Construction of a photovoltaic power plant by Amper in Jerutki (Q2717159): Difference between revisions
Jump to navigation
Jump to search
(Changed label, description and/or aliases in nl, and other parts: Adding Dutch translations) |
(Changed label, description and/or aliases in it, and other parts: Adding Italian translations) |
||||||||||||||
label / it | label / it | ||||||||||||||
Costruzione di una centrale fotovoltaica da parte di Amper a Jerutki | |||||||||||||||
Property / summary | |||||||||||||||
L'investimento oggetto di questo progetto consiste nella costruzione di una centrale fotovoltaica da 0,999 MW a Jerutki, nello svincolo n. 145, Jerutka. Il progetto ha lo scopo di: 3700 pz di pannelli fotovoltaici policristallini 270 W. I pannelli saranno montati a terra in costruzione di acciaio zincato a caldo o alluminio. Il progetto prevede l'utilizzo di 50 inverter con una potenza di 20 kW, sicurezza, cablaggio e costruzione della stazione Trafo e connessione elettrica. Il progetto si inserisce nel tipo di progetto elencato nel ROP SzOOP WiM 2014-2020 per l'azione 4.1 — impianti che utilizzano energia solare (ad esempio collettori solari, fotovoltaici) — fino a 2 MWe/MWth. Secondo la possibilità descritta in SzOOP, l'impianto servirà a scopi commerciali — l'energia elettrica prodotta sarà venduta al 100 % sul mercato concorrenziale. Ai sensi della legge del 20 febbraio 2015 sulle fonti energetiche rinnovabili (Dz. U. 2015, voce. 478) e articolo 2, paragrafo 2, della legge del 7 giugno 2018 che modifica la legge sulle fonti di energia rinnovabile e alcuni altri atti (Gazzetta delle leggi 2018, voce. 1276.)il permesso di costruzione richiede l'esecuzione di lavori di costruzione consistenti nell'installazione di dispositivi fotovoltaici con una potenza elettrica installata superiore a 50 kW. Pertanto, la ricorrente ha chiesto un permesso di costruzione. I pannelli fotovoltaici utilizzano il fenomeno fotovoltaico per gli inverter, dove c'è un cambio di corrente continua in corrente alternata. Collegati tra loro, formano catene dalle quali l'energia viene trasmessa per mezzo di collegamenti via cavo agli inverter. La centrale elettrica sarà collegata alla rete, ma non sarà necessario installare batterie e regolatori di carica, perché la rete è in grado di assorbire tutta l'energia prodotta dall'impianto fotovoltaico. L'energia elettrica prodotta sarà venduta al 100 % in un mercato competitivo. Il progetto soddisfa tutte le condizioni limite stabilite nel ROP SzOOP WiM 2014-2020. (Italian) | |||||||||||||||
Property / summary: L'investimento oggetto di questo progetto consiste nella costruzione di una centrale fotovoltaica da 0,999 MW a Jerutki, nello svincolo n. 145, Jerutka. Il progetto ha lo scopo di: 3700 pz di pannelli fotovoltaici policristallini 270 W. I pannelli saranno montati a terra in costruzione di acciaio zincato a caldo o alluminio. Il progetto prevede l'utilizzo di 50 inverter con una potenza di 20 kW, sicurezza, cablaggio e costruzione della stazione Trafo e connessione elettrica. Il progetto si inserisce nel tipo di progetto elencato nel ROP SzOOP WiM 2014-2020 per l'azione 4.1 — impianti che utilizzano energia solare (ad esempio collettori solari, fotovoltaici) — fino a 2 MWe/MWth. Secondo la possibilità descritta in SzOOP, l'impianto servirà a scopi commerciali — l'energia elettrica prodotta sarà venduta al 100 % sul mercato concorrenziale. Ai sensi della legge del 20 febbraio 2015 sulle fonti energetiche rinnovabili (Dz. U. 2015, voce. 478) e articolo 2, paragrafo 2, della legge del 7 giugno 2018 che modifica la legge sulle fonti di energia rinnovabile e alcuni altri atti (Gazzetta delle leggi 2018, voce. 1276.)il permesso di costruzione richiede l'esecuzione di lavori di costruzione consistenti nell'installazione di dispositivi fotovoltaici con una potenza elettrica installata superiore a 50 