The purpose of this tender is to propose a complex energy modernisation of the Romhány municipality’s building involved in the development. Development proposals aimed at reducing the operating costs of the building and thus of the municipality: — thermal insulation of external walls with a thickness of 15 cm EPS thermal insulation system; — replacement of windows with wooden frames for plastic insulated windows and doors; — thermal insulation of attic floor with 20 cm thickness mineral wool thermal insulation system; — thermal insulation of basement floor with a thickness of 14 cm with mineral wool thermal insulation system; — modernisation of the heating system: O replacement of existing gas boilers for a condensation gas boiler with weather monitoring regulation; — Installation of a solar system with a unit output of 7.5 kWp on the roof of the building. Increasing energy efficiency through energy modernisation would primarily serve the occupants and visitors of the building. However, the environmental impact area of the reduction of energy consumption extends beyond the boundaries of the building and indirectly improves the security and competitiveness of the entire country’s energy supply and serves to preserve the state of the environment. The planned state of all external boundaries of the building affected by the renovation was determined in such a way as to comply with the cost-optimal requirements for heat transmission factors in Decree No 7/2006 of 24 May 2006. Quantified results of the investment made: Result name Quantity Units Reduction of greenhouse gases: estimated annual greenhouse gas reductions of 40,98 CO2 equivalent tonnes Energy efficiency: Reduction in annual primary energy consumption in public buildings 160 324.97 kWh/year Renewable energy sources: The additional capacity of renewable energy production 0.008000 MW of primary energy consumption achieved by energy efficiency improvements is 0,00049590 PJ/year The amount of energy from renewable sources is 0.00003251 PJ/year The energy upgrades/developments covered by this tender comply with the strategic objectives of the Territorial and Urban Development Operational Programme (TOP) to reduce greenhouse gas (GHG) emissions from fossil fuels. The proposed timetable for implementation Activity Date TOP grant agreement concluded on 30.10.2017. Contract with suppliers and contractors 01.09.2018. Start of construction works 01/09/2018 Technical handover/receipt 31/05/2019 Submission of a final payment claim 30/06/2019 Total financial investment cost (ICT) 100 45 000 000 Eligible financial investment cost (ICE) 100 45 000 000 Grant amount (ICE*R) 45 000 000 The operation of the project is to be carried out under the responsibility of the municipality, since after the development operation does not require the involvement of an external resource. (English)
Property / summary: The purpose of this tender is to propose a complex energy modernisation of the Romhány municipality’s building involved in the development. Development proposals aimed at reducing the operating costs of the building and thus of the municipality: — thermal insulation of external walls with a thickness of 15 cm EPS thermal insulation system; — replacement of windows with wooden frames for plastic insulated windows and doors; — thermal insulation of attic floor with 20 cm thickness mineral wool thermal insulation system; — thermal insulation of basement floor with a thickness of 14 cm with mineral wool thermal insulation system; — modernisation of the heating system: O replacement of existing gas boilers for a condensation gas boiler with weather monitoring regulation; — Installation of a solar system with a unit output of 7.5 kWp on the roof of the building. Increasing energy efficiency through energy modernisation would primarily serve the occupants and visitors of the building. However, the environmental impact area of the reduction of energy consumption extends beyond the boundaries of the building and indirectly improves the security and competitiveness of the entire country’s energy supply and serves to preserve the state of the environment. The planned state of all external boundaries of the building affected by the renovation was determined in such a way as to comply with the cost-optimal requirements for heat transmission factors in Decree No 7/2006 of 24 May 2006. Quantified results of the investment made: Result name Quantity Units Reduction of greenhouse gases: estimated annual greenhouse gas reductions of 40,98 CO2 equivalent tonnes Energy efficiency: Reduction in annual primary energy consumption in public buildings 160 324.97 kWh/year Renewable energy sources: The additional capacity of renewable energy production 0.008000 MW of primary energy consumption achieved by energy efficiency improvements is 0,00049590 PJ/year The amount of energy from renewable sources is 0.00003251 PJ/year The energy upgrades/developments covered by this tender comply with the strategic objectives of the Territorial and Urban Development Operational Programme (TOP) to reduce greenhouse gas (GHG) emissions from fossil fuels. The proposed timetable for implementation Activity Date TOP grant agreement concluded on 30.10.2017. Contract with suppliers and contractors 01.09.2018. Start of construction works 01/09/2018 Technical handover/receipt 31/05/2019 Submission of a final payment claim 30/06/2019 Total financial investment cost (ICT) 100 45 000 000 Eligible financial investment cost (ICE) 100 45 000 000 Grant amount (ICE*R) 45 000 000 The operation of the project is to be carried out under the responsibility of the municipality, since after the development operation does not require the involvement of an external resource. (English) / rank
 
