Reconstruction of the regional road No 109 on the Trzebudowa — Trzebine section (Q138028): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Created claim: summary (P836): The subject of the investment is the reconstruction and development of provincial road No 109 with the transition from m. Nwielice at a length of 2 723 m. this is a road with the parameters of the ‘G’ main road. The road is marked at km 6 + 396,38 and the end of the 9 + 119,75 peak. The start of a development linked to the drainage of the road is located at km 6 + 300. The route takes place in the direction of the city of Trzebiles by the cultiv...)
Property / summary
 
The subject of the investment is the reconstruction and development of provincial road No 109 with the transition from m. Nwielice at a length of 2 723 m. this is a road with the parameters of the ‘G’ main road. The road is marked at km 6 + 396,38 and the end of the 9 + 119,75 peak. The start of a development linked to the drainage of the road is located at km 6 + 300. The route takes place in the direction of the city of Trzebiles by the cultivated area and by the village of Noglice. The scope of the road works shall include the following: the corrective (local) milling of the pavement, the extension of the existing pavement, the equalisation of the existing subconstruction of the pavement, the execution of the layer binding, execution of the wall with the SMA, the execution of a new complete pavement structure on the dismantled sections, the renovation of the existing bicycle cycle and the local alterations, construction and reconstruction of pedestrian areas. In addition, the investment in its scope includes: construction of traffic calming elements (pedestrian crossings in the form of azines, islets of traffic on flights to the town), reconstruction of existing bus bays, upgrading of existing traffic, a partial demolition of the existing road (in the areas of breakthroughs, in the area of level crossing, the construction of a bridge over the river Sarni, construction of a storm water sewage system (sewage system and purification plant), construction of a storm-water system (gas, electrician), re-construction of the existing water column, construction of storm water drainage, felling of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing (English)
Property / summary: The subject of the investment is the reconstruction and development of provincial road No 109 with the transition from m. Nwielice at a length of 2 723 m. this is a road with the parameters of the ‘G’ main road. The road is marked at km 6 + 396,38 and the end of the 9 + 119,75 peak. The start of a development linked to the drainage of the road is located at km 6 + 300. The route takes place in the direction of the city of Trzebiles by the cultivated area and by the village of Noglice. The scope of the road works shall include the following: the corrective (local) milling of the pavement, the extension of the existing pavement, the equalisation of the existing subconstruction of the pavement, the execution of the layer binding, execution of the wall with the SMA, the execution of a new complete pavement structure on the dismantled sections, the renovation of the existing bicycle cycle and the local alterations, construction and reconstruction of pedestrian areas. In addition, the investment in its scope includes: construction of traffic calming elements (pedestrian crossings in the form of azines, islets of traffic on flights to the town), reconstruction of existing bus bays, upgrading of existing traffic, a partial demolition of the existing road (in the areas of breakthroughs, in the area of level crossing, the construction of a bridge over the river Sarni, construction of a storm water sewage system (sewage system and purification plant), construction of a storm-water system (gas, electrician), re-construction of the existing water column, construction of storm water drainage, felling of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing (English) / rank
 
Normal rank

Revision as of 21:29, 10 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Reconstruction of the regional road No 109 on the Trzebudowa — Trzebine section
Project in Poland financed by DG Regio

    Statements

    0 references
    8,133,184.17 zloty
    0 references
    1,951,964.2008 Euro
    13 January 2020
    0 references
    8,163,178.79 zloty
    0 references
    1,959,162.9096 Euro
    13 January 2020
    0 references
    100.0 percent
    0 references
    12 February 2016
    0 references
    31 December 2017
    0 references
    WOJEWÓDZTWO ZACHODNIOPOMORSKIE
    0 references
    Przedmiotem inwestycji jest przebudowa i rozbudowa drogi wojewódzkiej nr 109 wraz z przejściem przez m. Nowielice na długości 2723 m. Jest to droga o parametrach drogi głównej "G". Początek przebudowy drogi znajduje się w km 6+396,38, natomiast koniec w pikiecie 9+119,75. Początek opracowania związany z odwodnieniem drogi zlokalizowany jest w km 6+300. Trasa przebiega w kierunku miasta Trzebiatów przez tereny uprawne oraz przez miejscowość Nowielice. Zakres robót nawierzchniowych obejmuje: korekcyjne (miejscowe) frezowanie nawierzchni, wykonanie poszerzeń istniejącej nawierzchni, wyrównanie istniejącej podbudowy masą bitumiczną, wykonanie warstwy wiążącej, wykonanie warstwy ścieralnej z SMA, wykonanie nowej pełnej konstrukcji nawierzchni na odcinkach rozbieranych, remont istniejącego ciągu rowerowego oraz lokalnie przebudowę, budowę i przebudowę ciągów pieszych. Ponadto niniejsza inwestycja swoim zakresem obejmuje: budowę elementów uspokojenia ruchu (przejścia dla pieszych w formie azyli, wysepki kanalizujące ruch na wlotach do miejscowości), przebudowę zatok autobusowych, przebudowę istniejących zjazdów, częściową rozbiórkę istniejącej jezdni (w miejscach przełomów, w rejonie przejazdu kolejowego, pod wykonanie odcinka kanalizacji w rejonie przejazdu kolejowego), rozbiórkę istniejącej kładki pieszo-rowerowej, przebudowę mostu na rzece Sarni polegająca na poszerzeniu mostu pod ciąg pieszo-rowerowy, budowę systemu odprowadzania ścieków opadowych (kanalizacja deszczowa oraz urządzenia oczyszczające), likwidację kolizji z sieciami uzbrojenia terenu (gaz, elektryka), przestawienie istniejącego słupa oświetleniowego, budowę kanalizacji deszczowej, wycinkę kolidujących drzew oraz krzewów, przebudowę istniejącego przepustu, wykonanie przepustów pod zjazdami, oczyszczenie istniejącego przepustu, regulacja istniejących rowów odwadniających, wykonanie oznakowania poziomego i pionowego. (Polish)
    0 references
    The subject of the investment is the reconstruction and development of provincial road No 109 with the transition from m. Nwielice at a length of 2 723 m. this is a road with the parameters of the ‘G’ main road. The road is marked at km 6 + 396,38 and the end of the 9 + 119,75 peak. The start of a development linked to the drainage of the road is located at km 6 + 300. The route takes place in the direction of the city of Trzebiles by the cultivated area and by the village of Noglice. The scope of the road works shall include the following: the corrective (local) milling of the pavement, the extension of the existing pavement, the equalisation of the existing subconstruction of the pavement, the execution of the layer binding, execution of the wall with the SMA, the execution of a new complete pavement structure on the dismantled sections, the renovation of the existing bicycle cycle and the local alterations, construction and reconstruction of pedestrian areas. In addition, the investment in its scope includes: construction of traffic calming elements (pedestrian crossings in the form of azines, islets of traffic on flights to the town), reconstruction of existing bus bays, upgrading of existing traffic, a partial demolition of the existing road (in the areas of breakthroughs, in the area of level crossing, the construction of a bridge over the river Sarni, construction of a storm water sewage system (sewage system and purification plant), construction of a storm-water system (gas, electrician), re-construction of the existing water column, construction of storm water drainage, felling of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing culverts, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing drainage ditches, cleaning of existing (English)
    0 references

    Identifiers

    RPZP.05.01.00-32-0002/16
    0 references