kW. Pertanto, la ricorrente ha chiesto un permesso di costruzione. I pannelli fotovoltaici utilizzano il fenomeno fotovoltaico per gli inverter, dove c'è un cambio di corrente continua in corrente alternata. Collegati tra loro, formano catene dalle quali l'energia viene trasmessa per mezzo di collegamenti via cavo agli inverter. La centrale elettrica sarà collegata alla rete, ma non sarà necessario installare batterie e regolatori di carica, perché la rete è in grado di assorbire tutta l'energia prodotta dall'impianto fotovoltaico. L'energia elettrica prodotta sarà venduta al 100 % in un mercato competitivo. Il progetto soddisfa tutte le condizioni limite stabilite nel ROP SzOOP WiM 2014-2020. (Italian) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: L'investimento oggetto di questo progetto consiste nella costruzione di una centrale fotovoltaica da 0,999 MW a Jerutki, nello svincolo n. 145, Jerutka. Il progetto ha lo scopo di: 3700 pz di pannelli fotovoltaici policristallini 270 W. I pannelli saranno montati a terra in costruzione di acciaio zincato a caldo o alluminio. Il progetto prevede l'utilizzo di 50 inverter con una potenza di 20 kW, sicurezza, cablaggio e costruzione della stazione Trafo e connessione elettrica. Il progetto si inserisce nel tipo di progetto elencato nel ROP SzOOP WiM 2014-2020 per l'azione 4.1 — impianti che utilizzano energia solare (ad esempio collettori solari, fotovoltaici) — fino a 2 MWe/MWth. Secondo la possibilità descritta in SzOOP, l'impianto servirà a scopi commerciali — l'energia elettrica prodotta sarà venduta al 100 % sul mercato concorrenziale. Ai sensi della legge del 20 febbraio 2015 sulle fonti energetiche rinnovabili (Dz. U. 2015, voce. 478) e articolo 2, paragrafo 2, della legge del 7 giugno 2018 che modifica la legge sulle fonti di energia rinnovabile e alcuni altri atti (Gazzetta delle leggi 2018, voce. 1276.)il permesso di costruzione richiede l'esecuzione di lavori di costruzione consistenti nell'installazione di dispositivi fotovoltaici con una potenza elettrica installata superiore a 50 kW. Pertanto, la ricorrente ha chiesto un permesso di costruzione. I pannelli fotovoltaici utilizzano il fenomeno fotovoltaico per gli inverter, dove c'è un cambio di corrente continua in corrente alternata. Collegati tra loro, formano catene dalle quali l'energia viene trasmessa per mezzo di collegamenti via cavo agli inverter. La centrale elettrica sarà collegata alla rete, ma non sarà necessario installare batterie e regolatori di carica, perché la rete è in grado di assorbire tutta l'energia prodotta dall'impianto fotovoltaico. L'energia elettrica prodotta sarà venduta al 100 % in un mercato competitivo. Il progetto soddisfa tutte le condizioni limite stabilite nel ROP SzOOP WiM 2014-2020. (Italian) / qualifier | |||||||||||||||
point in time: 15 January 2022
|
Revision as of 21:54, 15 January 2022
Project Q2717159 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of a photovoltaic power plant by Amper in Jerutki |
Project Q2717159 in Poland |
Statements
2,485,479.66 zloty
0 references
3,106,849.58 zloty
0 references
80.0 percent
0 references
6 April 2020
0 references
30 April 2021
0 references
AMPER SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Inwestycja objęta niniejszym projektem polega na budowie elektrowni fotowoltaicznej o mocy 0,999 MW w miejscowości Jerutki na dz.nr 145, obręb Jerutki. W ramach niniejszego projektu projektuje się: 3700 szt. paneli fotowoltaicznych polikrystalicznych o mocy 270 W. Panele zostaną zamontowane na gruncie na pod konstrukcjach ze stali ocynkowanej ogniowo lub aluminiowych. Projekt zakłada zastosowanie 50 inwerterów o mocy 20 kW, zabezpieczeń, okablowania oraz budowę stacji Trafo i przyłącza elektroenergetycznego. Projekt wpisuje się w typ projektu wymieniony w SzOOP RPO WiM 2014-2020 dla działania 4.1- instalacji wykorzystujących