Normal rank
Property / summary: The purpose of this tender is to propose a complex energy modernisation of the Romhány municipality’s building involved in the development. Development proposals aimed at reducing the operating costs of the building and thus of the municipality: — thermal insulation of external walls with a thickness of 15 cm EPS thermal insulation system; — replacement of windows with wooden frames for plastic insulated windows and doors; — thermal insulation of attic floor with 20 cm thickness mineral wool thermal insulation system; — thermal insulation of basement floor with a thickness of 14 cm with mineral wool thermal insulation system; — modernisation of the heating system: O replacement of existing gas boilers for a condensation gas boiler with weather monitoring regulation; — Installation of a solar system with a unit output of 7.5 kWp on the roof of the building. Increasing energy efficiency through energy modernisation would primarily serve the occupants and visitors of the building. However, the environmental impact area of the reduction of energy consumption extends beyond the boundaries of the building and indirectly improves the security and competitiveness of the entire country’s energy supply and serves to preserve the state of the environment. The planned state of all external boundaries of the building affected by the renovation was determined in such a way as to comply with the cost-optimal requirements for heat transmission factors in Decree No 7/2006 of 24 May 2006. Quantified results of the investment made: Result name Quantity Units Reduction of greenhouse gases: estimated annual greenhouse gas reductions of 40,98 CO2 equivalent tonnes Energy efficiency: Reduction in annual primary energy consumption in public buildings 160 324.97 kWh/year Renewable energy sources: The additional capacity of renewable energy production 0.008000 MW of primary energy consumption achieved by energy efficiency improvements is 0,00049590 PJ/year The amount of energy from renewable sources is 0.00003251 PJ/year The energy upgrades/developments covered by this tender comply with the strategic objectives of the Territorial and Urban Development Operational Programme (TOP) to reduce greenhouse gas (GHG) emissions from fossil fuels. The proposed timetable for implementation Activity Date TOP grant agreement concluded on 30.10.2017. Contract with suppliers and contractors 01.09.2018. Start of construction works 01/09/2018 Technical handover/receipt 31/05/2019 Submission of a final payment claim 30/06/2019 Total financial investment cost (ICT) 100 45 000 000 Eligible financial investment cost (ICE) 100 45 000 000 Grant amount (ICE*R) 45 000 000 The operation of the project is to be carried out under the responsibility of the municipality, since after the development operation does not require the involvement of an external resource. (English) / qualifier
 
point in time: 9 February 2022
Timestamp+2022-02-09T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:33, 9 February 2022

Project Q3951161 in Hungary
Language Label Description Also known as
English
Energy renovation of a municipal building in the village of Romhány
Project Q3951161 in Hungary

    Statements

    0 references
    124,434.45 Euro
    0.00276521 Euro
    6 December 2021
    0 references
    45,000,000 forint
    0 references
    144,721.355 Euro
    0.0027336256 Euro
    15 December 2021
    0 references
    52,941,176.471 forint
    0 references
    84.999989 percent
    0 references
    1 January 2018
    0 references
    30 June 2019
    0 references
    ROMHÁNY KÖZSÉG ÖNKORMÁNYZATA
    0 references
    0 references

