DRITTE FUNKTIONALE LOS DES BAUS DES KANALISATIONSNETZES FÜR DIE BEZIRKE UND GEMEINDEN DAR: BEI DEN BEIDEN ANDEREN LOSEN WURDE AUFGRUND DER FEHLENDEN FINANZIELLEN ABDECKUNG DIE KLÄRANLAGE FÜR 600 EINWOHNER GEPLANT, VERGLICHEN MIT DER GESCHÄTZTEN GESAMTBEVÖLKERUNG VON 900 EINWOHNERN UND ANDEREN KANALISATIONSABSCHNITTEN, DIE DIE GEMEINSCHAFT VILLAGES BEDIENEN. (German)
    24 December 2021
    0 references
    EL PROYECTO PROPUESTO CONSTITUYE EL TERCER LOTE FUNCIONAL DE LA CONSTRUCCIÓN DE LA RED DE ALCANTARILLADO PARA ATENDER A LOS DISTRITOS Y PUEBLOS MUNICIPALES: CON LOS OTROS DOS LOTES, DEBIDO A LA FALTA DE COBERTURA FINANCIERA, SE PREVÉ LA CONSTRUCCIÓN DE LA PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES PARA 600 HABITANTES, FRENTE A LA POBLACIÓN TOTAL ESTIMADA DE 900 HABITANTES Y OTROS TRAMOS DE ALCANTARILLADO AL SERVICIO DE LOS VILLAGES COMUNITARIOS. (Spanish)
    24 January 2022
    0 references
    TORELLA DEI LOMBARDI
    0 references

    Identifiers

    B53H15000000009
    0 references