energię słońca (np. kolektory słoneczne, fotowoltaika)-do 2 MWe/MWth. Instalacja zgodnie z możliwością opisaną w SzOOP będzie służyła celom komercyjnym - wyprodukowana energia elektryczna będzie sprzedawana w 100% na rynku konkurencyjnym. Zgodnie ustawą z dnia 20 lutego 2015 r. o odnawialnych źródłach energii (Dz. U. 2015 poz. 478) oraz z art. 2 pkt 2 ustawy z dnia 7 czerwca 2018 r. o zmianie ustawy o odnawialnych źródłach energii oraz niektórych innych ustaw (Dz.U. 2018 poz. 1276.)pozwolenia na budowę wymaga wykonywanie robót budowlanych polegających na montażu urządzeń fotowoltaicznych o zainstalowanej mocy elektrycznej powyżej 50 kW. W związku z tym, wnioskodawca wystąpił z wnioskiem o pozwolenie na budowę. Panele fotowoltaiczne wykorzystują zjawisko fotowoltaiczne do falowników, gdzie następuje zmiana prądu stałego w prąd zmienny. Połączone między sobą tworzą łańcuchy, z których energia przekazywana jest za pomocą połączeń kablowych do falowników. Elektrownia będzie podłączona do sieci, natomiast nie będzie potrzeby instalowania akumulatorów oraz regulatorów ładowania, ponieważ siec jak w stanie przyjąć całą energię wyprodukowaną przez system fotowoltaiczny. Wyprodukowana energia elektryczna będzie sprzedawana w 100% na rynku konkurencyjnym. Projekt spełnia wszystkie warunki brzegowe określone w SzOOP RPO WiM 2014-2020. (Polish)
0 references
The investment covered by this project consists of the construction of a 0.999 MW photovoltaic power plant in Jerutki at junction No 145, Jerutka. This project is designed to: 3700 pcs of 270 W polycrystalline photovoltaic panels. Panels will be mounted on the ground under constructions of hot-dip galvanised steel or aluminium. The project involves the use of 50 inverters with a power of 20 kW, security, wiring and construction of Trafo station and power connection. The project fits into the project type listed in the SzOOP ROP WiM 2014-2020 for action 4.1- installations using solar energy (e.g. solar collectors, photovoltaics) – up to 2 MWe/MWth. According to the possibility described in SzOOP, the installation will serve commercial purposes – the electricity produced will be sold 100 % on the competitive market. Pursuant to the Act of 20 February 2015 on renewable energy sources (Dz. U. 2015, item. 478) and Article 2(2) of the Act of 7 June 2018 amending the Renewable Energy Sources Act and certain other acts (Journal of Laws 2018, item. 1276.)the construction permit requires the execution of construction works consisting of the installation of photovoltaic devices with an installed electrical power exceeding 50 kW. Therefore, the applicant applied for a building permit. Photovoltaic panels use the photovoltaic phenomenon for inverters, where there is a change of DC into alternating current. Connected to each other, they form chains from which energy is transmitted by means of cable connections to inverters. The power plant will be connected to the grid, but there will be no need to install batteries and charge regulators, because the network is able to absorb all the energy produced by the photovoltaic system. The electricity produced will be sold 100 % in a competitive market. The project meets all the boundary conditions laid down in the SzOOP ROP WiM 2014-2020. (English)
8 July 2021
0 references