    47°55'2.06"N, 19°14'19.86"E
    0 references
    Jelen pályázat célja, hogy javaslatot tegyen a Romhány település fejlesztésbe bevont épületének komplex energetikai korszerűsítésére. Az épület és ezáltal az önkormányzat üzemeltetési költségeinek csökkentését célzó fejlesztési javaslatok: - külső falak hőszigetelése 15 cm vastagságú EPS hőszigetelő rendszerrel; - fa keretszerkezetű nyílászárók cseréje műanyag hőszigetelt üvegezésű ablakokra és ajtókra; - padlásfödém hőszigetelése 20 cm vastagságú ásványgyapot hőszigetelő rendszerrel; - pincefödém hőszigetelése 14 cm vastagságú ásványgyapot hőszigetelő rendszerrel; - fűtési rendszer korszerűsítése: o meglévő gázkazánok cseréje időjáráskövető szabályozással ellátott kondenzációs gázkazánra; - 7,5 kWp egységteljesítményű napelemes rendszer telepítése az épület tetőszerkezetére. Az energetikai korszerűsítéssel elérhető energiahatékonyság növelés elsősorban az épület használóit, látogatóit szolgálná. Az energiafelhasználás csökkenés környezeti hatásterülete azonban túlmutat az épület határain és közvetve az egész ország energiaellátásának biztonságát és versenyképességét javítja, továbbá a környezeti állapot megőrzését érdemben szolgálja. Az épület valamennyi, a korszerűsítésben érintett külső határoló szerkezetének tervezett állapota úgy került meghatározásra, hogy megfeleljen a 7/2006 (V.24.) TNM rendelet hőátbocsátási tényezőkre vonatkozó költségoptimalizált követelményértékeinek. A megvalósult beruházás számszerűsített eredményei: Eredmény megnevezése Mennyiség Mértékegység Üvegházhatást okozó gázok csökkentése: az üvegházhatású gázok becsült éves csökkenése 40,98 CO2 egyenérték tonnában Energiahatékonyság: A középületek éves primerenergia-fogyasztásának csökkenése 160 324,97 kWh/év Megújuló energiaforrások: A megújulóenergia-termelés további kapacitása 0,008000 MW Energiahatékonysági fejlesztések által elért primer energia felhasználás csökkenés 0,00049590 PJ/év A megújuló energiaforrásból előállított energiamennyiség 0,00003251 PJ/év A jelen pályázat tárgyát képező energetikai korszerűsítések/fejlesztések megfelelnek a Terület- és Településfejlesztési Operatív Program (TOP) stratégiai céljainak, amelyek a fosszilis energiahordozókból származó üvegházhatású gázok (ÜHG) kibocsátásának csökkentését szolgálják. A megvalósítás javasolt ütemezése Tevékenység Dátum TOP támogatási szerződés megkötése 2017.10.30 Beszállítókkal, kivitelezőkkel szerződéskötés 2018.09.01. Építési munkák megkezdése 2018.09.01. Műszaki átadás-átvétel 2019.05.31. Záró kifizetési kérelem benyújtása 2019.06.30. A fejlesztés tervezett pénzügyi keretei Megnevezés % Ft Teljes pénzügyi beruházási költség (ICT) 100 45 000 000 Elszámolható pénzügyi beruházási költség (ICE) 100 45 000 000 A támogatás összege (ICE*R) 45 000 000 A projekt üzemeltetését az önkormányzat saját hatáskörében kívánja megvalósítani, mivel a fejlesztést követően üzemeltetés nem kívánja a külső erőforrás bevonását. (Hungarian)
    0 references
    The purpose of this tender is to propose a complex energy modernisation of the Romhány municipality’s building involved in the development. Development proposals aimed at reducing the operating costs of the building and thus of the municipality: — thermal insulation of external walls with a thickness of 15 cm EPS thermal insulation system; — replacement of windows with wooden frames for plastic insulated windows and doors; — thermal insulation of attic floor with 20 cm thickness mineral wool thermal insulation system; — thermal insulation of basement floor with a thickness of 14 cm with mineral wool thermal insulation system; — modernisation of the heating system: O replacement of existing gas boilers for a condensation gas boiler with weather monitoring regulation; — Installation of a solar system with a unit output of 7.5 kWp on the roof of the building. Increasing energy efficiency through energy modernisation would primarily serve the occupants and visitors of the building. However, the environmental impact area of the reduction of energy consumption extends beyond the boundaries of the building and indirectly improves the security and competitiveness of the entire country’s energy supply and serves to preserve the state of the environment. The planned state of all external boundaries of the building affected by the renovation was determined in such a way as to comply with the cost-optimal requirements for heat transmission factors in Decree No 7/2006 of 24 May 2006. Quantified results of the investment made: Result name Quantity Units Reduction of greenhouse gases: estimated annual greenhouse gas reductions of 40,98 CO2 equivalent tonnes Energy efficiency: Reduction in annual primary energy consumption in public buildings 160 324.97 kWh/year Renewable energy sources: The additional capacity of renewable energy production 0.008000 MW of primary energy consumption achieved by energy efficiency improvements is 0,00049590 PJ/year The amount of energy from renewable sources is 0.00003251 PJ/year The energy upgrades/developments covered by this tender comply with the strategic objectives of the Territorial and Urban Development Operational Programme (TOP) to reduce greenhouse gas (GHG) emissions from fossil fuels. The proposed timetable for implementation Activity Date TOP grant agreement concluded on 30.10.2017. Contract with suppliers and contractors 01.09.2018. Start of construction works 01/09/2018 Technical handover/receipt 31/05/2019 Submission of a final payment claim 30/06/2019 Total financial investment cost (ICT) 100 45 000 000 Eligible financial investment cost (ICE) 100 45 000 000 Grant amount (ICE*R) 45 000 000 The operation of the project is to be carried out under the responsibility of the municipality, since after the development operation does not require the involvement of an external resource. (English)
    9 February 2022
    0 references
    Romhány, Nógrád
    0 references

    Identifiers

    TOP-3.2.1-16-NG1-2017-00012
    0 references