Last year, the company built a 3.888 MW solar cell park (a small photovoltaic power plant) with a loan carried out by Green Plan Energy Kft. Thanks to this investment, the company came into contact with various professionals who knew the profession, who helped to assemble and determine the amount and performance of the solar panels needed. The technical content was compiled by Green Plan Energy Kft, which has a huge experience with photovoltaic systems. The costs of the investment are detailed in the section Costs. The project is not subject to a building permit, since only solar-voltaic development takes place. The construction terc documentation is attached, which outlines the location of the solar panels. The company’s existing solar panel park was built under 3.888 MW, 3395 Demjén 0207/21 for the sole purpose of commercial energy production. This means that the electricity produced by solar panels produces into the electricity supply network (directly to ÉMÁSZ’s network) which buys the production directly from our company. The expansion of the existing solar park, taking into account the existing capacity, is not economical from such a long distance. On this basis, the electricity produced by the solar panel park does not serve the electricity needed for any of the company’s activities, and the amount of energy required for that activity is purchased directly by the company from the electricity supplier. (English) | |||||||||||||||
Property / summary: Last year, the company built a 3.888 MW solar cell park (a small photovoltaic power plant) with a loan carried out by Green Plan Energy Kft. Thanks to this investment, the company came into contact with various professionals who knew the profession, who helped to assemble and determine the amount and performance of the solar panels needed. The technical content was compiled by Green Plan Energy Kft, which has a huge experience with photovoltaic systems. The costs of the investment are detailed in the section Costs. The project is not subject to a building permit, since only solar-voltaic development takes place. The construction terc documentation is attached, which outlines the location of the solar panels. The company’s existing solar panel park was built under 3.888 MW, 3395 Demjén 0207/21 for the sole purpose of commercial energy production. This means that the electricity produced by solar panels produces into the electricity supply network (directly to ÉMÁSZ’s network) which buys the production directly from our company. The expansion of the existing solar park, taking into account the existing capacity, is not economical from such a long distance. On this basis, the electricity produced by the solar panel park does not serve the electricity needed for any of the company’s activities, and the amount of energy required for that activity is purchased directly by the company from the electricity supplier. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: Last year, the company built a 3.888 MW solar cell park (a small photovoltaic power plant) with a loan carried out by Green Plan Energy Kft. Thanks to this investment, the company came into contact with various professionals who knew the profession, who helped to assemble and determine the amount and performance of the solar panels needed. The technical content was compiled by Green Plan Energy Kft, which has a huge experience with photovoltaic systems. The costs of the investment are detailed in the section Costs. The project is not subject to a building permit, since only solar-voltaic development takes place. The construction terc documentation is attached, which outlines the location of the solar panels. The company’s existing solar panel park was built under 3.888 MW, 3395 Demjén 0207/21 for the sole purpose of commercial energy production. This means that the electricity produced by solar panels produces into the electricity supply network (directly to ÉMÁSZ’s network) which buys the production directly from our company. The expansion of the existing solar park, taking into account the existing capacity, is not economical from such a long distance. On this basis, the electricity produced by the solar panel park does not serve the electricity needed for any of the company’s activities, and the amount of energy required for that activity is purchased directly by the company from the electricity supplier. (English) / qualifier | |||||||||||||||
point in time: 8 February 2022
|
Revision as of 22:02, 8 February 2022
Project Q3936167 in Hungary
Language | Label | Description | Also known as |
---|---|---|---|
English | Environmentally friendly electricity supply to Egri Korona Borház Kft. by solar system Demén 0183/8/B |
Project Q3936167 in Hungary |
Statements
3,950,000 forint
0 references
7,181,818.182 forint
0 references
55.0 percent
0 references
2 March 2021
0 references
28 February 2022
0 references
Egri Korona Borház Kereskedelmi és Szolgáltató Korlátolt Felelősségű Társaság
0 references
A vállalkozás az elmúlt évben 3,888 MW teljesítményű napelem parkot (fotovoltaikus kis erőmű) épített hitelből, amelynek a kivitelezését a Green Plan Energy Kft végezte. Ennek a beruházásnak köszönhetően a vállalkozás különböző, a szakmát jól ismerő szakemberekkel került kapcsolatba, akik segítettek összeállítani, illetve meghatározni a szükséges napelemek mennyiségét és teljesítményét. A műszaki tartalom összeállítását a Green Plan Energy Kft végezte, amely óriási tapasztalattal rendelkezik a fotovoltaikus rendszerek tekintetében. A beruházás költségei részletezésre kerültek a költségek pontban. A beruházás nem építési engedély köteles, hiszen kizárólag napelemes fejlesztés történik. Csatolásra kerül az építési tercdokumentáció, amely vázlatosan tartalmazza a napelemek elhelyezkedését. A vállalkozás meglévő napelem parkja 3,888 MW, 3395 Demjén 0207/21 hrsz alatt épült, kizárólag kereskedelmi energiatermelés céllal. Ez azt jelenti, hogy a napelemek által megtermelt elektromos áram az áramszolgáltató hálózatába termel (közvetlenül az ÉMÁSZ hálózatára), mely a megtermelt mennyiséget közvetlenül megvásárolja társaságunktól. A meglevő napelempark bővítése a meglévő kapacitás figyelembevételével ilyen nagy távolságból nem gazdaságos. Ezek alapján, a napelem park által megtermelt elektromos áram nem szolgálja ki a társaság egyetlen tevékenységéhez szükséges elektromos áram szükségletét sem, az ahhoz szükséges energiamennyiséget, a társaság az áramszolgáltatótól közvetlenül megvásárolja. (Hungarian)
0 references
Last year, the company built a 3.888 MW solar cell park (a small photovoltaic power plant) with a loan carried out by Green Plan Energy Kft. Thanks to this investment, the company came into contact with various professionals who knew the profession, who helped to assemble and determine the amount and performance of the solar panels needed. The technical content was compiled by Green Plan Energy Kft, which has a huge experience with photovoltaic systems. The costs of the investment are detailed in the section Costs. The project is not subject to a building permit, since only solar-voltaic development takes place. The construction terc documentation is attached, which outlines the location of the solar panels. The company’s existing solar panel park was built under 3.888 MW, 3395 Demjén 0207/21 for the sole purpose of commercial energy production. This means that the electricity produced by solar panels produces into the electricity supply network (directly to ÉMÁSZ’s network) which buys the production directly from our company. The expansion of the existing solar park, taking into account the existing capacity, is not economical from such a long distance. On this basis, the electricity produced by the solar panel park does not serve the electricity needed for any of the company’s activities, and the amount of energy required for that activity is purchased directly by the company from the electricity supplier. (English)
8 February 2022
0 references
Demjén, Heves
0 references
Identifiers
GINOP-4.1.4-19-2020-03489
0 references