L’investissement couvert par ce projet consiste en la construction d’une centrale photovoltaïque de 0,999 MW à Jerutki, à la jonction no 145, Jerutka. Ce projet est conçu pour: 3700 pièces de 270 W panneaux photovoltaïques polycristallin. Les panneaux seront montés sur le sol sous des constructions en acier galvanisé à chaud ou en aluminium. Le projet prévoit l’utilisation de 50 onduleurs d’une puissance de 20 kW, la sécurité, le câblage et la construction d’une station Trafo et d’une connexion électrique. Le projet s’inscrit dans le type de projet indiqué dans le SzOOP ROP WiM 2014-2020 pour l’action 4.1 — installations utilisant l’énergie solaire (par exemple capteurs solaires, photovoltaïques) — jusqu’à 2 MWe/MWth. Selon la possibilité décrite dans SzOOP, l’installation servira à des fins commerciales — l’électricité produite sera vendue à 100 % sur le marché concurrentiel. Conformément à la loi du 20 février 2015 sur les sources d’énergie renouvelables (Dz. U. 2015, point. 478) et l’article 2, paragraphe 2, de la loi du 7 juin 2018 modifiant la loi sur les sources d’énergie renouvelables et certaines autres lois (Journal officiel 2018, point. 1276.)le permis de construction exige l’exécution de travaux de construction consistant en l’installation de dispositifs photovoltaïques d’une puissance électrique installée supérieure à 50 kW. Par conséquent, le demandeur a demandé un permis de construire. Les panneaux photovoltaïques utilisent le phénomène photovoltaïque pour les onduleurs, où il y a un changement de courant continu en courant alternatif. Connectés les uns aux autres, ils forment des chaînes à partir desquelles l’énergie est transmise au moyen de connexions par câble aux onduleurs. La centrale électrique sera connectée au réseau, mais il n’y aura pas besoin d’installer des batteries et des régulateurs de charge, car le réseau est capable d’absorber toute l’énergie produite par le système photovoltaïque. L’électricité produite sera vendue à 100 % sur un marché concurrentiel. Le projet répond à toutes les conditions limites fixées dans le SzOOP ROP WiM 2014-2020. (French)
4 December 2021
0 references
Die Investition im Rahmen dieses Projekts besteht in dem Bau eines Photovoltaik-Kraftwerks von 0,999 MW in Jerutki an der Kreuzung Nr. 145, Jerutka. Dieses Projekt hat folgende Ziele: 3700 Stück mit 270 W polykristallinen Photovoltaik-Panels. Platten werden auf dem Boden unter Konstruktionen aus feuerverzinktem Stahl oder Aluminium montiert. Das Projekt umfasst den Einsatz von 50 Wechselrichtern mit einer Leistung von 20 kW, Sicherheit, Verkabelung und Bau von Trafo-Anlagen und Stromanschluss. Das Projekt passt in den im SzOOP ROP WiM 2014-2020 aufgeführten Projekttyp für Aktion 4.1- Anlagen mit Solarenergie (z. B. Solarkollektoren, Photovoltaik) – bis zu 2 MWe/MWth. Nach der in SzOOP beschriebenen Möglichkeit dient die Anlage kommerziellen Zwecken – der erzeugte Strom wird zu 100 % auf dem wettbewerbsorientierten Markt verkauft. Gemäß dem Gesetz vom 20. Februar 2015 über erneuerbare Energiequellen (Dz. U. 2015, Punkt. 478) und Artikel 2 Absatz 2 des Gesetzes vom 7. Juni 2018 zur Änderung des Erneuerbare-Energien-Gesetzes und einiger anderer Rechtsakte (Gesetzblatt 2018, Punkt. 1276.)Die Baugenehmigung erfordert die Ausführung von Bauarbeiten, die aus der Installation von Photovoltaikanlagen mit einer installierten elektrischen Leistung von mehr als 50 kW bestehen. Daher beantragte die Klägerin eine Baugenehmigung. Photovoltaik-Panels nutzen das Photovoltaik-Phänomen für Wechselrichter, bei denen es einen Wechsel von Gleichstrom in Wechselstrom gibt. Miteinander verbunden, bilden sie Ketten, aus denen Energie durch Kabelanschlüsse an Wechselrichter übertragen wird. Das Kraftwerk wird an das Netz angeschlossen, aber es wird keine Notwendigkeit geben, Batterien und Laderegler zu installieren, da das Netz in der Lage ist, die gesamte von der Photovoltaik-Anlage erzeugte Energie zu absorbieren. Der erzeugte Strom wird zu 100 % auf einem wettbewerbsorientierten Markt verkauft. Das Projekt erfüllt alle im SzOOP ROP WiM 2014-2020 festgelegten Randbedingungen. (German)
16 December 2021
0 references
De investering waarop dit project betrekking heeft, bestaat uit de bouw van een fotovoltaïsche elektriciteitscentrale van 0,999 MW in Jerutki op knooppunt 145, Jerutka. Dit project is bedoeld om: 3700 stuks van 270 W polykristallijne fotovoltaïsche panelen. De panelen worden op de grond gemonteerd onder constructies van thermisch verzinkt staal of aluminium. Het project omvat het gebruik van 50 omvormers met een vermogen van 20 kW, beveiliging, bedrading en bouw van Trafo-centrale en stroomaansluiting. Het project past in het projecttype vermeld in de SzOOP ROP WiM 2014-2020 voor actie 4.1- installaties die gebruik maken van zonne-energie (bv. zonnecollectoren, fotovoltaïsche systemen) — tot 2 MWe/MWth. Volgens de in SzOOP beschreven mogelijkheid zal de installatie commerciële doeleinden dienen — de geproduceerde elektriciteit zal 100 % op de concurrerende markt worden verkocht. Overeenkomstig de wet van 20 februari 2015 inzake hernieuwbare energiebronnen (Dz. U. 2015, punt. 478) en artikel 2, lid 2, van de wet van 7 juni 2018 tot wijziging van de wet inzake hernieuwbare energiebronnen en bepaalde andere wetten (Staatsblad 2018, punt. 1276.)de bouwvergunning vereist de uitvoering van bouwwerken bestaande uit de installatie van fotovoltaïsche apparaten met een geïnstalleerd elektrisch vermogen van meer dan 50 kW. Daarom heeft verzoekster een bouwvergunning aangevraagd. Fotovoltaïsche panelen gebruiken het fotovoltaïsche fenomeen voor omvormers, waar een verandering van DC in wisselstroom plaatsvindt. Verbonden met elkaar vormen ze ketens waaruit energie wordt overgebracht door middel van kabelverbindingen naar omvormers. De centrale zal op het net worden aangesloten, maar er is geen noodzaak om batterijen en laadregelaars te installeren, omdat het netwerk in staat is om alle door het fotovoltaïsche systeem geproduceerde energie te absorberen. De geproduceerde elektriciteit zal voor 100 % worden verkocht op een concurrerende markt. Het project voldoet aan alle voorwaarden van de SzOOP ROP WiM 2014-2020. (Dutch)
18 December 2021
0 references
L'investimento oggetto di questo progetto consiste nella costruzione di una centrale fotovoltaica da 0,999 MW a Jerutki, nello svincolo n. 145, Jerutka. Il progetto ha lo scopo di: 3700 pz di pannelli fotovoltaici policristallini 270 W. I pannelli saranno montati a terra in costruzione di acciaio zincato a caldo o alluminio. Il progetto prevede l'utilizzo di 50 inverter con una potenza di 20 kW, sicurezza, cablaggio e costruzione della stazione Trafo e connessione elettrica. Il progetto si inserisce nel tipo di progetto elencato nel ROP SzOOP WiM 2014-2020 per l'azione 4.1 — impianti che utilizzano energia solare (ad esempio collettori solari, fotovoltaici) — fino a 2 MWe/MWth. Secondo la possibilità descritta in SzOOP, l'impianto servirà a scopi commerciali — l'energia elettrica prodotta sarà venduta al 100 % sul mercato concorrenziale. Ai sensi della legge del 20 febbraio 2015 sulle fonti energetiche rinnovabili (Dz. U. 2015, voce. 478) e articolo 2, paragrafo 2, della legge del 7 giugno 2018 che modifica la legge sulle fonti di energia rinnovabile e alcuni altri atti (Gazzetta delle leggi 2018, voce. 1276.)il permesso di costruzione richiede l'esecuzione di lavori di costruzione consistenti nell'installazione di dispositivi fotovoltaici con una potenza elettrica installata superiore a 50 kW. Pertanto, la ricorrente ha chiesto un permesso di costruzione. I pannelli fotovoltaici utilizzano il fenomeno fotovoltaico per gli inverter, dove c'è un cambio di corrente continua in corrente alternata. Collegati tra loro, formano catene dalle quali l'energia viene trasmessa per mezzo di collegamenti via cavo agli inverter. La centrale elettrica sarà collegata alla rete, ma non sarà necessario installare batterie e regolatori di carica, perché la rete è in grado di assorbire tutta l'energia prodotta dall'impianto fotovoltaico. L'energia elettrica prodotta sarà venduta al 100 % in un mercato competitivo. Il progetto soddisfa tutte le condizioni limite stabilite nel ROP SzOOP WiM 2014-2020. (Italian)
15 January 2022
0 references
Identifiers
RPWM.04.01.00-28-0049/18
0 references